2009/11/24 City Council Resolution 2009-125RESOLUTION NO. 2009 -125
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROHNERT PARK
APPROVING CONTRACT CHANGE ORDER #9 FOR $67,151.00 WITH GHILOTTI.
CONSTRUCTION CO. FOR THE CITY CENTER PLAZA PROJECT
CITY PROJECT NO. 2006-02
WHEREAS, the City approved a construction contract with Ghilotti Construction Co. on
September 8, 2008;
WHEREAS, changes to the construction contract are needed to best implement the goals
of the project.
NOWJHEREFORE, be it resolved by the City Council of the City of Rohnert Park
that Contract Change Order #9 with Ghilotti Construction Co. is approved for an amount of
$67,151.00, and
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to execute
the Contract Change Order.
. DULY AND REGULARLY ADOPTED by the City Council of the City of Rohnert
Park this 24th day of November, 2009.
ATTEST:
ig
CITY OF ROHNERT PARK
OON\L� - �) � NMI
Mayor
LIPp
BELFORTE: AYE CALLINAN: AYE MACKENZIE: AYE STAFFORD: AYE BREEZE: AYE
AYES: (5) NOES: (0) ABSENT: (0) ABSTAIN: (0)
CONTRACT CHANGE ORDER NO. 0009
Final Change Order
1400 Neotomas Avenue Phone: 707.588.2244
Santa Rosa, CA 95405 Fax: 707.588.2274
Email: ichunq(@7rpcity.orct PROJECT No: 2006 -02 DATE:. 11.06.09
City of Rohnert Park City Center Plaza and Drive Improvements
TO: Ghilotti Construction
You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not
included in_the plans and specifications of this contract. All new work herein described shall be done in accordance with the applicable
provisions of the plans and specifications, except as modified by this contract change order. NOTE: This change order is valid when
signed on behalf of the Owner.
DESCRIPTION OF CHANGE:
The amount difference between CCO# 3 -7 and Ghilotti CO #1 -5 $ 469
The amount withheld on CCO #8 $ 17,939
Expansive soil removal balance of unpaid quantity 523CY @ $25 /CY $ 13,075
Seat wall quantity $ 17,440
Ghilotti CO #14 Relocate Hydrant $ 6,264
Ghilotti CO #16 Mow Bands $ 11,964
Change order amount $ 67,151
Upon execution of this change order, Ghilotti agrees to all final cost adjustments associated with the project and shall waive
any and all claims against the City of Rohnert Park and will indemnify and hold the City of Rohnert Park harmless against
all subcontractors, any tier subcontractors and any and all suppliers.
Except as amended by this Contract Change Order, the Contract shall remain in full force and effect.
CONTRACT TIME ADJUSTMENT: 0 Days COST OF CHANGE: $ 67,151
The adjustments to the Contract Price and Contract Time in this Change Order include all costs, including direct, indirect, consequential,
and overhead (field and home office) costs, related to the Change described above. By signing this Change Order, Contractor agrees to
accept the adjustment to the Contract Price, calculated as provided above, and the adjustment of the Contract Time, as payment in full for
all costs, including direct, indirect, consequential, and overhead (field and home office) costs, related to the Changes described above.
Approv com ended by: City of Rohnert Park
John Chung Project Manager Date
Appr7Ghilotti Construction Approved By: City of Rohnert Park
Da e Darrin Jenkins City Engineer Date
ATTEST City Clerk Daniel Schwarz, Interim City Manager. Date
Per Resolution No. 2008 -141. adopted by the Rohnert Park City Council at its meeting of 9/8/08.
File No: 18 -2107
Contract Change Order #9 — Final Change Order