2011/01/11 City Council Resolution 2011-01RESOLUTION NO. 2011- 01
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROHNERT PARK
AUTHORIZING AND APPROVING TASK ORDER NO. 2011-01 WITH
WINZLER & KELLY, INC. FOR PROFESSIONAL SERVICES FOR
ENVIRONMENTAL CLEANUP OF CORPORATION YARD (600 Enterprise Drive)
WHEREAS, in 1989, the City removed a leaking Underground Storage Tank (UST) containing
diesel and gasoline at the Corporation Yard located at 600 Enterprise Drive;
WHEREAS, on January 10, 2003, the City approved a letter proposal with Winzler & Kelly, Inc.
to investigate the site;
WHEREAS, on October 28, 2003, the City Council adopted Resolution No. 2003 -260
authorizing Amendment #1 to the letter proposal and provided for environmental cleanup and site
remediation activities in accordance with County of Sonoma requirements;
WHEREAS, on September 14, 2004, the City Council approved Resolution No. 2004 -244
authorizing Winzler & Kelly Task Order No. 2004 -16 and provided for the destruction of wells;
groundwater monitoring, sampling and reporting; water characterization and disposal; and preparation of
State Fund reimbursement package for submittal;
WHEREAS, Resolution No. 2006 -87 was adopted by the City Council on March 28, 2006,
authorizing Task Order No. 2006 -04 with Winzler & Kelly to conduct soils investigations and prepare a
Corrective Action Plan and Remedial Action Plan;
WHEREAS, the City Council adopted Resolution No. 2007 -185 on November 17, 2007,
authorizing Winzler & Kelly Task Order No. 2007 -09 for additional professional services, specifically
soil investigation and performance of compliance groundwater sampling required by the Sonoma County
Department of Health Services and the North Coast Regional Water Quality Board;
WHEREAS, Winzler & Kelly Task Order No. 2009 -02 was authorized by the City Manager per
RPMC Chapter 3.04; Purchasing Program on September 25, 2009, for continued cleanup and
reimbursement work;
WHEREAS, the City now requires additional professional services to achieve site closure and to
prepare the State Fund reimbursement package for submittal; and
WHEREAS, Winzler & Kelly, Inc. is qualified to perform such work.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Rohnert Park
that it does hereby authorize and approve Task Order No. 2011 -01 by and between Winzler & Kelly, Inc.,
a California Corporation, and the City of Rohnert Park, a municipal corporation, for professional services
for the environmental cleanup of the Corporation Yard for an amount not to exceed $192,121.
BE IT FURTHER RESOLVED that the City Manager is hereby authorized and directed to
execute this Task Order in substantially similar form to the attached Task Order for and on behalf of the
City of Rohnert Park.
DULY AND REGULARLY ADOPTED this 11 th day of January, 2011.
CITY OF ROHNERT PARK
Mayor
JH- S:05 -f
AHANOTU: AYE CALLINAN: AYE MACKENZIE: AYE STAFFORD: AYE BELFORTE: AYE
AYES: (5) NOES: (0) ABSENT: (0) ABSTAIN: (0)
WINZLER & KELLY TASK ORDER NO. 2011-01
CITY OF ROHNERT PARK
AND
WINZLER & KELLY, INC.
AGREEMENT TO PROVIDE PROFESSIONAL SERVICES FOR
ENVIRONMENTAL CLEANUP OF CORPORATION YARD:
SOIL INVESTIGATION AND PERFORMANCE OF COMPLIANCE GROUNDWATER SAMPLING
SECTION 1 — PURPOSE
The purpose of this Task Order is to authorize and direct Winzler & Kelly, Inc. to proceed with the work
specified in Section 2 below in accordance with the provisions of the MASTER AGREEMENT between
the City of Rohnert Park ( "City ") and Winzler. & Kelly, Inc. ( "Consultant ") hereto dated June 25, 2006.
SECTION 2 — SCOPE OF WORK
The items authorized by this Task Order are presented in Attachment "A "- Scope of Services.
SECTION 3 — COMPENSATION AND PAYMENT
Compensation shall be as provided in the MASTER AGREEMENT between the parties hereto referenced
in SECTION 1 above. The total cost for services as set forth in SECTION 2 shall be actual costs (time
and materials) based on Consultants' standard labor charges in accordance with the provisions of the
MASTER AGREEMENT and as shown in Attachment "B" for an amount not -to- exceed $192,121.00.
SECTION 4 — TIME OF PERFORMANCE
The work described in SECTION 2 shall be completed by January 2012, or as extended by the City
Manager.
SECTION 5 — ITEMS AND CONDITIONS
All items and conditions contained in the MASTER AGREEMENT for professional services between
City and Consultant are incorporated by reference.
Approved this day of
CITY OF ROHNERT PARK
Gabriel Gonzalez, City Manager (Date)
Per Resolution No. 2011- adopted by the Rohnert Park
City Council at its meeting of January 11, 2011.
2011
ATTACHMENT" A "
TASK ORDER NO. 2011-01
SCOPE OF SERVICES
ENVIRONMENTAL CLEANUP OF CORPORATION YARD: SOIL INVESTIGATION AND
PERFORMANCE OF COMPLIANCE GROUNDWATER SAMPLING.
1. General Description and Background
The items authorized by this Task Order are to conduct required routine groundwater monitoring
and sampling activities associated with the former underground storage tank (UST) that was located
in the City of Rohnert Park's (City's) Corporation Yard located at 600 Enterprise Drive. This work
is required by the Sonoma County Department of Health Services, Environmental Health Division
(SCDHS -EHD) and the North Coast Regional Water Quality Control Board (NCRWQCB) and an
annual budget is required by the State UST Cleanup Fund ( USTCF), for which the City is being
reimbursed for costs associated with the environmental cleanup.
The work performed for this Task Order will keep the City in compliance with the SCDHS -EHD
and the NCRWQCB. An additional subsurface investigation and remedial pilot testing for site
cleanup is included. The estimated cost for this work is $192,121 and is reimbursable from the
USTCF except for the claim preparation, which has a limit of $3,000 per site.
2. Project Tasks
The Scope of Services to stay in compliance and enabling the City to proceed with the
environmental cleanup of the Corporation Yard site is presented below.
Task 1— Quarterly Groundwater Monitoring and Sampling Events
Perform five (5) groundwater monitoring and sampling events (4th quarter 2010 through 4th quarter
2011) for up`to nine (9) monitoring wells annually and up to six (6) monitoring wells quarterly.
Task includes collecting field measurements for pH, temperature, conductivity, dissolved oxygen,
and oxidation reduction potential prior to purging and sampling the wells for the purpose of
evaluating aerobic degradation activity. Task also includes sampling.and profiling the purge water
for disposal from the site.
Task 2 — Prepare Annual Report
Prepare two (2) annual monitoring and sampling reports 2010 and 2011 to summarize groundwater
monitoring and sampling. This will include potentiometric maps, iso- concentration maps,
groundwater contaminant trend graphs, conclusions, recommendations, and planned site activities.
. Task 3 — Prepare Quarterly Monitoring Reports
Prepare three (3) groundwater monitoring and sampling reports for the 1 st through 3rd quarters of
2011. Quarterly monitoring reports will summarize the analytical data, include a contour map, a
contaminant TPH- GBenzene/MTBE concentration map, conclusions, and planned site activities.
02056 -10 1 Attachment "A"
Task Order No. 2011 -01
Task 4 — Drilling Pre - Field, Permitting, USA Marking, and Coordination
Mark site as required by Underground Services Alert (USA) North, make required notifications to .
USA, SCDHS -EHD, and the City. Prepare drilling permits and pay fees. Coordinate with a drilling
company to install one (1) shallow monitoring/remediation well, and up to three (3) direct push soil
borings inside the corporation yard shop building. A limited access drilling rig will be used.
Task 5 — Drill and Install One Monitoring/Remediation Well and Three Soil Borings
Install one 44nch monitoring /remediation well and up to three soil borings. Borings to be
continuously cored and lithology logged and field screened for contaminants. Retain up to twelve
(12) soil and four (4) groundwater samples to be delivered to the analytical laboratory for testing.
Collect insitu groundwater samples from the three borings using a HydroPunch device. Retain
surface and smear soil samples for analytical testing. As directed by the SCDHS -EHD, one
saturated soil sample in at the depth of 17 feet bgs in one boring will be collected and submitted for
analysis. Develop the monitoring/remediation well and contain all waste generated from the drilling
activities in DOT approved drums, label and profile for disposal. Complete a well head elevation
survey of the top of casing (TOC) of the new well and the locations of the borings.
Task 6 — Additional Subsurface Investigation Report
Prepare a technical report describing the field activities and findings of this investigation. The report
will include a summary of findings including analytical data, dissolved concentration and soil
concentration maps, potentiometric map, survey data, conclusions, and recommendations. Upload .
site data to GeoTracker as required.
Task 7 - Prepare and Conduct a HVDPE Pilot Test
Prepare a workplan and submit to the SCDHS -EHD for approval. Conduct a Pilot Test using
HVDPE based on the observed petroleum concentrations in MW -5 and north of the former UST pit.
The proposed monitoring /remediation well inside the shop building will be included in the Pilot
Testing. Winzler & Kelly anticipates conducting a 30 -day high- vacuum dual -phase extraction
(HVDPE) pilot test event at the site. The Pilot Test will be performed in two 15 -day HVDPE events
(30 days total). The second event will be scheduled if the initial pilot test data proves to be
effective. Concentration trends and mass removal rates will be monitored. The Pilot Test event will
be evaluated to estimate long -term results for this option. Other parameters will be assessed such as
extraction well flow rate that can be sustained, projected mass removal rates, review dissolved
concentration trends, and prepare recommendations. Assume 30 days of extraction and 50,000
gallons of water to contain, treat and discharge to the sanitary sewer system.
Task 8 — HVDPE Pilot Test Report
After the completion of the initial HVDPE Pilot Test event, a Pilot Test report will be prepared
based on the two 15 -day HVDPE events. The report will summarize the data, compare initial and
ending dissolved groundwater concentrations and trends, estimate radius of influence and mass
removed, projections to reach cleanup goals, and recommendations for remedial options for site
cleanup. Winzler & Kelly will evaluate the effectiveness for possible additional events. If an
additional HVDPE event is not conducted, prepare the evaluation report with initial data only.
02056 -10 2 Attachment "A"
Task Order No. 2011 -01
Task 9 — Quarterly Groundwater (Purge Water) Disposal
Profile and coordinate the disposal of the quarterly purge water generated from the five (5)
monitoring and sampling events. One event for 2010 and two events for 2011 are planned to off
haul and dispose of the purge water. Winzler & Kelly will meet with the disposal company on site
during pickup.
Task 10 — Prepare State UST Cleanup Fund Reimbursement Numbers 10 and 11
Winzler & Kelly will prepare and submit the USTCF reimbursement request numbers 10 and 11 for
the corrective actions conducted at the site. Winzler & Kelly will need the assistance of the City in
providing the necessary backup and cancelled checks that are required. Additional. reimbursements
will be prepared (if directed) for similar costs.
3. Schedule
The anticipated schedule is shown in the table below. This schedule is dependent upon receiving
timely lead agency approval on environmental submittals:
Task
Start
Complete
Notice to Proceed
January 2010
1
Quarterly Groundwater Sampling
December 2010
December 2011
2
Quarterly Monitoring Reports
January 2011
January 2012
3
Annual Reports (Two Reports)
January 2011
January 2012
4
Drilling Pre -Field and Permitting
February 2011
February 2011
5
Install One Well and Three Borings
February 2011
February 2011
6
Prepare Additional Subsurface Report
February 2011
April 2011
7
Conduct HVDPE Pilot Test
April 2011
May 2011
8
Prepare HVDPE Pilot Test Report
May 2011
June 2011
9
Quarterly Groundwater Disposal
December 2010
December 2011
10
State USTCF Reimbursement .
March 2011
January 2012
4.
Fee
The work described above will be completed on a time and materials basis for a not -to- exceed
budget of $192,121. Direct costs are to cover project expenses including office consumables and
expenses. Using CalClean provides the City with a special contracted benefit that they will defer
their payment until the USTCF payment has been received the City. In essence there is no out of
pocket money for CalClean's portion of work. The estimated costs associated with performing each
task are summarized in Exhibit `B" — Fee Schedule and Estimating Sheets. Any additional services
not included in this Scope of Services will be performed only after receiving written authorization
from the City and a corresponding budget augmentation.
02056 -10 3 Attachment "A"
Task Order No. 2011 -01
Attachment "B"
WINZLER(Sx-KEELY
FEE SCHEDULE - CENTRAL CALIFORNIA
(Effective February 2009)
Hourly Rates(*)
Principal
$ 180 -250
Senior Project Engineer
130 -250
Project Engineer
100 -170
Staff Engineer
60 -145
Senior Project Scientist
120 -190
Project Scientist
95 -135
Staff Scientist
70 -105
Senior Planner
110 -190
Staff Planner
80 -120
3- Person Survey Crew
255 -390
2- Person Survey Crew
170 -270
1- Person Survey Crew
85 -175
Construction Manager
120 -185
Construction Inspector
85 -115
Professional Land Surveyor
145 -160
Staff Surveyor /LSIT
95 -115
Technician
75 -145
Designer
85 -150
CADD
80 -135
Project Administrator
70 -150
Word Processor & Clerical Support
45 -100
Employee time will be billed in accordance with the fees listed above. These rates are subject to
change on a semi - annual basis. For other than professional employees, time spent over 8 hours
per day, time spent on swing shifts, and time spent on Saturdays will be charged at 1.5 times the
hourly billing rate. Work on Sundays will be charged at 2.0 times the hourly billing rate and holiday
work will be charged at 2.5 times the hourly billing rate. All field personnel charges are portal to
portal. Professional employees will not be charged out at premium charge rates for overtime work.
Expenses and other similar project related costs are billed out at cost plus 15 %. The cost of using
equipment and specialized supplies is billed on the basis of employee hours dedicated to projects. Our
rates are:
A. Office consumables $6.00 /hr
B. Environmental Dept/Construction Inspector consumables $11.00 /hr
C. Survey Field consumables $14.00 /hr
D. Various Environmental, Construction and Land Surveying Equipment At market
Payment for work and expenses is due and payable upon receipt of our invoice. Amounts unpaid thirty
(30) days after the issue date of our invoice shall be assessed a service charge of one and one half (1.5)
percent per month.
(•� These rates do not apply to forensic - related services, or to work for which Prevailing Wage obligations
exist It is the responsibility of the client to notify Winzler & Kelly in writing if Prevailing Wage obligations
are applicable, in which case the fees will be adjusted proportionate to the increase in labor cost.
Central CA Fee Schedule Feb 2009
1 Attachment "B"
Task Order No. 2011 -01
WINZLER &-KELLY Attachment B
SUMMARY
COST ESTIMATING SHEET (UST FUND RATES)
PROJECT NAME: City of Rohnert Park Corporation Yard
Project Phase Description: Quarterly M &S and RAP Implementation 4rd (Qtr 2010 -4th Qtr 2011)
PROJECT NUMBER: 2056- 10 -OOXX PROJECT MANAGER: David J. Vossler
Prepared by: David J. Vossler Reviewed By:
Date: December 10, 2010 Review Date:
TASK / UNIT
W &K LABOR
EXPENSES
TOTAL COST
1) Quarterly Groundwater Monitoring and Sampling Events (4th Qtr 2010 -4th Qtr 2011;
5 events )
$7,450
$10,183
$17,633
2) Annual Monitoring and Sampling Report for 2010 and 2011. (2 Reports)
3) Quarterly Monitoring Reports (1st; 2nd, 3rd Qtrs 2011; 3 Reports)
$6,200
$100
$6,300
$8,160
$150
$8,310
4) Purge Water Disposal (3 Events)
5) Prepare State USTCF Reimbursement Nos. 10 and 11
$2,025
$5,857
$7,882
6) Prepare and Conduct a HVDPE Pilot Test
$2,500
$0
$2,500
7) Pilot Test Report
$9,520
$97,090
$106,610
8) Drilling Event Prefield, Permitting, USA Marking, and Coordination
$4,970
$4,960
$9,930
9) Drill and Install One Monitoring/Remediation Well, and Three Soil Borings
$1,660
$762
$2,422
10) Prepare Additional Subsurface Report
$3,610
$21,995
$25,605
11)
$4,930
$0
$4,930
12)
$0
$0
$0
$0
$0
$0
** *Please ante that thPCe rnct aclimatPC � t• t 1 d
$51,025
$141,096
$192121
es tma es on y, an the actual cost may vary depending on field conditions at the time the work is completed.
2010 -2011 RP Cost Esti nate.xlsx Attachment "B"
Task Order No. 201 4/2010
FEE ESTIMATING SHEET
PROJECT: City of Rohnert Park Corporation Yard
TASK 1: Quarterly Groundwater Monitoring and Sampling Events (4th
Qtr 2010 -4th Qtr 2011; 5 events)
Prepare and conduct five (5) quarterly groundwater monitoring and sampling events from the 4th quarter 2010 through the 4th
quarter 2011. Nine (9) monitoring wells will be monitored annually and up to six (6) monitoring wells quarterly; purge and
sample according to the Winzler & Kelly SOP and on the schedule presented in the 2007 RAP and the March 3, 2009 SCDHS-
EHD letter. Monitoring will include, but is not limited to, the collection of field measurements for DO, ORP, pH, temperature,
and DTW to evaluate the aerobic degradation activity on site. This task will also include sampling the contained purge water for
profiling and off -site disposal.
3 Attachment 'B"
Task Order No. 2011 -01
..
Principal Geologist
$145.00
HOUR
NA
$0.00
Senior/ Project Manager
$120.00
HOUR
2
NA
5
$1,200.00
Associate / Project Consultant
$105.00
HOUR
1
NA
5
$525.00
Sr. Staff Consultant
$90.00
HOUR
12
NA
5
$5,400.00
Junior Consultant/Senior Technician
$80.00
HOUR
NA
$000
Junior Technician
$75.00
HOUR
NA
$0.00
Drafting
$65.001
HOUR
NA
$0.00
Technical Report Reviewer
$65.001
HOUR .
1
NA
5
$325:00
Clerical/Word Processing
$55.00.
HOUR
NA
$0.00
SUBTOTAL EMPLOYEE LABOR 16 $7,450.00
EaiPEiVSES >:..:.. -
Subcontractors
Utility Clearance
TASK
1
$0.00
1
$0.00
Concrete Corer
TASK
I
$0.00
1
$0.00
Traffic Control
TASK
1
$0.00
1
$0.00
Laboratory (See Attached Breakdown)
Driller
$7,150.00
TASK
TASK
1
1
$1,072.50
$0.00
1
1
$8,222.50
$0.00
Equipment Rental
TASK
1
$0.00
1
$0.00
Disposal/Landfill Fees
TASK
1
$0.00
1
$0.00
Permits
Well/Boring Permits $330 + $70 ea additional
TASK
1
1 $0.001
1
$0.00
Discharge Permit
TASK
1
1 $0.001
1
$0.00
Encroachment Permit
TASK
1
1 $0.001
1
$0.00
Equipment Costs
Misc. Small Items
$25.00
DAY
2
NA
5
$250.00
Tyvek/Polyethylene Suits .
$7.59
SUIT
NA
$0.00
Gloves - Nitrite, Lined, Heavyweight
$2.59
PAIR
NA
$0.00
Gloves - Nitrite, Disposable, Unlined
$0.50
PAIR
NA
$0.00
Organic Vapor Cartridge R51
$10.08
PAIR
NA
$0.00
2" Disposable Bailer with drain tube
$8.00
EACH
9
NA
5
$360.00
Purge Pump 2" submersible
$45.00
DAY
1
NA
5
$225.00
Pressurized Bailer with Fitter
$25.00
EACH
NA
$0.00
Encore Sample Set (includes 3 -(5) gm. Samplers)
$30.00
EACH
NA
$0.00
Soil Tubes (stainless steel)
$10.00
EACH
NA
$0.00
Hand Auger with Split Spoon and Hammer
$30.00
DAY
NA
$0.00
Drums
$40.00
EACH
2
NA
5
$400.00
2" Weighted Surge Block
$5.00
EACH
NA
$0.00
Locking Well Caps
$20.00
EACH
1
NA
5
$100.00
Padlock
$10.00
EACH
NA
$0.00
Water Level /Interface Indicator Probes
$35.00
DAY
1
NA
5
$175.00
Photovac TIP Photo - Ion Detector
$100.00
DAY
NA
$0.00
Dissolved Oxygen / ORP Multi -Meter
$40.00
DAY
1
NA
5
$200.00
Field Nitrate/Phosphate Tests
$2.00
EACH
NA
$0.00
Sensidyne Pump and Tubes
$25.00
DAY
NA
$0.00
Air Sampling Pump
$50.00
DAY
NA
$0.00
pH/Condfremp Meter
$40.00
DAY
1
NA
5
$200.00
Turbidity Meter
$20.00
DAY
NA
$0.00
Pipe Finder (metal detector)
$20.00
DAY
NA
1
$0.00
Surveying Equipment
$100.00
DAY
NA
$0.00
Traffic Control Barricades
$5.00
EACH
NA
$0.00
Mileage
$0.50
MILE__I..
20
NA
5
$50.00
SUBTOTAL EXPENSES $10,$50.50
TASK #1 GRAND TOTAL = $17,632.50
>.Ol - ost shmate.x sx min
12/1 o7l
3 Attachment 'B"
Task Order No. 2011 -01
FEE ESTIMATING SHEET
PROJECT: City of Rohnert Park Corporation Yard
TASK 2: Annual Monitoring and Sampling Report for 2010 and 2011 (2
Reports)
Prepare two annual monitoring and sampling reports for the 4th quarter of 2010 and 4th quarter 2011. These reports will
summarize the groundwater monitoring for a complete hydrologic cycle (year) and will include the potentiometric map, iso-
concentration map, groundwater contaminant trend graphs, conclusions, recommendations, and planned site activities.
ITEM jy Y
RATE " a C)MT
QTANTITI�
MARKUPO
TOTAL
#EVENTS
y
Principal Geologist
$145.00
HOUR
I
NA
2
....
$290.00
Senior / Project Manager
$120.00
HOUR
4
NA
2
$960.00
Associate / Project Consultant
$105.00
HOUR
NA
2
$0.00
Sr. Staff Consultant
$90.00
HOUR
14
NA
2
$2,520.00
Junior Consultant/Senior Technician
$80.00
HOUR
NA
2
$0.00
Junior Technician
$75.00
HOUR
NA
2
$0.00
Drafting.
$65.00
HOUR
6
NA
2
$780.00
Technicl Report Reviewer
$65.001
HOUR
I 1
NA
2
$1,430.00
Clerical/Word Processing
$55.001
HOUR
2
NA
2
$220:00
SUBTOTAL EMPLOYEE LABOR 38 $6,200.00
EKgENaES, >:
Subcontractors
Utility Clearance
TASK
$0.00
$0.00
Concrete Corer
TASK
1
$0.00
1
$0.00
GeoTracker Lab Fee
TASK
1
$0.00
1
$0.00
Laboratory (See Attached Breakdown)
TASK
1
$0.00
1
$0.00
Driller
TASK
1
$0.00
1
$0.00
Equipment Rental
TASK
1
$0.00
1
$0.00
Disposal/Water Recycling Fee
TASK
1
$0.001
1
$0.00
Permits
Well/Boring Permits $330 + $70 ea additional
TASK
1
$0.00
1
$0.00
Discharge Permit
TASK
1
$0.00
1
$0.00
Encroachment Permit
TASK
1
$0.00
1
$0.00
Equipment Costs
Misc. Small Items
$25.00
DAY
2
NA
2
$100.00
Tyvek/Polyethylene Suits
$7.59
SUIT
NA
1
$0.00
Gloves - Nitrile, Lined, Heavyweight
$2.59
PAIR
NA
1
$0.00
Gloves - Nitrite, Disposable, Unlined
$0.50
PAIR
NA
1
$0.00
Organic Vapor Cartridge R51
$10.08
PAIR
NA
1
$0.00
2" Disposable Bailer with drain tube
$8.00
EACH
NA
1
$0.00
Purge Pump 2" submersible
$45.00
DAY
NA
I
$0.00
Pressurized Bailer with Filter
$25.00
EACH
NA
1
$0.00
Encore Sample Set (includes 3 -(5) gm. Samplers)
$30.00
EACH
NA
1
$0.00
Soil Tubes (stainless steel)
$10.00
EACH
NA
1
$0.00
Hand Auger with Split Spoon and Hammer
$30.00
DAY
NA
1
$0.00
Drums
$40.00
EACH
NA
1
$0.00
2" Weighted Surge Block
$5.00
EACH
NA
1
$0.00
Locking Well Caps
$20.00
EACH
NA .
I
$0.00
Padlock
$10.00
EACH
NA
I
$0.00
Water Level /Interface Indicator Probes
$35.00
DAY
NA
1
$0.00
Photovac TIP Photo -Ion Detector
$100.00
DAY
NA
1
$0.00
Dissolved Oxygen / ORP Multi -Meter
$40.00
DAY
NA
1
$0.00
Field Nitrate/Phosphate Tests
$2.00
EACH
NA
1
$0.00
Sensidyne Pump and Tubes
$25.00
DAY
NA
1
$0.00
Air Sampling Pump
$50.00
DAY
NA
1
$0.00
pH/Condfremp Meter
$40.00
DAY
NA
1
$0.00
Turbidity Meter
$20.00
DAY
NA
1
$0.00
Pipe Finder (metal detector)
$20.00
DAY
NA
I
$0.00
Surveying Equipment
$100.001
DAY
NA
1
$0.00
Traffic Control Barricades
$5.00
EACH
NA
1
$0.00
Mileage
$0.50
MILE
NA
1
$0.00
SUBTOTAL EXPENSES $100.00
TASK #2 GRAND TOTAL= $6,300.00
2010 -2011 RP Cost Estimate.xlsx 12/10/2010
4 Attachment "B"
Task Order No. 2011 -01
FEE ESTIMATING SHEET
PROJECT: City of Rohnert Park Corporation Yard
TASK 3: Quarterly Monitoring Reports (1st, 2nd, 3rd Qtrs 2011; 3
Reports)
Prepare three (3) quarterly monitoring and groundwater sampling reports; 1st, 2nd, and 3rd quarters for 2011. Reports will
summarize the analytical data, including a contour map, a contaminant distribution map, conclusions, and a planned activities
section.
iTEM
]2ATE
[JNLT
f
QUAI�'TTTY
MARKUPAA
_. _ ,ry,,,:
"TOTAU
<, ,i#��NTS
T07A%'
SFBK.T etiOR ... .. . ..
Principal Geologist
$145.00
HOUR
1
NA
3
$435:00
Senior /Project Manager
$120.00
HOUR
3
NA
3
$1,080.00
Associate / Project Consultant
$105.00
HOUR
NA
3
$0.00
Sr. Staff Consultant
$90.00
HOUR
14
NA
3
$3,780.00
Junior Consultant/Senior Technician
$80.00
HOUR
NA
3
$0.00
Junior Technician
$75.00
HOUR
NA
3
$0.00
Drafting
$65.001
HOUR
1 4
1 NA
3
$780.00
Technical Report Reviewer
1 $65.001
HOUR
9
1 NA
1 3
$1,755.00
Clericat/Word Processing
1 $55.001
HOUR
1 2
1 NA
1 3
1 $330.00
SUBTOTAL EMPLOYEE LABOR 33 $8,160.00
....
EXPENSES:;;.. ..: .
..... .......... .
Subcontractors
Utility Clearance
TASK
1
$0.00
1
$0.00
Concrete Corer
TASK
1
$0.00
1
$0.00
Traffic Control
TASK
1
$0:00
1
$0.00
Laboratory (See Attached Breakdown)
TASK
1
$0.00
1
$0.00
Driller
TASK
1
$0.00
1
$0.00
Equipment Rental
TASK
1
$0.00
1
$0.00
Disposal/Landfill Fees
TASK
1
1 $0.00
1
1 $0.00
Permits
Well/Boring Permits $330 + $70 ea additional
TASK
1
$0.001
1
$0.00
Discharge Permit
TASK
1 1
$0.00
1 1
$0.00
Encroachment Permit
TASK
1
$0.00
1 1
$0.00
Equipment Costs
Misc. Small Items
$25.00
DAY
2
NA
3
$150.00
Tyvek/Polyethylene Suits
$7.59
SUIT
NA
1
$0.00
Gloves - Nitrile, Lined, Heavyweight
$2.59
PAIR
NA
1
$0.00
Gloves - Nitrite, Disposable, Unlined
$0.50
PAIR
NA
1
$0.00
Organic Vapor Cartridge R51A
$10.08
PAIR
NA
1
$0.00
2" Disposable Bailer with drain tube
$8.00
EACH
NA
1
$0.00
Purge Pump 2" submersible
$45.00
DAY
NA
1
$0.00
Pressurized Bailer with Filter
$25.00
EACH
NA
1
$0.00
Encore Sample Set (includes 3-(5) gm. Samplers)
$30.00
EACH
NA
1
$0.00
Soil Tubes (stainless steel)
$10.00
EACH
NA
1
$0.00
Hand Auger with Split Spoon and Hammer
$30.00
DAY
NA
1
$0.00
Drums
$40.00
EACH
NA
1
$0.00
2" Weighted Surge Block
$5.00
EACH
NA
1
$0.00
Locking Well Caps
$20.00
EACH
NA
1
$0.00
Padlock
$10.00
EACH
NA
1
$0.00
Water Level/Interface Indicator Probes
$35.00
DAY
NA
1
$0.00
Photovac TIP Photo -Ion Detector
$100.00
DAY
NA
1
$0.00
Dissolved Oxygen / ORP Multi -Meter
$40.00
DAY
NA
1
$0.00
Field Nitrate/Phosphate Tests
$2.00
EACH
NA
1
$0.00.
Sensidyne Pump and Tubes
$25.00
DAY
NA
1
$0.00
Air Sampling Pump
$50.00
DAY
NA
1
$0.00
pH/Cond/remp Meter
$40.00
DAY
NA
1
$0.00
Turbidity Meter
$20.00
DAY
NA
1
$0.00
Pipe Finder (metal detector)
$20.001
DAY
NA
1
$0.00
Surveying Equipment
$100.00
DAY I
NA
1
$0.00
Traffic Control Barricades
$5.001
EACH I
NA
1
$0.00
Mileage
$0.501
MILE I
NA
1
$0.00
SUBTOTAL EXPENSES $150.00
TASK #3 GRAND TOTAL= $8,310.00
2010 -2011 RP Cost Estimate.xlsx 12/10/2010
5 Attachment "B"
Task Order No. 2011 -01
FEE ESTIMATING SHEET
PROJECT: City of Rohnert Park Corporation Yard
TASK 4: Purge Water Disposal (3 Events)
Profile and coordinate the disposal of the purge water generated from the quarterly monitoring and sampling events; meet the disposal
company at the site during pickup. Four planned events, one. for 2010, two for 2011, and one for 2012.
ITEIii � Z �
RATE
Imp
QUANTITY
��RK�
; '1'AI�
St' &K h ABQR .. .. : :.. : :.... . ........
Principal Geologist
$145.00
HOUR
NA
I
$0.00
Senior / Project Manager
$120.00
HOUR
1
NA
3
$360.00
Associate / Project Consultant
$105.00
HOUR
I
NA
3
$315.00
Sr. StaffConsultant
$90.00
HOUR
5
NA
3
$1,350.00
Junior Consultant/Senior Technician
$80.00
HOUR
NA
1
$0.00
Junior Technician
$75.00
HOUR
NA
1
$0.00
Draliing
$65.001
HOUR
NA
1
$0.00
Technical Report Reviewer
$65.001
HOUR
NA
1
$0.00
Clerical/Word Processing
1 $55.001
HOUR
I
NA
1
$0.00
SUBTOTAL EMPLOYEE LABOR 7 $2,025.00
EXPENSES. ._
..... .... ........... .. ......... .........
Subcontractors
Utility Clearance
TASK,
1
$0.00
1
$0.00
Concrete Corer
TASK
1
$0.00
1
$0.00
Traffic Control
TASK
1
$070
1
$0.00
Laboratory (See Attached Breakdown)
$339.00
TASK
3
$152.55.
1
$1,169,55
Driller
TASK
1
$0.00
1
$0.00
Disposal/Landfill Fees Quarterly Event
$225.00
TASK
2
$67.50
3
$1,552.50
Disposal/Landfill Fees Annual Event
1 $225.001
TASK
1 6
$202.501
2
1 $3,105.00
Permits
Well/Boring Permits $330 + $70 ea additional
TASK
1
$0.001
1
$0.00
Discharge Permit
TASK
1
$0.001
1
$0.00
Encroachment Permit
TASK
1
$0.00
1 1
$0.00
Equipment Costs
Misc. Small Items
$25.00
DAY
NA
1
$0.00
Tyvek/Polyethylene Suits
$7.59
SUIT
NA
1
$0.00
Gloves - Nitrile, Lined, Heavyweight
$2.59
PAIR
NA
1
$0.00
Gloves - Nitrile, Disposable, Unlined
$0.50
PAIR
NA
1
$0.00
Organic Vapor Cartridge R51A
$10.08
PAIR
NA
1
$0.00
2" Disposable Bailer with drain tube
$8.00
EACH
NA
1
$0.00
Purge Pump 2" submersible
$45.00
DAY
NA
1
$0.00
Pressurized Bailer with Filter
$25.00.
EACH
NA
1
$0.00
Encore Sample Set (includes 3 -(5) gm. Samplers)
$30.00
EACH
NA
1
$0.00
Soil Tubes (stainless steel)
$10.00
EACH
NA
1
$0.00
Hand Auger with Split Spoon and Hammer
$30.00
DAY
NA
1
$0.00
Drums
$40.00
EACH
NA
1
$0.00
2" Weighted Surge Block
$5.00
EACH
NA
I
$0.00
Locking Well Caps
$20.00
EACH
NA
1
$0.00
Padlock
$10.00
EACH
NA
1
$0.00
Water LeveVlnterface Indicator Probes
$35.00
DAY
NA
1
$0.00
Photovac TIP Photo -Ion Detector
$100.00
DAY
NA
1
$0.00
Dissolved Oxygen / ORP Multi -Meter
$40.00
DAY
NA
1
$0.00
Field Nitrate/Phosphate Tests
$2.00
EACH
NA
1
$0.00
Sensidyne Pump and Tubes
$25.00
DAY
NA
1
$0.00
Air Sampling Pump
$50.00
DAY
NA
I
$0.00
pH/Cond/remp Meter
$40.00
DAY
NA
1
$0.00
Turbidity Meter
$20.00
DAY
NA
1
$0.00
Pipe Finder (metal detector)
$20.001
DAY
NA
1
$0.00
Surveying Equipment
$100.001
DAY
NA
1
$0.00
Traffic Control Barricades
$5.001
EACH
NA
I
$0.00
Mileage
$0.501
MILE 1
20
NA
3
$30.00
SUBTOTAL EXPENSES $5,857.05
TASK #4 GRAND TOTAL = $7,882.05
2010 -2011 RP Cost Estimate.xlsx 12/10/2010
6 Attachment "B"
Task Order No. 2011 -01
FEE ESTIMATING SHEET
PROJECT: City of Rohnert Park Corporation Yard
TASK 5: Prepare State USTCF Reimbursement Nos. 10 and 11
Prepare and submit two reimbursements to the USTCF. Winzler & Kelly will need the assistance of the City of Rohnert Park in
providing the necessary backup and cancelled checks that are required. Additional reimbursements and follow -up to the USTCF
will be prepared (if directed) for similar costs described below. The State has been short of funds, but it is still prudent to complete
these claims for future reimbursements. The claims will be prepared immediately after the Feasibilty Study is completed.
ITEM RATE.
VVBcK LABOR . _ . : ::... ,...: ......................
,s UNIT QUANTITY MARKUP �QI<A"I.�
x # YE' NT
.......................................... :...
TOTAL
W
Principal Geologist
$145.00
HOUR
NA
$0.00
Senior / Project Manager
$120.00
HOUR
4
NA
2
$960.00
Associate / Project Consultant
$105.00
HOUR
NA
$0.00
Sr. StaffConsultant
$90.00
HOUR
NA
$0.00
Junior Consultant/Senior Technician
$80.00
HOUR
NA
$0.00
Junior Technician
$75.00
HOUR
NA
$0.00
Drafting
$65.00
HOUR
I
NA
$0.00
Technical Report Reviewer
$65.001
HOUR
I
NA
1 2
$1,430.00
Clerical/Word Processing
$55.001
HOUR
I
NA
1 2
$110.00
SUBTOTAL EMPLOYEE LABOR 16 $2,500.00
Subcontractors
Utility Clearance
TASK
1
$0.00
1
$0.00
Concrete Corer
TASK
1
$0.00
1
$0.00
Traffic Control
TASK
1
$0.00
1
$0.00
Laboratory (See Attached Breakdown)
TASK
1
$0.00
1
$0.00
Driller
TASK
1
$0.00
I
$0.00
Equipment Rental
TASK
1
$0.00
1
$0.00
Disposal/Landfill Fees
TASK
1
$0.00
1
$0.00
Permits
Well/Boring Permits $330 + $70 ea additional
TASK
1
$0.00
1
$0.00
Discharge Permit
TASK
1
$0.00
I'
$0.00
Encroachment Permit
TASK
1
$0.00
1
$0.00
Equipment Costs
Misc. Small Items
$25.00
DAY
NA
1
$0.00
Tyvek/Polyethylene Suits
$7.59
SUIT
NA
I
$0.00
Gloves - Nitrile, Lined, Heavyweight
$2.59
PAIR
NA
1
$0.00
Gloves - Nitrile, Disposable, Unlined
$0.50
PAIR
NA
1
$0.00
Organic Vapor Cartridge R51 A
$10.08
PAIR
NA
I
$0.00
2" Disposable Bailer with drain tube
$8.00
EACH
NA
1
$0.00
Purge Pump 2" submersible
$45.00
DAY
NA
1
$0.00
Pressurized Bailer with Filter
$25.00
EACH
NA
1
$0.00
Encore Sample Set (includes 3 -(5) gm. Samplers)
$30.00
EACH
NA
1
$0.00
Soil Tubes (stainless steel)
$10.00
EACH
NA
I
$0.00
Hand Auger with Split Spoon and Hammer
$30.00
DAY
NA
1
$0.00
Drums
$40.00
EACH
NA
1
$0.00
2" Weighted Surge Block
$5.00
EACH
NA
1
$0.00
Locking Well Caps
$20.00
EACH
NA
1
$0.00
Padlock
$10.00
EACH
NA
]
$0.00
Water Level /Interface Indicator Probes
$35.00
DAY
NA
1
$0.00
Photovac TIP Photo -Ion Detector
$100.00
DAY
NA
1
$0.00
Dissolved Oxygen / ORP Multi -Meter
$40.00
DAY
NA
1
$0.00
Field Nitrate/Phosphate Tests
$2.00
EACH
NA
1
$0.00
Sensidyne Pump and Tubes
$25.00
DAY
NA
1
$0.00
Air Sampling Pump
$50.00
DAY
NA
1
$0.00
pH/Cond/I'emp Meter
$40.00
DAY
NA
1
$0.00
Turbidity Meter
.$20.00
DAY
NA
1
$0.00
Pipe Finder (metal detector)
$20.00
DAY
NA
I
$0.00
Surveying Equipment
$100.001
DAY
NA
1
$0.00
Traffic Control Barricades
$5.001
EACH
NA
1
$0.00
Mileage
$0.501
MILE i
NA
1
$0.00
SUBTOTAL EXPENSES $0.00
TASK #5 GRAND TOTAL = $2,500.00
2010 -2011 RP Cost Estimate.xlsx 12/10/2010
7 Attachment "B"
Task Order No. 2011 -01
FEE ESTIMATING SHEET
PROJECT: City of Rohnert Park Corporation Yard
TASK 6: Prepare aild Conduct a HVDPE Pilot Test
Prepare a workplan and submit to the SCDHS -EHD for approval. Conduct a Pilot Test using HVDPE based on the observed
petroleum concentrations in MW -5 and north of the former UST pit. The proposed monitoring/remediation well in side the shop
building will be included in the Pilot Testing. Winzler & Kelly anticipates conducting a 30 day dual -phase extraction ( HVDPE)
pilot test event at the site. The Pilot Test may be performed in two 15 -day HVDPE events (30 days total) if preliminary data
indicates. Concentration trends and mass removal rates will be monitored. The Pilot Test event will be evaluated to estimate long-
term results for this option. Other parameters will be assessed such as extraction well flow rate that can be sustained, projected
mass removal rates, review dissolved concentration trends, and prepare recommendations. Assume 30 days of extraction and
50,000 gallons of water to contain, treat, and discharge.
a ITEM
9 �
RATE
.��
UNIT
QUANTITI'v
MARKUP
TO AL,
#EVENTS
W &K LABOR
..
_.. ..
Principal Geologist
$145.00
HOUR
2
NA
1
...
$290.00
Senior/ Project Manager
$120.00
HOUR
24
NA
I
$2,880.00
Associate / Project Consultant
$105.00
HOUR
NA
1
$0.00
Sr. Staff Consultant
$90.00
HOUR
16
NA
1
$1,440.00
Junior Consultant/Senior Technician
$80.00
HOUR
48
NA
1
$3,840.00
Junior Technician
$75.00
HOUR
NA
1
$0.00
Drafting
1 $65.001
HOUR
1 2
NA
1
$130.00
Technical Report Reviewer
1 $65.001
HOUR
1 6
NA
1
$390.00
Clerical/Word Processing
1 $55.001
HOUR
1 10
NA
1
$550.00
SUBTOTAL EMPLOYEE LABOR 108 $9,520.00
E)F1rEivSS :.... -
Subcontractors
Utility Clearance
TASK
1
$0.00
1
$0.00
Concrete Corer
TASK
1
$0.00
1
$0.00
Traffic Control '
TASK
1
$0.00
1
$0.00
Laboratory (See Attached Breakdown)
$3,600.00
TASK
1
$540.00
1
$4,140.00
Cal Clean Inc. Mobile HVDPE Contractor (30 -days)
$48,000.00
TASK
1
$7,200.00
1
$55,200.00
Water Treatment and Discharge
$15,500.00
TASK
1
$2,325.00
2
$35,650.00
Disposal/Landfill Fees
I TASK
1
1 $0.00
1
1 $0.00
Permits
Well/Boring Permits $330 + $70 ea additional
TASK
1
$0.00
1
$0.00
Discharge Permit
$1,000.00
TASK
1
$150.00
1
$1,150.00
Encroachment Permit
TASK
1
$0.00
1 1
$0.00
Equipment Costs
Misc. Small Items
$25.00
DAY
15
NA
2
$750.00
Tyvek/Polyethylene Suits
$7.59
SUIT
NA
1
$0.00
Gloves - Nitrite, Lined, Heavyweight
$2.59
PAIR
NA
1
$0.00
Gloves - Nitrite, Disposable, Unlined
$0.50
PAIR
NA
1
$0.00
Organic Vapor Cartridge R51
$10.08
PAIR
NA
1
$0.00
2" Disposable Bailer with drain tube
$8.00
EACH
NA
1
$0.00
Purge Pump 2" submersible
$45.00
DAY
NA
1
$0.00
Pressurized Bailer with Filter
$25.00
EACH
NA
1
$0.00
Encore Sample Set (includes 3 -(5) gm. Samplers)
$30.00
EACH
NA
I
$0.00
Soil Tubes (stainless steel)
$10.00
EACH
NA
1
$0.00
Hand Auger with Split Spoon and Hammer
$30.00
DAY
NA
1
$0.00
Drums
$40.00
EACH
NA
1
$0.00
2" Weighted Surge Block
$5.00
EACH
NA
1
$0.00
Locking Well Caps
$20.00
EACH
NA
1
$0.00
Padlock
$10.00
EACH
NA
1
$0.00
Water Level /Interface Indicator Probes
$35.00
DAY
NA
1
$0.00
Photovac TIP Photo -Ion Detector
$100.00
DAY
NA
1
$0.00
Dissolved Oxygen / ORP Multi -Meter
$40.00
DAY
NA
1
$0.00
Field Nitrate/Phosphate Tests
$2.00
EACH
NA
1
$0.00
Sensidyne Pump and Tubes
$25.00
DAY
NA
1
$0.00
Air Sampling Pump
$50.00
DAY
NA
1
$0.00
pH/Condfremp Meter
$40.00
DAY
NA
1
$0.00
Turbidity Meter
$20.00
DAY
NA
1
$0.00
Pipe Finder (metal detector)
$20.00
DAY
NA
1
$0.00
Surveying Equipment
$100.001
DAY I
NA
1
$0.00
Traffic Control Barricades
$5.001
EACH I
NA
1
$0.00
Mileage
$0.501
MILE 1
20
NA
20
$200.00
SUBTOTAL EXPENSES $97,090.00
TASK #6 GRAND TOTAL= $106,610.00
2010 -2011 RP Cost Estimate.xlsx 8 Attachment 'B" 12/10/2010
Task Order No. 2011 -01
FEE ESTIMATING SHEET
PROJECT: City of Rohnert Park Corporation Yard
TASK 7: Pilot Test Report
Prepare a Pilot Test report based on the 30 day HVDPE event. After the completion of the Pilot Test HVDPE event, summarize
the data, compare initial and ending dissolved groundwater concentrations, estimate radius of influence, and mass removed.
Evaluate option for additional events. Evaluate and recommend HVDPE as a remedial option and projections to reach cleanup
goals.
��� ITE .
RATE
[TNIT
QiANTI Y
MARKUP
T AL
-T
# EIVTS
TOTAL
W &K'EABOR ..
.....:.. .. :.....
:...
.. .. .
Principal Geologist
$145.00
HOUR
2
NA
1
$290.00
Senior /Project Manager
$120.00
HOUR
8
NA
1
$960.00
Associate / Project Consultant
$105.00
HOUR
2
NA
1
$210.00
Sr. Staff Consultant
$90.00
HOUR
8
NA
1
$720.00
Junior Consultant/SeniorTechnician
$80.00
HOUR
24
NA
1
$1,920.00
Junior Technician
$75.00
HOUR
NA
1
$0.00
Drafting
i $65.00
HOUR
i 4
NA
1
$260.00
Technical Report Reviewer
1 $65.001
HOUR
1 6
NA
1
$390.00
Clerical/Word Processing
1 $55.001
HOUR
1 4
NA
I
$220.00
SUBTOTAL EMPLOYEE LABOR 58 $4,970.00
EXPENSES: i> . .. ........ _...
Subcontractors
Utility Clearance
TASK
1
$0.00
1
$0.00
Concrete Corer
TASK
1
$0.00
1
$0.00
Traffic Control
TASK
1
$0.00
1
$0.00
Laboratory (See Attached Breakdown)
$3,750.00
TASK
1
$562.50
I
$4,312.50
Driller
TASK
1
$0.00
1
$0.00
Equipment Rental
TASK
1
$0.00
1
$0.00
Disposal/Landfill Fees
TASK
1
1 $0.001
1
$0.00
Permits
Well/Boring Permits $330 + $70 ea additional
TASK
1
$0.00
1
1 $0.00
Discharge Permit
TASK
1
$0.00
1
$0.00
Encroachment Permit
TASK
1 1
$0.00
1 1
$0.00
Equipment Costs
Misc. Small Items
$25.00
DAY
4
NA
1
$100.00
Tyvek/Polyethylene Suits
$7.59
SUIT
NA
1
$0.00
Gloves - Nitrile, Lined, Heavyweight
$2.59
PAIR
NA
1
$0.00
Gloves - Nitrile, Disposable, Unlined
$0.50
PAIR
NA
1
$0.00
Organic Vapor Cartridge R51
$10.08
PAIR
NA
1
$0.00
2" Disposable Bailer with drain tube
$8.00
EACH
4
NA
1
$32.00
Purge Pump 2" submersible
$45.00
DAY
NA
1
$0.00
Pressurized Bailer with Filter
$25.00
EACH
NA
1
$0.00
Encore Sample Set (includes 3 -(5) gm. Samplers)
$30.00
EACH
NA
1
$0.00
Soil Tubes (stainless steel)
$10.00
EACH
NA
I
$0.00
Hand Auger with Split Spoon and Hammer
$30.00
DAY
NA
1
$0.00
Drums
$40.00
EACH
1
NA
1
$40.00
2" Weighted Surge Block
$5.00
EACH
NA
1
$0.00
Locking Well Caps
$20.00
EACH
NA
1
$0.00
Padlock
$10.00
EACH
NA
1
$0.00
Water Level/Interface Indicator Probes
$35.00
DAY
1
NA
1
$35.00
Photovac TIP Photo -Ion Detector
$100.00
DAY
1
NA
I
$100.00
Dissolved Oxygen / ORP Multi - Meter.
$40.00
DAY
NA
1
$0.00
Field Nitrate/Phosphate Tests
$2.00
EACH
NA
1
$0.00
Sensidyne Pump and Tubes
$25.00
DAY
NA
1
$0.00
Air Sampling Pump
$50.00
DAY
NA
1
$0.00
pH/Cond/Temp Meter
$40.00
DAY
1
NA
1
$40.00
Turbidity Meter
$20.00
DAY
NA
1
$0.00
Pipe Finder (metal detector)
$20.00
DAY
NA
1
$0.00
Surveying Equipment
$100.00
DAY
NA
1
$0.00
Traffic Control Barricades
$5.00
EACH
NA
1
$0.00
Mileage
$0.50
MILE
20
NA
30
$300.00
SUBTOTAL EXPENSES $4,959.50
TASK #7 GRAND TOTAL = $9,929.50
2010 -2011 RP Cost Estimate.xlsx 12/10/2010
9 Attachment "B"
Task Order No. 2011 -01
FEE ESTIMATING SHEET
PROJECT: City of Rohnert Park Corporation Yard
TASK 8: Drilling Event Prefield, Permitting, USA Marking, and
Coordination
Mark site as required by Underground Services Alert (USA). North, make required notifications to USA, SCDHS -EHD, and the
City. Prepare drilling permits and pay fees. Coordination with a drilling company to install one (1) shallow monitoring well, and
up to three (3) soil borings inside the Corporation Yard Shop Building. A limited access drilling rig will. be used.
3I TEM 3 lTE
V1 &K LABOR
IMT
QT1AN X l 1'
MAiiliClP
OTYAL
` t O TAL
Principal Geologist
$145.00
HOUR
NA
I
$0.00
Senior / Project Manager
$120.00
HOUR
2
NA
1
$240.00
Associate / Project Consultant
$105.00
HOUR
1
NA
1
$105.00
Sr. StaffConsuitant
590.00
HOUR
2
NA
1
$180.00
Junior Consultant/Senior Technician
$80.00
HOUR
12
NA
1
$960.00
Junior Technician
$75.00
HOUR
NA
1
$0.00
Drafting
$65.001
HOUR
NA
1
$0.00
Technical Report Reviewer
$65.001
HOUR
I
NA
1
$65.00
Clerical/Word Processing
$55.001
HOUR
2
NA
1
$110.00
SUBTOTAL EMPLOYEE LABOR 20 $1,660.00
EJEPEidSE$, 6,
Subcontractors
Utility Clearance
TASK
1
$0.00
1
$0.00
Concrete Corer
TASK
1
$0.00
1
$0.00
Traffic Control
TASK
1
$0.00
1
$0.00
Laboratory (See Attached Breakdown)
TASK
1
$0.00
I
$0.00
Driller.
TASK
1
$0.00
I
$0.00
Equipment Rental
TASK
1
$0.00
1
$0.00
Disposal/Landfill Fees
TASK
I
$0.00
1
1 $0.00
Permits
Well/Boring Permits $330 + $70 ea additional
$610.00
TASK
I
$91.50
1
$701.50
Discharge Permit
TASK
I
$0.00
1
$0.00
Encroachment Permit
TASK
1
$0.00
1
$0.00
Equipment Costs
Misc. Small Items
$25.00
DAY
2
NA
1
$50.00
Tyvek/Polyethylene Suits
$7.59
SUIT
NA
I
$0.00
Gloves - Nitrile, Lined, Heavyweight
$2.59
PAIR
NA
1
$0.00
Gloves - Nitrile, Disposable, Unlined
$0.50
PAIR
NA
1
$0.00
Organic Vapor Cartridge R51 A
$10.08
PAIR
NA
I
$0.00
2" Disposable Bailer with drain tube
$8.00
EACH
NA
1
$0.00
Purge Pump 2" submersible
$45.00
DAY
NA
1
$0.00
Pressurized Bailer with Filter
$25.00
EACH
NA
1
$0.00
Encore Sample Set (includes 3 -(5) gm. Samplers)
$30.00
EACH
NA
1
$0.00
Soil Tubes (stainless steel)
$10.00
EACH
NA
1
$0.00
Hand Auger with Split Spoon and Hammer
$30.00
DAY
NA
1
$0.00
Drums
$40.00
EACH
NA
1
$0.00
2" Weighted Surge Block
$5.00
EACH
NA
I
$0.00
Locking Well Caps
$20.00
EACH
NA
1
$0.00
Padlock
$10.00
EACH
NA
I
$0.00
Water Level /Interface Indicator Probes
$35.00
DAY
NA
I
$0.001.
Photovac TIP Photo -Ion Detector
$100.00
DAY
NA
1
$0.00
Dissolved Oxygen / ORP Multi -Meter
$40.00
DAY
NA
1
$0.00
Field Nitrate/Phosphate Tests
$2.00
EACH
NA
1
$0.00
Sensidyne Pump and Tubes
$25.00
DAY
NA
I
$0.00
Air Sampling Pump
$50.00
DAY
NA
1
$0.00
pH/Cond/Temp Meter
$40.00
DAY
NA
1
$0.00
Turbidity Meter
$20.00
DAY
NA
1
$0.00
Pipe Finder (metal detector)
$20.001
DAY
NA
1
$0.00
Surveying Equipment
$100.00
DAY
NA
1
$0.00
Traffic Control Barricades
$5.00
EACH
NA
1
$0.00
Mileage
$0.501
MILE 1
20
NA
I
$10.00
SUBTOTAL EXPENSES $761.50
TASK #8 GRAND TOTAL = $2,421.50
2010 -2011 RP Cost Estimate.xlsx 12/10/2010
10 Attachment "B"
Task Order No. 2011 -01
FEE ESTIMATING SHEET
PROJECT: City of Rohnert Park Corporation Yard
TASK 9: Drill and Install One Monitoring/Remediation Well, and Three
Soil Borings
Install one 4 -inch monitoring/remediation well and up to three soil borings. Borings to be continuousely cored and lithology
logged and field screened for contaminants. Collect insitu groundwater samples from the three borings using a GeoProbe device.
Retain surface and smear soil samples for analytical testing. As directed by the SCDHS -EHD, one saturated soil sample in at the
depth of 17 feet bgs in one boring will be collected and submitted for analysis. Develop monitoring/remediation well. Contain all
waste generated from the drilling activities in DOT approved drums, label, and profile for disposal. Survey TOC of the new well
and the locations of the borings. Up to twelve (12) soil and groundwater samples to be delivered to the analytical laboratory .for
testing.
�T1wM x RATE i)NiT QUANTx'I'X<
MAI;ZKU�
' TOTAL
TOTAIL
Principal Geologist
$145.00
HOUR
NA
1
$0.00
Senior/ Project Manager
$120.00
HOUR
3
NA
1
$360.00
Associate / Project Consultant
$105.00
HOUR
3
NA
1
$315.00
Sr. Staff Consultant
$90.00
HOUR
20
NA
1
$1,800.00
Junior Consultant/Senior Technician
$80.00
HOUR
12
NA
1
$960.00
Junior Technician
$75.00
HOUR
NA
1
$0.00
Drafting
$65.001
HOUR
NA
I
$000
Technical Report Reviewer
$65.001
HOUR
1
NA
1
$65.00
Clerical/Word Processing
$55.001
HOUR
2
NA
1
$110.00
SUBTOTAL EMPLOYEE LABOR 41 $3,610.00
1? fPENSkS: _.. ... ..
Subcontractors
Utility Clearance
$350.00
TASK
1
$52.50
1
$402.50
Concrete Corer
$750.00
TASK
1
$112.50
1
$862.50
Surveyor
$1,750.00
TASK
1
$262.50
1
$2,012.50
Laboratory (See Attached Breakdown)
$4,760.00
TASK
1
$714.00
1
$5,474.00
Driller
$8,000.00
TASK
1
$1,200.00
1
$9,200.00
Equipment Rental
TASK
1
$0.00
1
1 $0.00
Disposal/Landfill Fees
1 $225.001
TASK
1 10
$337.501-----------r
$2,587.50
Permits
Well/Boring Permits $330 + $77 ea additional
$561.00
TASK
1
$84.15
1
$645.15
Discharge Permit
TASK
1
$0.00
I
$0.00
Encroachment Permit
TASK
1
$0.001
$0.00
Equipment Costs
Misc. Small Items
$25.00
DAY
8
NA
1
$200.00
Tyvek/Polyethylene Suits
$7.59
SUIT
NA
1
$0.00
Gloves - Nitrite, Lined, Heavyweight
$2.59
PAIR
NA
1
$0.00
Gloves - Nitrile, Disposable, Unlined
$0.50
PAIR
NA
T
$0.00
Organic Vapor Cartridge R51A
$10.08
PAIR
NA
1
$0.00
2" Disposable Bailer with drain tube
$8.00
EACH
2
NA
1
$16.00
Purge Pump 2" submersible
$45.00
DAY
1
NA
1
$45.00
Pressurized Bailer with Filter
$25.00
EACH
NA
1
$0.00
Encore Sample Set (includes 3 -(5) gm. Samplers)
$30.00
EACH
NA
1
$0.00
Soil Tubes (stainless steel)
$10.00
EACH
NA
1
$0.00
Hand Auger with Split Spoon and Hammer
$30.00
DAY
NA
1
$0.00
Drums
$40.00
EACH
2
NA
I
$80.00
2" Weighted Surge Block
$5.00
EACH
1
NA
1
$5.00
Locking Well Caps
$20.00
EACH
NA
1
$0.00
Padlock
$10.00
EACH
NA
1
$0.00
Water Level /Interface Indicator Probes
$35.00
DAY
1
NA
1
$35.00
Photovac TIP Photo -Ion Detector
$100.00
DAY
3
NA
1
$300.00
Dissolved Oxygen / ORP Multi -Meter
$40.00
DAY
I
NA
1
$40.00
Field Nitrate/Phosphate Tests
$2.00
EACH
NA
1
$0.00
Sensidyne Pump and Tubes
$25.00
DAY
NA
1
$0.00
Air Sampling Pump
$50.00
DAY
NA
1
$0.00
pH/Condfremp Meter
$40.00
DAY
1
NA
1
$40.00
Turbidity Meter
$20.00
DAY
I
NA
1
$20.00
Pipe Finder (metal detector)
$20.00
DAY
NA
1
$0.00
Surveying Equipment
$100.00
DAY
NA
1
$0.00
Traffic Control Barricades
$5.001
EACH
NA
1
$0.00
Mileage
$0.501
MILE
20
NA
3
$30.00
SUBTOTAL EXPENSES $21,995.15
TASK #9 GRAND TOTAL = $25,605.15
2010 -2011 RP Cost Estimate.xlsx 11 Attachment 'B"
Task Order No. 201 )f2 /alil/2010
FEE ESTIMATING SHEET
PROJECT: City of Rohnert Park Corporation Yard
TASK 10: Prepare Additional Subsurface Report
Prepare a technical report describing the field activities and a findings of this investigation. The report will include a summary of
findings including analytical data, dissolved concentration and soil concentration maps, potentiometric map, survey data,
conclusions, and recommendations.
ITEM '
I2�TE
> JNIT
QUANTITI'
W:
b ARTIMM
TOTAL
TUAL
....
w &x Lasax
.
Principal Geologist
$145.00
HOUR
1
NA
I
$145.00
Senior/ Project Manager
$120.00
HOUR
4
NA
I
$480.00
Associate /Project Consultant
$105.00
HOUR
3
NA
1
$315.00
Sr. Staff Consultant
$90.00
HOUR
8
NA
I
$720.00
Junior Consultant/Senior Technician
$80.00
HOUR
24
NA
i
$1,920.00
Junior Technician
$75.00
HOUR
NA
1
$0.00
Drafting
$65.001
HOUR
10
NA
1
$650.00
Technical Report Reviewer
$65.001
HOUR
4
NA
1
$260.00
Clerical/Word Processing
$55.001
HOUR
8
1 NA
1
$440.00
SUBTOTAL EMPLOYEE LABOR 62 $4,930.00
........ ......... ..... .... ..
Subcontractors
Utility Clearance
TASK
1
$0.00
I
$0.00
Concrete Corer
TASK
7
$0.00
1
$0.00
Traffic Control
TASK
1
$0.00
1
$0.00
Laboratory (See Attached Breakdown)
TASK
1
$0.00
1
$0.00
Driller
TASK
1.
$0.00
1
$0.00
Equipment Rental
TASK
1
$0.00
1
$0.00
Disposal/Landfill Fees
TASK
1
$0.00
1
$0.00
Permits
Well/Boring Permits $330 + $70 ea additional.
TASK
1
$0.00
1
1 $0.00
Discharge Permit
TASK
1
$0.00.
1
1 $0.00
Encroachment Permit
TASK
1
so-001,
1
$0.00
Equipment Costs
Misc. Small Items
$25.00
DAY
NA
1
$0.00
Tyvek/Polyethylene Suits
$7.59
SUIT
NA
1
$0.00
Gloves - Nitrile, Lined, Heavyweight
$2.59
PAIR
NA
1
$0.00
Gloves - Nitrile, Disposable, Unlined
$0.50.
PAIR
NA
1
$0.00
Organic Vapor Cartridge R51A
$10.08
PAIR
NA
1
$0.00
2" Disposable Bailer with drain tube
$8.00
EACH
NA
1
$0.00
Purge Pump 2" submersible
$45.00
DAY
NA
I
$0.00
Pressurized Bailer with Filter
$25.00
EACH
NA
1
$0.00
Encore Sample Set (includes 3 -(5) gm. Samplers)
$30.00
EACH
NA
1
$0.00
Soil Tubes (stainless steel)
$10.00
EACH
NA
1
$0.00
Hand Auger with Split Spoon and Hammer
$30.00
DAY
NA
1
$0.00
Drums
$40.00
EACH
NA
I
$0.00
2" Weighted Surge Block
$5.00
EACH
NA
1
$0.00
Locking Well Caps
$20.00
EACH
NA
1
$0.00
Padlock
$10.00
EACH
NA
1
.$0.00
Water Level /Interface Indicator Probes
$35.00
DAY
NA
1
$0.00
Photovac TIP'Photo -Ion Detector
$100.00
DAY
NA
1
$0.00
Dissolved Oxygen / ORP Multi-Meter
$40.00
DAY
NA
1
$0.00
Field Nitrate/Phosphate Tests
$2.00
EACH
NA
1
$0.00
Sensidyne Pump and Tubes
$25.00
DAY
NA
1
$0.00
Air Sampling Pump
$50.00
DAY
NA
1
$0.00
pH/Condfremp Meter
$40.00
DAY
NA
1
$0.00
Turbidity Meter
$20.00
DAY
NA
1
$0.00
Pipe Finder (metal detector)
$20.00
DAY
NA
i
$0.00
Surveying Equipment
$100.001
DAY
NA
I
$0.00
Traffic Control Barricades
$5.001
EACH
NA
1
$0.00
Mileage
$0.50
MILE
NA
1
$0.00
SUBTOTAL EXPENSES $0.00
TASK #10 GRAND TOTAL = $4,930.00
2010 -2011 RP Cost Estimate.xlsx 12/10/2010
12 Attachment "B"
Task Order No. 2011 -01
WINZLER&KELLY LABORATORY ANALYSES
Supplemental Cost Information: Commercial Rates for Laboratory Analyses
PROJECT NAME: City of Rohnert Park Corporation Yard
PROJECT NUMBER: 2056- 10 -OOXX
PROJECT MANAGER: David J. Vossler
Supplemental Cost Information: Commercial Rates for Laboratory Analyses
Task
#
Sample
Analysis
Laboratory Method
Soil, Water;
or Air
Cost per
Sample
(without
overhead)
#
Sample
s
Total Cost
per Line
Total Cost
Per Task
Quarterly/Annual Sampling
TPH -G, BTEX, 5 Oxys, Pb Sc
EPA Methods 8015M, 8260B
Water
$195.00
33
$6,435 00
Annual - 9 wells
$0.00
1
Quarterly 6 wells
$0.00
,A
Disposal
Water
$3.00
33
$99.00
GeoTracker 10 %)
$600.00
1
$600.00
$,7,134,QOi
Purge water disposal
TPH -G, D, BTEX, and MTBE
EPA Method 8015M, 8260B
Water
$110.00
3
$330.00
4
Disposal
$3.00
3
$9.00
HVDPE Pilot-Test
TPH -G, BTEX, 5 Oxys, Pb Sc
EPA Methods 8015M, 8260B
Water
$195.00
8
$1,560.00
,
TPH -G -D -MO BTEX and
Air
$210.00
8
$1,680.00
6
$0.00
Disposal
$3.00.
8
$24.00
, ,�z$, �„ ,;;•
GeoTracker
$330.00
1
$330.00
Well and Soil Boring Install TPH -G, -D, BTEX, and MTBI
EPA Method 8015M, 8260B
soil
$250.00
12
$3,000.00['
U to 4 borings, 3 samples each
water
$250.00
4
$1,000 00
;r�a ie
9
Soil Disposal
TPH -G, -D, BTEX, and Lead
soil
$280.00
Disposal
soil /water
$3.00
16
$48 00
, =,
GeoTracker
$425.00
1
$425.00
Total Analytical Cost =
$15,820.00
$15,820.00
2010 -2011 RP Cost Estimate.xlsx 12/10/2010
13 Attachment "B"
Task Order No. 2011 -01