2007/04/24 City Council Resolution 2007-71RESOLUTION NO. 2007 -71
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROHNERT PARK
AUTHORIZING AND APPROVING AMENDMENT NO. 2 TO AGREEMENT WITH
WINZLER & KELLY CONSULTING ENGINEERS FOR PROFESSIONAL
ENGINEERING SERVICES FOR THE CITY CENTER
PEDESTRIAN IMPROVEMENT PROJECT
WHEREAS, on May 23, 2006 the City Council approved Resolution No. 2006 -135
approving an agreement for services with Winzler & Kelly Consulting Engineers for engineering
and design services to take the Pedestrian Improvement Project from the future City Center Plaza
west to Commerce Boulevard along City Center Drive (the "Project ") to the 30% completion
phase (the "Agreement "); and
WHEREAS, on October 5, 2007, the City entered into Amendment No. 1 to provide for
professional services associated with the environmental review documentation and design work
necessary for the Project and amending the indemnification language of the Agreement; and
WHEREAS, the City desires to amend the Agreement to provide for engineering and
design services to a 100% completion phase and to provide construction documents for the Project.
NOW THEREFORE BE IT RESOLVED by the City Council of the City of Rohnert
Park that it does hereby authorize and approve Amendment No. 2 to the Agreement by and
Between Winzler & Kelly Consulting Engineers and the City of Rohnert Park, a municipal
corporation, for engineering and design services associated with the development of the Project;
and
BE IT FURTHER RESOLVED that the City Manager is hereby authorized and directed
to execute the Amendment, negotiate future changes to the Agreement, and execute any future
Amendments necessitated by those changes.
DULY AND REGULARLY ADOPTED this 24th day of April, 2007.
ATTEST:
ag
CITY OF ROHNERT PARK
rLI F -OR 14AP
BREEZE: AYE MACKENZIE: AYE SMITH: AYE STAFFORD: AYE VIDAK- MARTINEZ: AYE
AYES: (5) NOES: (0) ABSENT: (0) ABSTAIN: (0)
AGREEMENT FOR SERVICES
AMENDMENT NO. 2
This Amendment is made and entered into this day of April; 2007, by and between
the City of Rohnert Park, hereinafter referred to as the "City," and Winzler & Kelly Consulting
Engineers, hereinafter referred to as the "Consultant."
WHEREAS, the City entered into an Agreement for Services with Consultant on July 6,
2006 for engineering services associated with the development of the pedestrian improvements
along City Center Drive from the future Plaza west to Commerce Boulevard (the "Project "), per
City Council Resolution No. 2006 -135 ( "Agreement ") which took the project to 30% completion;
and
WHEREAS, the City entered into Amendment No. 1 on October 5, 2006 to provide for
professional services associated with the environmental review documentation, landscaping work
necessary for the Project and amendment to the indemnification Language of the Agreement; and
WHEREAS, the City desires to amend the Agreement again to provide for Consultant
Services to take the Project to 100% design completion and to provide for construction
documents; and
NOW, THEREFORE, said City and said Consultant for the considerations hereinafter set
forth, mutually agree as follows:
SECTION 1 OF THE AGREEMENT IS AMENDED TO READ AS FOLLOWS:
1. SCOPE OF WORK. The Scope of Work of the Agreement is hereby amended
to include the additional work specified in the Additional Scope of Work attached as Exhibit
"A"
SECTION 2 OF THE AGREEMENT IS AMENDED TO READ AS FOLLOWS:
2. COMPENSATION.
A. City shall pay Consultant as compensation in full for such services and
expenses at the rates set forth in the City Center Drive Design Project Proposal, Project Fee
Estimating Sheet, dated April 9, 2007, attached as "Exhibit "A," the total sum for the work is not
to exceed $149,949. Progress payments will be tied to completion of tasks so all payments are
proportional to the work completed. Payment by City under this Agreement shall not be deemed
a waiver of defects, even if such defects were known to the City at the time of payment.
B. Consultant shall submit itemized monthly statements for work performed.
City shall make any payment due within thirty (30) days after approval of the invoice by City.
Payment will be made for the approved amount of the invoice minus ten (10) percent. The ten
(10) percent retained by City will be held until 30 days after final completion and acceptance of
the contract work.
C. Payments due and payable to Consultant for current services are within the
current budget and within an available, unexhausted and unencumbered appropriation of the City.
In the event the City has not appropriated sufficient fiends for payment of Consultant services
beyond the current fiscal year, this Agreement shall cover only those costs incurred up to the
conclusion of the current fiscal year; payment for additional work is conditional upon future City
appropriation.
All remaining provisions of the Agreement and of Amendment No. 1 stand and remain in effect.
IN WITNESS WHEREOF, the parties hereto have caused this Amendment to be
executed the day and year first above written.
CITY OF ROHNERT PARK:
By: /
Name: Stephen Donley (Date)
Title: City Manager
ATTEST:
CITY CLERK
APPROVED AS TO FORM:
161" �' &I , �' S1�
CITY KTTORNE Y
CONSULTANT:
By: /
Name: (Date)
Title.
By: l
Name: (Date)
Title:
E_ A-bit A
C O N S U E T I N O _ E N G i N E E R S
Ref. 02056 06 015
April 16, 2007
Mr. Ron Bendorff
City of Rohnert Park
6750 Commerce Boulevard
Rohnert Park, CA. 94928
Re: City Center Drive Design Project Proposal
Dear Ron:
We are pleased to provide this proposal to the City of Rohnert Park for continued professional
engineering services for the City Center Drive Streetscape Project and Project Management of
Transportation for Livable Communities (TLC) funding conditions. The limits of the City Center
Drive Improvements will begin approximately 450 feet east of the intersection of Padre Parkway
and Commerce Boulevard to the proposed City Park Plaza improvements, approximately 1,300
feet. The attached Site Plan (from Page 15 of the TLC Grant Application) shows the area to be
included as part of this project.
PROJECT UNDERSTANDING
The City of Rohnert Park Community Development staff is working to execute a streetscape
project on City Center Drive (formerly referred to as City Hall Drive and Padre Parkway). The
City has recently received a Transportation and Livable Community (TLC) Grant from the
Sonoma County Transportation Authority (SCTA) to fund construction of the project in three (3)
phases. This work will be done in conjunction with the City Center Plaza Design Project. The
streetscape work is intended to create a Downtown Rohnert Park and provide enhanced
appearance, functionality, safety, and infrastructure. To achieve this, Winzler & Kelly will work
with Gates and Associates landscape architects, the prime on the City Center Plaza Project.
It is understood that the proposed streetscape will include sidewalks, lighting, trees, targeted
bulbouts on State Farm Drive at the City Center Drive intersection, drainage, and other similar
improvements. The area for the proposed street improvements to City Center Drive will be from
the proposed City Center Plaza to 450 feet East of Commerce Boulevard.
For the portion of City Center Drive from the plaza to the west property line of the Town Homes
Development it is intended that the existing curb, gutter, and sidewalk along the north side of
City Center Drive in the area of the two new mixed -use development projects (The Arbor and
City Center Town Homes) shall remain in place where possible. The south side street
improvements across from the mixed -use development projects in this area will include
sidewalk, street lighting and trees, the existing curb and gutter will remain. The landscaping
elements will include improvements consistent with current planning documents ( Rohnert Park
City Center Concept Plan) and will include street furniture /appurtenatices throughout the street
where appropriate.
Mr. Ron Bendorff
April 16, 2007
Page 2
The proposed. work will include three primary tasks.
Task 4 Contract Documents
Task 5 Project Management
Task 6 Construction Services
Our proposal and fee is outlined below for your consideration.
SCOPE OF WORK
TASK 4.0 CONTRACT DOCUMENTS
4.1 60% Plans, Specifications and Opinion of Probable Cost
The purpose of this task is to present the preliminary design including planimetrics, typical
sections and profiles, and technical specifications for City review and approval. These
documents will ultimately be used as the Basis of Design for the Final Design Phases of the
project.
We will prepare plans and preliminary cost estimates. All design shall be in accordance with City
of Rohnert Park Design and Construction Standards. The preliminary plans shall be sufficiently
detailed to serve as the basis of the 90% submittal.
Technical Specifications will be prepared to establish the minimum level of quality acceptable
including relevant reference standards, allowable materials and construction methods, and testing
procedures and acceptance requirements. Winzler & Kelly will also provide editing of the City's
standard bid and contract forms to meet funding agency requirements and the specifics of the
project. Specifications and other document will be prepared using Microsoft Word 2000 software
in CSI format.
We will prepare preliminary plans and an estimate of probable construction costs for the
streetscape improvements proposed along City Center Drive, which will include but are not
limited to:
1. Demolition plans
2. Roadway plans (including curb, gutter, and sidewalk)
3. Grading and drainage plans
4. Utility plans
5. Lighting plans
6. Erosion control plans
7. Striping plans
Mr. Ron Bendorff
April 16, 2007
Page 3
Winzler & Kelly will identify the locations of existing underground utilities that present potential
conflicts with the installation of proposed underground improvements (storm drain /etc. and
optional Joint Trench (JT). Underground utility location services can be used to field locate
underground utilities as an option.
The proposed location for a new reclaimed water line in City Center Drive from City Center
Plaza to Commerce Boulevard will be shown on the Utility Plan. (Tie in to the existing
reclaimed water line may be completed under a separate project.)
Winzler & Kelly will utilize existing improvements where possible (curb, gutter, sidewalk) along
City Center Drive.
4.2 Storm Water Pollution Prevention Plan (SWPPP)
Because the disturbed area is over 1 acre, Winzler & Kelly shall develop the Storm Water
Pollution Prevention Plan as a base plan for the contractor's use during construction. A Notice of
Intent will be prepared for the City's signature and submittal to the Regional Board.
4.3 90% Plans, Specifications and Opinion of Probable Cost
Comments and recommendations provided by the City from the 60% submittal shall be
incorporated into the 90% plan set for the improvement plans as part of this Scope of Services.
Winzler & Kelly will perform the following work as necessary to complete the detailed design of
the project. Design work shall include, but not be limited to, roadway structural sections, street
alignment, grades, curbs, gutters, sidewalks, storm drain facilities, utilities as required, pavement
delineation, striping and signage, and streetlights. Particular care will be provided in the design
of the improvements to ensure acceptable conformance with all adjoining private property
improvements and to provide proper conformance with those properties. All design shall be in
accordance with City Design and Construction Standards.
We will prepare detailed and complete improvement plans for the entire project. Plans will be
prepared at a scale of F=20' (unless otherwise approved by the City). Plans shall include, but
not be limited to, typical street sections, street improvement plans and profiles, grading plans,
demolition plans, construction details, standard details, cross sections, pavement delineation
plans, and streetlight plans.
We will submit one (1) set of reproducible improvement plans and technical specifications to
David Gates and the City for review and approval prior to the preparation of final plans.
Mr. Ron Bendorff
April 16, 2007
Page 4
4.4 Final Plans, Specifications and Opinion of Probable Cost
Comments and recommendations provided by the City from the 90% submittal shall be
incorporated into the Final plans as part of this Scope of Services.
Winzler & Kelly will finalize the Plans, Technical Specifications and Opinion of Probable Costs
to be used as Bid Documents for the City.
Quality Control
Winzler & Kelly will perform an in -house Quality Control effort, including review by senior
staff for the 60 %, 90% and Final plan submittals.
It is anticipated that three formal submittals will be made (60 %, 90 %, Final), requiring three plan
reviews. We will submit fifteen (15) sets of reproducible improvement plans and technical
specifications for each submittal. The third review is understood to be a back -check submittal
only.
Deliverables: 15 Sets Reproducible Plans (22x34) - Each submittal
15 Sets Technical Specifications (CSI Format) - Each submittal
15 Sets Opinion of Probable Construction Costs
Estimate of Costs for Task 4 Construction Documents is $119,895
TASK 5.0 PROJECT MANAGEMENT
Project management of the TLC funding requirements will be provided by Winzler & Kelly as
the design team lead for the streetscape project. Winzler & Kelly will coordinate with the design
team, subconsultants, and the City as required to perform their tasks. At a minimum Winzler &
Kelly will provide the following:
5.1 Attend City Review Meetings
5.2 Attend and Participate in Public Meetings
5.3 Coordinate with Agencies and Other Consultants participating with the Project
(ROW Acquisition, Traffic Study, Geotechnieal). The City will engage services
for a Right of Way (ROW) Acquisition consultant. However, Winzler & Kelly
will coordinate with the ROW Consultant and provide necessary information for
the process.
5.4 Overall Project Management throughout the project, including Progress Reports
and Financial and Project Tracking
Mr. Ron Bendorff
April 16, 2007
Page 5
Estimate of Costs for Task S Project Management is $7,240
TASK 6.0 CONSTRUCTION SERVICES
6.1 Technical assistance will be provided during the contractor solicitation and award
period. Assistance will include the following:
• Response to questions from potential bidders during the bid period.
• Attendance at pre -bid meeting.
6.2 Up to four (4) site visits at the request of City staff..
6.3 Respond to up to fifteen (15) Requests for Information (RFI) submitted by City
staff.
6.4 Review and respond up to six (6) contract submittals.
6.5 Prepare record drawings following the completion of the project. Record
drawings will be completed using clear and accurate markups provided by the
contractor.
Estimate of Costs for Task 6 Construction Services is $20,639
ASSUMPTIONS
1. No hazardous materials will be encountered within the limits of the work area for City Center
Drive Project.
2. No traffic signal or is required for improvements to City Center Drive, or State Farm.
However, design will follow recommendations of the .Traffic Study prepared by W- Trans.
3. CAD files for the existing improvement plans along portions of City Center Drive will be
provided by the City (if they have them).
4. Environmental permitting, CEQA/NEPA documentation, and mitigations have been prepared
by Winzler & Kelly and will be provided as part of the submittal to the Funding Agencies.
5. No geotechnical services are included in our proposal. However, a geotechnical investigation
was prepared for the Road Reconstruction for the Town Homes Development. It is assumed
that Winzler & Kelly will be provided a copy of this report for design purposes. Coordination
with the Geotechnical Consultant that prepared the investigation is included in Task 5.3.
6. The technical specifications will be in CSI format; preparation of the front end documents is
not included in this proposal.
ADDITIONAL SERVICES:
Preparation of the front end documents. Winzler& Kelly can provide this service if
requested.
2. Hazmat review of the project site.
1LL -Y
Mr. Ron Bendorff
April 16, 2007
Page 6
PROJECT FEE
Based upon the estimated hours and reimbursable costs identified on the attached spreadsheet,
our total time - and - materials fee is estimated to be $149,949 for the City Center Drive.
Winzler & Kelly is excited to be assisting you and the City with the development of
improvement plans for the City Center Plaza and City Center Drive Projects. Please contact us if
you have any questions or require any additional information. We are prepared to meet with you
to review and discuss the scope or level of effort if you have any concerns regarding our
assumptions.
PROJECT SCHEDULE
It is anticipated that TASK 4 be completed using the schedule outlined below:
60% SUBMITTAL
May 14, 2007
CITY REVIEW 1
May 21, 2007
90% SUBMITTAL
July 2, 2007
CALTRANS REVIEW
July 30, 2007
FINAL PLANS ONLY
August 20, 2007
CITY AND CALTRANS REVIEW 2
September 10, 2007
FINAL SUBMITTAL
October 1, 2007
Winzler & Kelly is excited to be assisting you with the development of improvement plans for
the City Center Drive Projects. Please contact us if you have any questions or require any
additional information. We are prepared to meet with you to review and discuss the scope or
level of effort if you have any concerns regarding our assumptions.
Sincerely,
WINZLER & KELLY
Margaret Witt,
Project Manager
cc: Wendy Ziegler, Winzler & Kelly
City of Rohnert Park - City Center Plaza
Proposed Project Limits, including Plazaj
Cite C ntcr Drivelliaza hrmlxovaiii tits T'roiect t`l,C: Gfi'a w 119/06
face 15
WINZLER & KELLY - PROJECT FEE ESTIMATING SHEET
Project Name: Rohnert Park Padre Parkway Client: City of Rohnert Park
Prepared by: Maggie Witt Date: April 16, 2007 Project Total: $149,949
LABOR GOSTS' .. FEE COMPUTdTION
LABOR CATEGORY>
RATE >
Task / Item
PIC
$205
/HR
PM /PE
$150
IHR
Tech
$110
IHR
Struc
$135
IHR
Elec
$145
/HR
Clerical
$65
/HR
Total
Hours
'Other
Direct
Costs
Sub
Cons.
Costs
TOTAL
FEE
TASK 4.0
Contract Documents
4.1
60% Plans
3
59
42
3
10
116
$698
$16,513
4.1 a
Landscape Plans
$37,950
$37,950
4.1 b
Specifications
16
5
7
28
$168
$3,782
4.1 c
Opinion of Probable Cost
16
8
3
26
$156
$3,731
4.1 d
Quality Control
7
3
1
10
$62
$1,934
4.2
Storm Water Pollution Prevention Plan SWPPP
4
28
6
38
$228
$5,908
4.3
90 % Plans, Specifications, Opinion of Probable Cost
2
91
98
16
5
5
216
$1,299
$29,271
4.3 a
Incorporate Comments
13
20
3
3
38
$226
$5,049
4.3 b
Quality Control
7
3
1
10
$62
$1,934
4.4
Final Plans, Specifications, Opinion of Probable Cost
6
29
65
5
106
$635
$13,823
SUBTOTAL TASK 4.0
28''
252
238
26
29
17
589
$3;535
$119;895
TASK 5.0
Project Management
5,1
City Review Meetings
14
14
$84
$2,184
5.2
Public Meetings and Participation
2
5
7
$42
$1,202
5.3
1 Coordination with Agencies & Traffic Consultant
1
18
19
$114
$3,019
5.4
Pro ress Report/Financial/Project Tracking
1
4
5
$30
$835
SUBTOTAL TASK 5.0
4
41
0
0
0
0 =-
45
$270
$7,240
TASK 6.0
Construction Services
6.1
Bidding Assitance
4
8
12
$72
$2,092
6.2
Site Visits
6
12
6
24
$144
$3,984
6.3
Respond to Request for Information
4
26
10
8
48
$290
$6,917
6.4
IContractor Submittal Review
4
18
6
28
$168
$4,078
6.5
lPrepare Record Drawings
8
20
28
$168
$3,568
SUBTOTAL TASK 6.0
18
72
;,20
16
0
14 '
140 -'
$842
$20,639 '
Reimbursables
8 -112 X11
100
ISheets
15
JCopies
1 3
1 Submittals
$0.15
Per Sheet
$675
Full -Size Plans
15
Sheets
1 15
ICopies
1 3
ISubmittals
1 $2.00
1 Per Sheet
$1,350
Deliveries
1
1 3
JSubmiftals
1 $50.00
lPerSheet
$150
SUBTOTAL REIMBURSABLES
$2,175
PROJECT TOTAL
50 365 258 42
29
31
774
$4,646
$149,949