2013/11/12 City Council Resolution 2013-151RESOLUTION NO. 2013 -151 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROHNERT PARK AUTHORIZING AND APPROVING FOUR CONTRACT CHANGE ORDERS FOR SEWER INTERCEPTOR OUTFALL PHASE 2 SCWA SPOOL REPLACEMENT PROJECT NO. 2011-04 WITH VALENTINE CORPORATION WHEREAS, the City of Rohnert Park has a contract with Valentine Corporation for the sewer interceptor outfall SCWA spool replacement, Project No. 2011 -04. WHEREAS, in the process of executing the agreement differing site conditions were discovered, namely, that the spool is very close to the high pressure SCWA aqueduct. WHEREAS, as a result of this discovery several changes in the scope of work were required to perform the agreement. WHEREAS, Valentine Corporation provided four change orders, for a total cost of $29,963.02, to complete its work in light of changed site conditions. WHEREAS, staff has determined that the change order price offered by Valentine Corporation is reasonable and was necessary to complete the Project. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Rohnert Park that it does hereby authorize and approve the change orders for the total amount of Twenty - nine Thousand Nine Hundred Sixty -three dollars and two cents ($29,963.02) for the Sewer Interceptor Outfall Phase 2 SCWA Spool Replacement, Project No. 2011 -04, copies of which are attached hereto as Exhibits A through D and incorporated by this reference. BE IT FURTHER RESOLVED that the City Manager is hereby authorized and directed to execute documents pertaining to same for and on behalf of the City of Rohnert Park. DULY AND REGULARLY ADOPTED this 12"' day of November, 2013. CITY OF ROHNERT PARK Pam Stafford, Mayor ATTEST: ° c t�Rr�:' al ¢ 4 VF2 J , Anne M. Buergler, City Clerl�" Attached: Exhibits A through D ` ..... AHANOTU: _(SI BELFORTE: Njt-_ MACKENZIE: t—\�J5 CALLINAN: STAFFORD: % AYES: (5 ) NOES: ( 0 ) ABSENT: ( 0 ) ABSTAIN: ( 0 ) Exhibit "A" CONTRACT GHANGE ORDER No. 001 City of Rohnert Park Sewer Interceptor Outfall SCWA Spool Replacement Project No. 2011 -04 Item: Miscellaneous Additional Work Items DESCRIPTION OF CHANGE: This Contract Change Order shall constitute full compensation to the Contractor to complete the following additional work items: Extra Work Report No. pate Performed Additional Work Description Total 1,0 n/a Upgrade to SST hardware on pipe couplings $ 802.41 2.0 8/1/2013 _ Removal of 11' section of 12" mortar -lined steel ARV pipeline in excavation $ 922.57 3.0 8/6/2013 Removal of excess concrete encasement around SCWA Aqueduct to allow for support installation $ 2,410.95 4.0 8/7/2013 Removal of excess concrete encasement around SCWA Aqueduct to allow for support installation $ 1,148.58 5.0 8/8/2013 Removal of excess concrete encasement around SCWA Aqueduct to allow for support installation $ 3,361.61 6.0 8/9/2013 Removal of excess concrete encasement around SCWA Aqueduct to allow for support installation _ $ 689.16 7.0 8/15/2013 Excavation around sewer main, underneath concrete encasement, to allow for removal of pipe $ 596.75 8.0 8/19/2013 Excavate underneath concrete interference_ $ 669.31 9.0 8/16/2013 Plug sewer line and dewater sewage that entered pit overnight $ 1 594.81 10.0 8/19/2013 Construct pad for storage of contaminated dirt $ 135.04 11.0 8/21/2013 Pick -up materials for extension of SCWA pipeline concrete encasement $ 776.87 12.0 8/22/2013 Installation of forms and rebar for extension of SCWA pipeline concrete encasement $ 3,959.00 13.0 8/23/2033 Pour concrete for extension of SCWA pipeline concrete encasement $ 5,004.39 14.0 8/26/2013 Strip concrete forms, clean -up materials, and haul demolished SCWA pipeline concrete to Stony Pt. $ 1,079.90 3.5.0 8/28/2013 Dispose of excess concrete material surrounding SCWA aqueduct at dump $ 182,93 17.0 9/3.1/2013 Haul and dispose of Contaminated Soil at Redwood landfill $ 4,762.86 REFERENCES: Field Order No. 01 — Misc T &M Items Field Order No. 02 — Concrete Encasernent at 48" Aqueduct L $ 28,097.14 Page ] of 2 Field Order No. 04 -- Disposal of Sewer Contaminated Soil COST OF CHANGE: Add $28,497.94 CONTRACT TIME ADJUSTMENT: None This change order constitutes full and complete compensation for all tabor, equipment, materials, overhead, profit, any and all indirect costs and time adjustment required to perform the above described change, ACCEPTED: Valentine Corporation Project nager: B : G �o Lisa Davis Date: 9 ' f �� City of Rohnert Park Deputy City Engineer: By: Patrick Barnes Date: RECOMMENDED FOR ACCEPTANCE: The Covello Group, Inc, Construct'on Manager: By: �Lk�� Ci y uuz a Date: q~ f g° 1 3 Page 2 oft CONTRACT CHANCE ORDER No. 002 City of Rohnert Park Sewer Interceptor Outfall SCWA Spool Replacement Project No. 2011-04 Item: Removal of Additional ACP ripe for Sampling DESCRIPTION OF CHANGE., Per Field Order No. 03, cut and remove section of 24" ACP force main at a location roughly 300 ft from the intersection of Rohnert Park Expressway and Stony Point Rd, on the SCWA Access Road. The City will excavate, shore and fully expose the pipe. Valentine shall then enter the excavation and cutout the asbestos cement pipe. Once the pipe is removed from the excavation, Valentine shall cut samples of the pipe as required by the tester. Once the tester has the needed samples, Valentine shall remove from the site legally dispose of the ACP pipe. REFERENCES: Field Order No. 03 — Removal of Additional 24" ACP Pipe for Sampling COSTOFCHANGE: Add $3,062,63 CONTRACT TIME ADJUSTMENT: None This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit, any and all indirect costs and time adjustment required to perform the above described change. A CCEPTED: Valentine rporation Proje t n ger. Lisa Davis Date: 10 - /. 13 City of Rohnert Park Deputy City Engineer: By: Patrick Barnes Date: RECOMMENDED FOR ACCEPTANCE: The Covello Group, Inc. Construction Manager: By: la I< m Date: io Page 1 01A s C) m .t1' 'N' M tD O .� 'C? cCD I �_ o h N a o ra 33o U uj YJ N r Ch CO O C) : � tj `t U ro • rt w ° t� cd C U a lu rt d 69 — -- wt,;.].. �. 2 ' �: � LM 4 .00 ii3: i c ..�- f � ! At lu i II I r 1 3 I� U I 2 ' c > I ,( I I . + + c .o 'z i n � G � 1 a i I � � � i L� I•� o � i ! ([ + Nn? + t1 i E, Iz .O ro c c c ° o ro m w Z O o lll i s U v n. M U n m q ' ' r 0 • O r WN' to .J 1 U I i ta a ¢ w i a �� t o a7 Q! i ! - � i p 1 ! i�,II�u I ! F-IN 'c Q :q (� m: ,N,,�.!o _ _ to ,co rl0c) is Q :p E I Q' W ilta1:Q .Oi c7 ;!C7 CD o i Z a q Q N N ! (I i!rl I!�'Ilr ! it ilr:lt —ii :o - t"W q :OO :.Ut .t1' 'N' M tD O .� 'C? cCD I o h N r Ch CO O C) : ut • rt w ° t� a lu a LM i c � At lu i E 3 + I 2 c > . + + c � � U ! ([ + Nn? + t1 i E, Iz .O ro c c c ° o ro m w Z lll i s U v n. n m q ' • O r I O n - � � o a ! - � • tpf 'c Q :q (� 'cY3'ItV7"t3� ,N,,�.!o _ _ to ,co rl0c) is Q lG�l ilta1:Q .Oi c7 ;!C7 CD o ! (I i!rl I!�'Ilr ! it ilr:lt —ii :o ! n. U ! rn is U v t ro E Z + Ed + j d + m ro m o m E `w r iG ;pro E I v ro n �; v u5 Ir ! ,4 W `� 'g ro I E xt E A cn 4 -ro1 E O c a m (: o F 7 0 0 lq H N W !u'i x 'O d :O (A p �� i� N w N U a u r C LL Cr � C Q (0LL J a A(1 L {L' C N a X w W U �i ILU M N � O O h z c ° v°i w CA G) v_ C ° C E m 12 03 oc ? z �� r ❑ ❑� m a o w ° E3 p U w d !S) N 0. H CJ co (Y) N C) o j` m m c� cv `- m 8 m z O � � � •� i7 3' ❑ ❑ c oZ o t' a o2 E E E w z �Z ns N O U z z m u) z E, `° fl. 4 p a C] O - --, C] O Ca � p U x U c> y @ `'• C6 C6 CO v z ? CD Q h i 3y O E CD o y cV r- 7 — att (Y) i LLx m Q ¢ a i CO (� Z ° o C) (D N •R7 Ca C7 i b. •Q1 v C6 () q 6//� 61 .� C' ZO �.1/ V 11J Q N 2 cl 1� (D 3 CO 6 z (7 Q p U C LL x'S. o p p C U M x c CD (D o CD AJ z 0- L io •,- Q �y � c to �- U o Q N v U U U ro > W u N 'CL f- CL (III d Z f� O a� U U U) Z d 2! _ v p� Cl. a 0 ,, > U d W o s u5 i - -- o I E m W W 4-- Y >� E l a S ° Z o n CO ° tr 'S t N G o w O `_ ro @ , 0. uj G ci j✓ z o z o U o m u a q 7 z D � J ' N o � o b p Q i•- O CA O rn d O ay � C C � - N N [�•I Cpl CAF t7 V UJ U/ 2 �i ILU . entine Corporation General Engineering Contractors 111 Pelican Way . San Rafael, CA 94901 P.O. Bnx 9337 • San Rafael, CA 94912 -9337 CONTRACTOR'S LICENSE NO. 229226 PHONE (415) 453 -3732 DAILY 44:; Jab Name: ' pate Per€ormed:-9--4� . Job Number: Location: S`t __�'� { c`1 date of Report: C--�z - -(- YOU ARE HERESY AUTHORIZED TO PROCEED WITH THE FOLLOWING EXTRA WORK: Description of work to be performed: t— Reference Drawing No. i lr�,r f�er� ?�5; 6(C � �' V-'-, - Employee Name Craft Sub Strai ht Time Overtime Premium Time Extended Amount Hours Hate Hours Rate Hours mate t- e r- \k e- ` z- U" tt- tv ec --'S 1 t 66 ` 1^'1 ' A-\ Total Maierial escrip ion t' y' Unit Price Amount .- '� y Total Equipment Hours Rate Amount Total The above Record is complete and correct. .4 Grand Total Performed By: Accepted By: Co Owner /Contractor's Representative Craft Designation: G.F . (General Foreman) J.C. (Journeyman Carpenter) OPR (Operating Foreman) L, (Laborer) APP (Apprentice) P.D. (Pile Driver) C.M. (Cement Mason) Purchase Order No. hite rl� CDIIlsr"CT,Il1N SUPIP5F 016- Concord 1640 Challenge Drive Concord, CA, 94520 (925) 685 -9130 Sold To: 7474000 VALENTINE CORP PO 13OX 9337 SAN RAIZAEL, CA, 94912 415 - 453.3732 Printed By : T1 DANTONO Printed Dnte : 09119I2nt'i m•nn pM PAf-imr- ON RECEIPT OrrirrrriRv! MARK HAAArC 11350380 Ship To, 7060- ROHNERT PARK EXPY & STONY POINT,10000231 167 STONY POINT RD & ROHNERT PARK E,YPRESSWAY -7060 ROHNERT PARK, CA. 94928 Jab Site Contact: MARK HARRIS ,lob Site Phone; blap #; 11350380 0911912013 09/19/2013 White, A k_ SIB _ . ..( µ _ - 1,51ON30 5. Walk In 7060 1�3ri10114, `1' _ '� � ;��T r4 n 1.1 2232300 10" BLACK KNIT 4 4 0 Pit +2. ]749 $8,6996 WRIST GLOVES 1 -00803 3889 LBS US 2.1 444DCO7 T'DRICUTPREMIUM I 1 4 EA $60.2205 $60.2205 TURBO DIAMOND I•CW01 BLADE BRIGADE R4 LBS US 3.1 123BTIODOC 3 "XI000'YELLOW 2 2 0 RL $9.35 $18.70 CAUTION TAPE I -BO703 1.12 LBS US 2 -FI104 4.1 161683368 2 "X60YRD RED DUCT 3 3 0 RL S10.2207 530,6621 TAPE 213 I -80702 1.71 LBS US 2•BOB07 5.1 4326208 61M1L20'XI00' BLACK 1 I 0 RL S99.99 $99.99 POLYFILM VISQUEEN 1 -H0502 57.4 LAS US 6.1 444BRI2357 55GAL3MILBLACK j j 0 BOX $29.6577 $29.6577 TRASH BAG 30CT I -FFC03 BRIGADE 12.3 LBS US ON ACCOUNT Cp1SlSFHUCTlpN S�IPFLY 016 - Concord 1640 Challenge Drive Concord, CA, 94520 (925) 685 -9130 Sold To: 7474000 VALENTINE CORP PO BOX 9337 SAN RAFAEL, CA, 94912 415 -453 -3732 Printed By : TJ DANTONO Printed Date : ❑9ttO/ m A m•nn nne oe rrmrl RECEIPT ("1111 13111 1R A- 11Anat <n 11350380 Ship To : 7060 - ROHNERT PARK EXPY & STONY POIN'T.10000231167 STONY POINT RD & ROHNERTPARK EXPRESSWAY -7060 ROHNERT PARK, CA, 94928 Job Site Contact: MARK HARRIS Job Site Phone: Map 4: Page 2 or 3 r -- - - - - -- - • °•• --••- a,.Vll tit 111 LIV lIL -i 11350380 • - � •�} •�" ° 09/19/20y13�, 09119/2013 White, A _ _�i13Ie ' „ ,5%i 1.51 ON30 _n. .. i� 9^1,..ir?!J_t?.r�i c,. .•� . tz7ll s= 5, Walk In 706e D;wtono, T 7.1 590C3XLG 3XL. HOOD & BOOT 4 4 0 EA $8.6359 $34.5436 1 -BO807 WHITE COVERALL TYVSK .44 LBS US 8.1 1212091 2PK HEPA FILTER P100 3 3 0 PKG $9.5459 $28.6377 I. 130703 2091 3M .01 LBS US `3.1 12167.00 AMED RESPIRATOR 6200 1 ] 0 EA SI4 $145509 1 -B0702 LO MANi TENANCE3M -5509 7.28 LBS us 10.1 4441TR141849 3.50AL 0 EA &29.7955 $29.7255 SPRAYER 24" W AN D 1-AECL BRIGADE _..._.. .49 LBS us- _. Page 2 or 3 �nrsr>tuGrraru Surr�.r , 016 - Concord 1640 Challenge Drive Concord, CA, 94520 (925)685 -9130 Sold To: 7474000 VALENTINE COR P PO BOX 9337 SAN RAFAEL, CA, 94912 415 -453 -3732 ON ACCOUNT RECEIPT ililll:' lli�liil6 'lli�iilllliillll�t(Illilfi 11350380 Strip To ; 7060- ROHNERT PARK EXPY & STONY POINT, 10000231167 STONY POINT RD & ROI INERT PARK EXPRESSWAY-7060 ROHNERT PARK, CA, 94928 Job Site Contract: MARK HARRIS Job Site Phone: Map #: Shipped amount $355.39 Order charges $0.00 Tax amount $3X.95 Lumber Tax rate/amount 1.00% $0.Q0 Order total $387.34 Deposttlfunds tendered $0.00 Balance due $337.34 PRINT: SIGN REPORT DISCREPA NCIES W ITI-IIN 24 HRS. IF YOU DIDNT RECEIVE THE SERVICE YOU EXPECTED CALL JAMES JACKSON 916-997-9524 NO REFUNDS OR EXCHANGES ON NON STOCK 114ERCHANDISE SEE REVERSE SIDE FOR TERMS AND CONDITIONS mYSVmuITI' CAP COM SHIPPED WEIGHT: 89.03 LBS PULLED BY: CHECKED BY: LOADED BY: These PrOdutts Contnur Chendcals Known To The State Of California To Cause Cancer And Birth Defects Or Other Reproductive Harm Page 3 of 3 Redwood Landfill ;M1= . Rat e. �Tast �_________________ �-' A 8950 Redwood HWY W�Q- origin 1 Alb Non Fri-Cubic. yards- - Original Novato, CA, 94948 -___- c FUEL -Fuel 6larchar.ga - La._ 1{4t 5 Ti.cket#1 1270415 561.04 R Rohner t p Ph: (415) 892 -2051 customer Name Val8ntinecorP Valentine CorP Ticket Date 09/20/201v Carrier 700 Inbound Beneric GarrierY Payment Type Credit Account Vehicle# 10 YRD Val ?tt�e Manual Ticket## Container . 7rtArJii YOU. . £S•ApflUA.ifAAGlI R Route Driver volahra, corral a, lam a e explosiulet hazardo s Hauling Ticketf# check# Destination Billing# 0000174• f='Q## 7060 Tire Grid ��� Q •� 2-2— Scale operator In 09/20/2013 12:50 :,,4 Scalel - Inbo SAS Inbound Gross Out 09/20/2013 12 :50:34 SAG Tare Net Comments 814620GA Tons Product ;M1= . Rat e. �Tast �_________________ �-' A Amount o origin 1 Alb Non Fri-Cubic. yards- - ---------- ___- __------- - -- - -__ - - - -___- c FUEL -Fuel 6larchar.ga - La._ 1{4t 5 X1.04 .': 561.04 R Rohner t p RCR- p- Regulatory``C'ds Re1C�0 Y =`;r`T '0 5 56.80 R Rohnet't P !+ frUF -L- Standard E~nvi nMe` `.1100; _ _• 10 $ $1.58 R Rohnert P .. = $14. +�0 Rnhrrert P . 7rtArJii YOU. . £S•ApflUA.ifAAGlI R O r may Y r volahra, corral a, lam a e explosiulet hazardo s rrratetr'P S Drlver s Tntal Tic ?oe ket IanJi7tlohabrGty, na u $83.4 . Exhibit "C" CONTRACT CHANGE ORDER No. 003 City of Rohnert Park Sewer Interceptor Outfall SCWA Spool Replacement Project No. 2011 -04 Item: Corrosion Tape for Pipe Couplings DESCRIPTION OF CHANGE: Per RFI No. 4 response, Contractor shall wrap the new pipe couplings with 6' wide 60 mil corrosion tape after installation. REFERENCES: RFl No, 04 COSTOFCHANGE: Add $853.26 CONTRACT TIME ADJUSTMENT. None This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit, any and all indirect costs and time adjustment required to perform the above described change. ACCEPTED: RECOMMENDED FOR ACCEPTANCE: Valentine Corporation Project ger: By. C•� c Lisa Davis Date: 1 City of Rohnert Park Deputy City Engineer. By: Patrick Barnes Date: The Covello Group, Inc. Construe 'o Manager: By: Cl y Ku a Date: to Page 1 or 1 :79 u. Lp !ld 6 mi Ax� 10. :I LLJ C) 0- LLJ a) yj < cq w W L) W L) E.) ca CD L3 :C).-O;.(N: CL ic-) LLJ C) 0- LLJ a) yj < cq w W L) CD 0 :C).-O;.(N: CL ic-) M a) ii j 2 :m 0 U C ¢ cc LLJ C) 0- LLJ a) yj < cq w W L) CD 0 :C).-O;.(N: CL M a) CL 2 :m 0 U C ¢ cc U) 2 LO co- Lo co 0 4- LL. + E + 10 Z) t9 CD 0 :C).-O;.(N: o :m LO co LO co- Lo co + 9 + Z) t9 a p LL CL + 43 + + R z 0 OL d, ;5i f6 E U) an rL r j2 tu CD (C) 0') (M C\l LO C) N'!O C), C� C) C:� IC)!!C) C6 , L C) .0 , C) oo! y d) El fa L U1 E (Al + Im V3 m -9 2 is w to I E C) .00 cr 0, LU 7E 1§ LU E ks, E to w I • i3 :�15 �65 ni 0 LO U-) -- oi N (Y) 6 Ln Z Q ca 00 24 r- 'n tj E E N W C 0 5 L11 CD cc is it jgip z i 12. lz E S to. 0--.: --------- a: .;j 12 Al c -LI iLU+M rz co id LU CL! — ---------------- CD LO LU v I ,q I 0 C> I �p , 1 1 i CLI C) CL )L Y) CD o Li LL U) tl O 10 LL, to C :al eu c IG W LU 1 i 4- 4 < < a Co cr) a Itu ILI X w n l o o I o Q o f m rn I cp - ----------- m C5 !'L m G c l` A Ci)l4fSTRUCT/OtN SUPPLY Credit Services 601 W, Church Street, Oriando, FL 32805 -2247 I�ECEIVED ENROLLMENT'.. ''. HKX ARV AUG 2 7 2 SOLD Td: 7474000 8354 1 AO 9.984 E0111X 10193 D769347970 P1674708 0001,I0061nane Corp, lIIlull�lrrlll=Illtr =Irr, == rl�rrr ,Il #Ir�lr,r�III, Nirrlll,rl VALENTINE CORP k PO BOX 9337 SAN RAFAEL CA 94912 -9337 BRANCH ADDRESS 026 -SANTA ROSA (707) 586 -4330 300 EAST TODD RD SANTA ROSA CA 95407 INVOICE NUMB[ii:`' 50000387065 INVOICE DATE -_ 48119/2013 CUSTOMER- PO-NLIMBER. ' 11075831 TERRITORY: " 'PLEASE REMIT PAYMENT-TO: SHIP TO: 7474999 HDS WHITE CAP CONST SUPPLY P -O. BOX 6040 CYPRESS, CA 90630.0040 YARDNALENTINE CORP -STOCK 111 PELICAN WAY SAN RAFAEL CA 94912 .`;::ORDERDA7t:';':' :;_.- ;..-..:'ORDERNO= t "'.i::`., ':;F:':'.�:ORpEREDBY -• ., - - •. .;.•ACCOUNThtAHAGERt:�. -'-; .'.•.;.: - _- " ?-TANENBYi..'�: :::._.:-.._ 08/15/2013 11075831 LISA DAVIS WHITE, ANDY A WHITE, ANDY A .o,.. :ACCTAOeND.`•,:..,_: ;:`rfR#ds .:.. .. ... ,. •,. .''SHIP. VII 7ROUTING'' CUSTOMER'J08 N0.' 026 7474999 1,5% 10 (JAYS NET 30 3. UPS - ,sLINEi_;.,i: .:z._PART NU,41eER;':' < >:_SP- TAXI:- 1 SP60MILAC6 6 °X 50' 50MIL ANTICORROSIVE TAPE 6 113.45 RL 0 6 680.70 611.2E APPROVED IMPORTANT: Effective Friday, 0410112013 please note the fallowing change to our remittance address: OLD ADD I=SS HDS White Cap Const. Supply Dept. 33020 P.O. Box 4133020 San Francisco, CA 94139 NEW ADDRESS; HDS White Cap ConsL Supply P.O. Box 6040 Cypress, CA 90630 -0040 For questions regarding this invoice please call 1 -800- WHITECAP TOTAL. GROSS 680.7( (1 -800. 944 - 8322). TOTAL TAX • 61,2E NO REFUNDS OR EXCHANGES ON NON STOCK MERCHANDISE Visit htip: l/ whitecap. GOmlml sclterms_and_condlllons.pdf to view complete terms and TOTAL SHIPPING conditions. AND HANDLING O.00 RECEIVED BY; UPS-DAVIS SIGNATURE COPY ON FILE 741,9E Please verify that tha rerril! io address you are using agrees to Ehe.address 5hotvn'at the top of this invoice. p.n. i ,f 0001;0001 _.. -. ...... _ . _ RECEIVED BY CN S ay s V. MATERIALS A. Street laterals shall be Polyvinyl Chloride (PVC) or ductile iron pipe. B. Gravity server mains tip to arid including 18 inches will be PVC (SDR 26 minimum), or firsion- welded HDPE. PVC joints shall be wrapped with 60 mil 6- inch wide corrosion tape. Exceptions must be approved by the City. Engineer. 4. C. Materials for pipes larger than 18 inches must be approved by the City Engineer. D. Seaver force mains shall be constructed to Waterworks Standards using AWWA C900 PVC, Fusion Welded HDRE, or a Polyurethane or Epoxy lined Ductile Iron Pipe. E. If a gravity sewer main is installed outside of a paved roadway, ductile iron pipe and sewer identification tapd is required. F. In general, use the same pipe material from structure to structure. G. Use of Asbestos Cement Pipe is not allowed under any circumstances. H. Gravity sewer mains within 50 feet of a well or 200 feet from a stream shall be constructed to Waterworks Standards using A W WA C900 PVC, Fusion Welded HDPE or Polyurethane or Epoxy lined Ductile Iron Pipe in areas outside of roadway. . V.T. ALIGNMENT Any deviation in clearances from the requirements of the Standard Drawings, the "California Waterworks Standards" and criteria for water main separation set forth under Title 22 of the California Code of Regulations, must be approved in advance of the plan submittal by the California Department of Public Health (CDPH) and the City Engineer. Additional requirements may be unposed for such deviations. A Horizontal 1. Horizontal separation from other utilities, such as gas, underground electric, underground television cable, etc., will be a minimum of four feet clear between the pipes except at crossings. Horizontal separation from other sewer lines and storm drains shall be 5 feet. 2. In general, design public sewer mains in straight street sections to run parallel to the street centerline. All public mains must be a minimum five feet clear from all structures, building overhangs, gutters, property lines or edge of easements and 3 feet clear from all monuments, and /or Iips of gutters. The alignment will be designed so that any 48 -inch manhole shall be centered a minimum of 3 feet from the lip of gutter and any 60 -inch manhole shall he centered a minimum of4 -foot from lip of gutter. Design Standards SA Volume 1 for Public Improvements Revised July 2009 Exhibit "D" City of Rohnert Park Sewer Interceptor Outfaii SCWA Spool Replacement Project No. 2011-04 Item: Credit for CCTV Inspection DESCRIPTION OF CHANGE: The City waives the requirement per the project plan coversheet, Spec 10- 2.03.8.1, and City Std 530, to video test the sewer main after the project is complete in lieu of a cost credit to the City. REFERENCES: RFQ No. 01 COST OF CHANGE: Delete $2,050.00 CONTRACT TIME ADJUSTMENT: None This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit, any and all indirect costs and time adjustment required to perform the above described change. ACCEPTED: Valentine Corporation Project C M er: _ Lisa Davis Date: ) p , City of Rohnert Park Deputy City Engineer: By: Patrick Barnes Date: 57.04 56N RECOMMENDED FOR ACCEPTANCE: The Covello Group, Inc. Construction Manager: By: Cay Kuz a� Date: /o Page 1 of l