2014/02/11 City Council Resolution 2014-011RESOLUTION NO. 2014 -011
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROHNERT PARK
AUTHORIZING AND APPROVING A DESIGN PROFESSIONAL SERVICES
AGREEMENT FOR THE ROHNERT PARK INTERCEPTOR OUTFALL GRAVITY
SECTION REHABILITATION PROJECT NO. 2011-04 WITH BRELJE AND RACE,
INC., FOR DESIGN REVIEW AND CONSTRUCTION MANAGEMENT
ENGINEERING SERVICES
WHEREAS, on November 6, 2013, staff issued a Request for Proposals ( "RFP ") for the
Interceptor Outfall Gravity Section Rehabilitation Project No. 2011 -04 ( "Project ") to identify a
qualified consultant that can assist the City with the design review and construction management
of the Project;
WHEREAS, the City of Rohnert Park Municipal Code Title 3 Chapter 3.04 provides that
the city's purchasing functions shall be governed by the city's purchasing policy; and
WHEREAS, consistent with City of Rohnert Park Purchasing Policy Section 3.6.6(D),
the City prepared a Request For Proposals and received four proposals on December 3, 2013;
WHEREAS, the City project team chose Brelje and Race, Inc., for an award of contract
due to their (1) quality of team and ability to staff the Project, (2) experience and expertise in this
particular type of work, and (3) understanding of the Project as demonstrated in the selection
process; and
WHEREAS, the City has entered into a Master Agreement with Brelje & Race dated
February 25, 2011 ( "Master Agreement "), and additional work may be authorized under that
agreement via Task Order.
NOW, THEREFORE BE IT RESOLVED that the City Council of the City of Rohnert
Park authorizes and approves a an additional task order under the Master Agreement by and
between Brelje and Race, Inc., a California corporation, and the City of Rohnert Park, a
municipal corporation, for design related services for the Interceptor Outfall Gravity Section
Rehabilitation Project No. 2011 -04, for a not -to- exceed cost of $130,920.
RF. IT FTTRTNF.R RF.001,VF.D that the City Mnnnuer is hereby authorized and
directed to execute this Task Order for and on behalf of the City of Rohnert Park in substantially
similar form as shown in Exhibit A, subject to minor modification by the City Manager or City
Attorney.
DULY AND REGULARLY ADOPTED this 11 `" day of February, 2014.
2014 -011
ATTEST:
41nne Buergler, City Clerk
Attachment — Exhibit A
BELFORTE: MACKENZIE: MCI STAFFORD: I ( AIIANOTU: _fk-4r-, CALLINAN: i� 'YC
AYES: ( ) NOES: ( 0 ) ABSENT: ( J ) ABSTAIN: ( c )
2014 -011
CITY OF ROHNERT PARK
19 Ez
Joseph T. 11inan, Mayor
ATTEST:
41nne Buergler, City Clerk
Attachment — Exhibit A
BELFORTE: MACKENZIE: MCI STAFFORD: I ( AIIANOTU: _fk-4r-, CALLINAN: i� 'YC
AYES: ( ) NOES: ( 0 ) ABSENT: ( J ) ABSTAIN: ( c )
2014 -011
Exhibit A
BRELJE & RACE TASK ORDER NO. 2014 -02
CITY OF ROHNERT PARK
AND
BRELJE & RACE
AUTHORIZATION FOR ENGINEERING SERVICES FOR
SEWER INTERCEPTOR OUTFALL GRAVITY SECTION REHABILITATION
PROJECT NO. 2011 -04
SECTION I —PURPOSE
The purpose of this Task Order is to authorize and direct BRELJE & RACE to proceed with the work
specified in Section 2 below in accordance with the provisions of the MASTER AGREEMENT between
the City of Rohnert Park ( "City ") and BRELJE & RACE ( "Consultant ") dated February 25, 2011.
SECTION 2 — SCOPE OF WORK
The items authorized by this Task Order are presented in Attachment "A" - Scope of Services.
SECTION 3 — COMPENSATION AND PAYMENT
Compensation shall be as provided in the MASTER AGREEMENT between the parties hereto referenced
in SECTION I above. The total cost for services as set forth in SECTION 2 shall be actual costs (time
and materials) based on Consultants' standard labor charges in accordance with the provisions of the
MASTER AGREEMENT and as shown in Attachment "B" for an amount not -to- exceed $130,920.
SECTION 4 — TIME OF PERFORMANCE
The work described in SECTION 2 shall be completed on approval of the design /contract documents, or
as extended by the City Manager.
SECTION 5 — ITEMS AND CONDITIONS
All items and conditions contained in the MASTER AGREEMENT for professional services between
City and Consultant are incorporated by reference.
Approved this day of , 20_
CITY OF ROHNERT PARK
Darrin Jenkins, City Manager (Date)
Per Resolution No. 2014- adopted by the Rohnert
Park City Council at its meeting of February 11, 2014.
BRELJE & RACE
By: Name and Title
BRELJE & RACE
By: Name and Title
(Date)
(Date)
Proposal for Engineering Services
EXhibl City of Rohnert Park Interceptor Outfall
Gravity Section Rehabilitation Project
PROPOSAL B DESIGN REVIEW / VALUE ENGINEERING AND CONSTRUCTION
MANAGEMENT
Design Review and Value Engineering
Brelje & Race's role as the design review and value engineering consultant will be to check the work of the j
design engineer and provide recommendations for improvements to the design to lower costs, provide a
better product and avoid change order work or construction claims during the construction phase.
Task 1.01 Review Preliminary Design Memorandum
A review of the preliminary design memorandum will be
conducted with focus on the items listed herein as critical
to the design, namely the thoroughness of the research
performed for the lining material options, the calculations
for existing piping thickness /strength requirements and the
ensuing liner thickness selections, hydraulic modeling and flow
calculations methodology, thoroughness and accuracy of the
site review and constructability. The cost analysis will also be
reviewed.
During the review of the preliminary design memorandum
Brelje & Race would conduct a general field reconnaissance.
The reconnaissance will provide an awareness of any special
circumstance that may influence the project intent, potential
construction limitations and circumstances that may have significant project cost influences. After review
and analysis our findings will be summarized in a project memorandum. A meeting will be held to review
Brelje & Race's comments with the City and design engineer, An agenda for the meeting and follow -up
meeting minutes will be provided if not being provided by the design engineer.
Task 1.02 Review 60% Design Submittal
Design drawings will be reviewed for limits of utility replacement, alignments of piping, clearness of pipe
rehabilitation methods and constriction notes, profile information, sewer manhole riser replacements or
rehabilitation, and locations and extent of piping replacement ahead of lining (if needed). The drawings will
also be reviewed to determine if pavement /surface repair locations are delineated and if they arc compliant
with City Standard details.
Brelje & Race will conduct a field review of the proposed alignment and compare the topographic
information included on the drawings to the existing field conditions. Conflicts between existing utilities and
those that are proposed in the design will be determined. Constructability issues will be addressed.
Our staff wilt perform a cross check to determine if, for what is shown on the drawings, there is a
corresponding specification section to address the planned improvement. We will compare the specification
scope and completeness to those that have been commonly used for other successful sewer rehabilitation
projects. We will ensure that bid items are clearly defined and that an appropriate means of payment for each
item of work has been included.
Brelje & Race will review the cost estimate to determine if all items of work shown on the drawings are
included in the cost itemization. Unit costs will be compared to recent bid tabulations for like projects
where data is available. A critical look will be taken to determine if items that will be part of the contractor's
indirect project costs are included in the preliminary cost estimate.
Brelje & Race will compare the 60% submittal documents to the pre - design memorandum to determine
if all the stated information in the memorandum have been incorporated or otherwise addressed. Inquiry
regarding the status of all necessary permits will be made. A 60% review memorandum with itemized
Page 16 Bre1je NSUITING LN "aG��
Proposalfor Engineering Services
City of Rohnert Park Interceptor Outfall
Gravity Section Rehabilitation Project
coinnnents by sheet number or specifications section will be completed and distributed to the City and the
design engineer. A follow -up review meeting will be held between the design engineer, City and Brelje &
Race to discuss and reconcile the review comments. Brelje and Race will prepare the agenda for the meeting
and provide written minutes if not in the scope of the design engineer.
Task 1.03 Review 90% Design Submittal
Design drawings at the 90% level will be reviewed for notes and details, ambiguities, conflicts,
cons tructability, compliance with the City's "Design Consultants Requirements" and bidability. Project
specifications will be checked for accuracy of bid quantities, bid item descriptions, specification
thoroughness, appropriateness of material selections and testing methods and requirements.
The contract documents will be reviewed for their conformance to City Standards and with accepted
standards of professional and technical practices with respect to appropriateness of the design for its
intended use, completeness of the plans and specifications and their suitability for bidding and construction.
The construction cost estimate will be reexamined and compared to the 60% submittal to make certain that
items that have been added to the project are included in the 90% estimate. An update on permit status will
be requested.
A review memorandum will be completed and distributed to the City and the design engineer. A follow -up
review meeting will be held between Brelje & Race, the design engineer and City to discuss and reconcile the
review comments. Brelje and Race will establish the agenda for the meeting and provide written minutes in
not included in the design engineer's scope.
Task 1.04 Final Submittal Review
A check of the final submittal to determine if all comments for the 90% review have been incorporated in
the documents will be completed. A brief memorandum confirming bid readiness will be issued.
Construction Management
Brelje & Race's work during the construction phase of the project will consist of a comprehensive range
of services to provide the City with the highest level of assurance that the project is being conducted in a
manner that is safe, minimizes complaints, results in a properly performing finished product conforming
to the construction contract documents, and minimizes the City's exposure to risk and cost overruns.
This comprehensive range of services is understood to include the four general categories of Contract
Administration, Construction Management, Field Inspection and Geotechnical Observation and Testing.
Included within the RFP was a 20 -point listing of construction phase services desired by the City. We
consider this list to be well- conceived, covering all of the above listed general categories, and as such, have
included it below as the basis for our Work flan. Comments have been inserted beneath some of the service
tasks where merited, and a few items (Tasks 2.21 and 2.22) have been added to the end of the list to more
completely convey our understanding of a full- service approach to construction management.
Task 2.01 Pre- Construction Meeting
Conduct the pre- construction meeting, which will include the City, the design engineer, contractor, and major
subcoiitsactorS. Prepare agenda Gild iiuirUtc for the pre- COiistrucUoii iiiecting. I ine piecUll'auut-Uuin illluuurig
shall include a discussion of all items pertinent to the successful performance of the contractor leading to
smooth completion of the project.
Our approach to organising pre- construction meetings is intended to result in all parties to the project being
appropriately represented. Discussions during the meeting will establish a clear understanding of communication
protocols and each party s responsibilities for the duration of the project. This is also the time to point out any
irregular or non - standard n,,ork items, sequence of work and e- pectations regarding the contractor's field and office
support perfomlance.
Page 17 Breli INSULT NG LV nee
0 1 E(2!)
Task 2.02 Project Meetings
Conduct and document progress meetings and other special
technical meetings on a weekly or bi- weekly basis. Prepare
and distribute agenda describing key issues, schedule status,
potential change orders. Prepare minutes of the meetings.
Task 2.03 Schedule Management
Review contractor's as- planned schedule for conformance
with the specifications and for reasonableness of activity
duration and sequence. Coordinate review comments by the
City and the designs engineer and transmit review continents
to the contractor. Meet with the contractor to discuss and
clarify any significant issues. Review revised schedules as
required. Review work progress as compared to the as-
planned schedule and notify contractor of schedule slippage.
Analyze schedule to determine impact of the weather
and change orders on the construction schedule. Review
contractor's updates of the construction schedule which
incorporates actual progress, weather delays, and change
order impacts.
Bre je Race feels it is important to require the Contractor
to produce a weekly 3 -week, "look, - ahead" schedule as a
means to keep the overall project schedule current.
Task 2.04 Maintain Project Records
Maintain project records including submittals log, daily
logs, inspection reports, compliance testing results, photos,
measurement of quantities, schedules and correspondence.
Task 2.05 Prepare Weekly Reports
Prepare and submit to the City a weekly project status report
including construction progress summary, construction cash
flow and payments, and sunntnary logs for proposed change
orders (PCO's) and change orders.
The City requires a monthly report, however our practice
has been to provide a weekly or sometimes bi- weekly t pdale
r�ia email. This ensures that the City's prTect munuger is
kept fully informed and records are incorporated in u timely
and accurate manner.
Task 2.06 Review Monthly Progress Payments
Evaluate the monthly progress payment requests from
the Contractor, negotiate differences over payment, and
recommend payment to the City.
Proposal for Engineering Services
City of Rohnert Park Interceptor Outfall
Gravity Section Rehabilitation Project
At the beginning of the project, Bre je & Race will review the Contractor's Initial Cost Breakdown for accuracy,
which is then used to establish the form of Progress Payment Requests. Submitted progress payment requests are fully
reviewed by both Bre je e- Race fieldpersonnel and the Construction Manager before forwarding to the City with
recommendations for payment.
Page 18Tre1j CONSULTING
Proposal for Engineering Services
City of Rohnert Park Interceptor Outfall
Gravity Section Rehabilitation Project
Task 2.07 Requests for Information (RFIs) and Requests for Clarifications (RFCs)
Coordinate and manage the RFI and RFC evaluation and response process. This includes log, transmit to the
design engineer for response, coordinate with design engineer on field status, track progress, review response,
and transmit response to contractor.
Task 2.08 Potential Change Orders (PCOs) and Change Orders
Coordinate and manage the change orders process, including log, review in conjunction with design engineer
and City, assist with determination of changed conditions and scope definition as needed, assist with
negotiation, and incorporate change orders into the construction contract.
It is vital that PCO, Change Orders and Force Account work are evaluated, negotiated, tracked and ftnali .Zed
in such manners that result in prompt and accurate determination oj' the costs involved. We also encourage the
Contractor to prepare extra work requests immediately and submit with each monthly progress payment request in
order that accurate project accounting and budget status stays up to -date.
Task 2.09 Coordinate Submittal and Shop Drawing Review Process
Coordinate and manage the submittal /shop drawing review process. This work includes log, transmit to
design engineer for response, coordinate with design engineer on field status, track progress, review response,
and transmit response to contractor.
Task 2.10 Permits Compliance
Monitor Contractor compliance with construction permits and CEQA mitigation measures. Coordinate with
design engineer for compliance. Recommend course of action to City if required measures are not being met
by the Contractor.
Task 2.11 Monitor Construction Record Drawings
Monitor construction record drawings maintained by the Contractor and inspector on a regular basis.
Provide to design engineer upon project completion for accurate creation of Record Drawings.
Task 2.12 Claims Management
Analyze potential claims for additional compensation that are submitted during the construction period
and make recommendations to resolve them. Perform claims administration, including coordination and
monitoring claims response preparation, logging claims, and tracking claitns status.
Task 2.13 Field Inspection
Provide construction inspection to monitor the Contractor's work for compliance with the contract
documents.
Task 2.14 Photograph or Video Documentation
Prepare a video or photo documentation of initial site conditions prior to Contractor's commencement of
construction. Provide additional photos of construction progress.
Construction prouress photos will carry date stamps for easy cross- reference with daily inspection reports. Daily photos
are incorporated into our daily inspection reportc.
Task 2.15 Field Changes
Document field changes to the Drawings and Specifications.
Task 2.16 Inspection Reports
Prepare and review Daily Inspection Reports.
Bre je 6 .Dace utilises standardised, in -house developed forms for Daily Inspection Rtportr and Weekly Working
Days Statements to aid efficient recordkeeping.
Page 19
Bret/ e
CIVIL ENGINEERS
Proposal for Engineering Services
(W City of Rohnert Park Interceptor Outfall
Gravity Section Rehabilitation Project
Task 2.17 Geotechnical Observation
Brelje & Race will subcontract with RGH, Inc. for geotechnical observation and testing and materials testing
services, as required.
A small budget has been included, however, geotechnical services may not he necessary for this project.
Task 2.18 Substantial Completion and Punch List
Schedule with City and the design engineer, conduct substantial completion inspections and issue punch lists.
Task 2.19 Project Documents
Provide the City with a complete set of all records of the project, indexed and properly filed, and a listing of
warranties provided under the project including the items covered and the warranty duration.
Bre je & Dace widprepare a set of fresh redline plans that consolidates field set mark -ups at the end of the prod.
It is our understanding that Record drawings are to be prepared 4 the design engineer, based on the field set mark-
ups.
Task 2.20 Notice of Completion
Prepare the final pay estimate and balance change orders, prepare the Notice of Completion, and coordinate
retention release.
Task 2.21 Worksite Safety and Liability Awareness
Brelje & Race has an Injury and Illness Prevention Program in place that, in part, establishes clear procedures
for maintaining awareness of the risks and liabilities associated with worksite safety practices. Although the
Contractor is solely responsible for worksite and worker safety, our field personnel are trained to recognize
imminent and flagrant threats to life or safety and, consistent with normal standard professional care, will
promptly notify the Contractor and the City when such conditions are recognized. A copy of our IIPP can
be provided upon request.
Task 2.22 Public Relations - Outreach and Communications
Initial notifications to locally affected homes and businesses shall be prepared and delivered by Brelje & Race.
All notifications shall receive review and approval by City Staff prior to delivery.
We will also ensure that Contractor provides required public notifications of construction activity. Brclje
& Race will act as the primary contact for the public during construction, maintain a log of complaints
including the name and address of the person complaining, date and nature of complaint, date the
Contractor was notified and the action taken (with date) to resolve the complaint.
Pa g e 20 BreliR Raa
ce
ANSTNG CIVIL
Proposal for Engineering Services
M Exhibit "B° City ofRohnert Park Interceptor Outfall
Gravity Section Rehabilitation Project
FEE INFORMATION
Task, Work Hour and Cost Tabulation work sheets have been prepared, one for each area of Service:
Design, Review and CM. They have been prepared based on the City's required time frame for design
services, the construction time estimated for the completion of the project, and an assumption based on
our experience of the time necessary to devote to the specific project tasks. Each work sheet identifies the
specific project task and sub -tasks to be performed, the individuals responsible, and their expected time to
complete the specified tasks. The work sheets tabulate the total estimated fee based on our 2014 billing rates,
which will become effective on March 1, 2014. The Cost Tabulations are shown in the following pages, and
our 2014 Services Rate Schedule has been included on the next page. The 2014 Rate Schedule reflects an
approximately 5% increase in fees over our current, 2013 fees which will remain in effect through the end of
February. Assumptions and limitations for the costs proposed have also been included immediately following
the Services Rate Schedule.
Proposal. B - Task 1 Services for Design ReviewNalue Engineering
Brelje & Race proposes to complete the Design Review services as outlined herein on a time and materials
basis with a not -to- exceed budget limit of $16,420. These services will be billed monthly based on actual
time and materials expended by staff and will not exceed the set budget without prior, written approval.
Proposal B - Task 2 Services for Construction Management
Brelje &Race proposes to complete Construction related services as outlined herein on an actual time and
materials basis with a recommended budget allowance of $114,500. This budget is based on our experience
and the expected duration for a project of this nature. Our services will be billed monthly on an actual T &M
basis, however the final fee may be subject to adjustment based on several factors including time allowed for
the contract construction, the methods employed by the contractor, and other factors that are not possible
to predict prior to design and construction. Should our fees approach the budgetary allowance ahead of
project completion, B &R will prepare a revised estimate and propose an amended fee amount for the City's
consideration.
Page 22 r °l a -SW JDA.Cace
Proposal for Engineering Services
(w City of Rohnert Park Interceptor Ontfall
Gravity Section Rehabilitation Project
PROPOSAL B. DESIGN REVIEW - VALUE ENGINEERING
TASK, WORK HOUR AND COST TABULATION
INTERCEPTOR OUTFALL - GRAVITY SECTION REHABILITATION
CITY OF ROHNERT PARK
Page 24 r
l . `Ct7NSULTING CIVIL
Proposalfor Engineering Services
City of Rohnert Park Interceptor OuOWI
Gravity Section Rehabilitation Project
PROPOSAL B. CONSTRUCTION MANAGEMENT
TASK, WORK HOUR AND COST TABULATION
INTERCEPTOR OUTFALL - GRAVITY SECTION REHABILITATION
CITY OF ROHNERT PARK
Page 25 Bret e & Race
®
-WING CIVIL ENGINEERS
SERVICES RATE SCHEDULE
PROFESSIONAL SERVICES
Senior Principal ..................... ........................
$190.00 /hour
Associate Principal . .........................140.00
to 150.00 /hour
Associate ............... .........................110.00
to 140.00 /hour
Senior Engineer ..... .........................120.00
to 140.00 /hour
Engineer ................ .........................100.00
to 130.00 /hour
Engineering Technician ....................85.00
to 105.00 /hour
Senior Planner ........... .. ... . ..100.00
to 140.00 /hour
Planner .......................... .., ................ 85.00
to 105.00 /hour
Senior Surveyor ..... .........................110.00
to 130.00 /hour
Surveyor ................ .........................100.00
to 115.00 /hour
Survey Technician .... ........................85.00
to 105.00 /hour
CAD Technician . .........................85.00
to 110.00 /hour
Construction Technician ..................85.00
to 105.00 /hour
EXPERT WITNESS & MEDIATION SERVICES ................$300.00
/hour
FIELD SURVEYING
One -man Party ............................ ...................$160.00
/hour
(Including Survey Equipment & Vehicle)
Two -man Party ............................ ...................$225.00 /hour
(Including Survey Equipment & Vehicle)
Three -man Party ......................... ...................$280.00 /hour
(Including Survey Equipment & Vehicle)
TYPING AND CLERICAL ............................. ....................$70.00 /hour
OUTSIDE CONSULTANTS ....................... ...........................Cost +5%
OUTSIDE REPRODUCTION/ PLOTTING ... ...........................Cost + 5%
Proposal for Engineering Services
City of Rohnert Park Interceptor Outfall
Gravity Section Rehabilitation Project
Our en
gineerr and inspectors turn
difficult prry"ecls into success stories.
Note Hourly rates are inclusive of nearly all expenses. Brelje & Race does not charge separately for expenses
that are traditionally recouped from the Client as "reimburseable ", such as mileage, surveying materials,
copies of recorded documents, and in -house reproduction and computer equipment costs.
Page 26 BrelieNsULTINGGIv ENGINEERS