2014/07/22 City Council Resolution 2014-086RESOLUTION NO. 2014-086
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROHNERT PARK
AUTHORIZING AND APPROVING A SECOND AMENDMENT TO TASK ORDER
2013 -01 WITH BRELJE & RACE FOR ADDITIONAL ENGINEERING SERVICES FOR
ROHNERT PARK EXPRESSWAY WATER TRANSMISSION MAIN PROJECT NO.
2004 -08
WHEREAS, the City of Rohnert Park Municipal Code Title 3 Chapter 3.04 provides that the
City's purchasing functions shall be governed by the City's purchasing policy;
WHEREAS, the City Council, via Resolution No. 2011 -13, approved a Master Design
Professional Agreement for Municipal Engineering Services with Brelje & Race (Consultant) on
February 22, 2011;
WHEREAS, on December 12, 2013 the City and Consultant entered into Task Order 2013 -01
for the amount of $15,000.00 to develop updated bid documents, including 100% plans, for the Rohnert
Park Expressway portion of the Eastside Water Transmission Main, as authorized by the Rohnert Park
Municipal Code Chapter 3.04 Purchasing Program.
WHEREAS, on April 14, 2014, the First Amendment to Task Order 2013 -01 was authorized
through the Purchasing Ordinance for an additional amount of $18,500.00 for additional design services
that had not been anticipated which included, but were not limited to, revisions due to Sonoma County
Water Agency review comments and ADA ramp improvements.
WHEREAS, City and Consultant now desire to enter into this Second Amendment to provide
for additional work including bidding and construction- related services requested by the City that were
outside the scope of the original Task Order 2013 -01 and the First Amendment for this project for an
additional amount of $20,770.00, thereby increasing the total cost of the agreement to $54,270.00
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF ROHNERT PARK AS FOLLOWS:
Section 1. Recitals. The above recitations are true and correct and material to this
Resolution.
Section 2. Environmental Clearance. The adoption of this Resolution and
accompanying Second Amendment is exempt from review under the California Environmental
Quality Act because it is not a project as that term is defined by CEQA Guidelines Section
15061(b)(3) as it can be seen with certainty that awarding additional design services to an
engineering firm will not have a significant effect on the physical environment. To the extent this
action affects development of the pipeline, the action would be exempt from CEQA as the
pipeline does not exceed one mile in length and therefor is not a project as defined under CEQA
Guidelines Section 15282(k).
2014 -086
Section 3. Agreement. The City Council of the City of Rohnert Park authorizes and
approves a Second Amendment to Task Order 2013 -01 by and between Brelje & Race, a
California corporation, and the City of Rohnert Park, a municipal corporation, for construction
management and related services for the Rohnert Park Expressway Water Transmission Main
Project No. 2004 -08, for a not -to- exceed cost of $20,770.00 ( "Second Amendment "). Total
compensation under this task order including the two amendments shall not exceed $54,270.00.
Section 4. Authorization. The City Manager is hereby authorized and directed to
take all actions to effectuate the Second Amendment for and on behalf of the City of Rohnert
Park, including execution if necessary, in substantially similar form to the Second Amendment
attached hereto as Exhibit "A," attached hereto and incorporated by this reference, subject to
minor modifications by the City Manager or City Attorney.
DULY AND REGULARLY ADOPTED this date of July 22, 2014.
ATTEST:
&aw,0.,�Il
`,, oAnne Buergler, City IeM
CITY OF ROHNERT PARK
�r
' --- Jo e h T. Callihant 1 , Mayor
Attachments: Exhibit A — second amendment
BELFORTE: (-V%WT MACKENZIE- tVi1` 01' STAFFORD: 0- Ci AHANOTU: ()46' CALLINAN: {` �
APES: ( S ) NOES: ( 0 ) ABSENT: ( �2. ) ABSTAIN: ( () )
2014 -086
AMENDMENT 2 TO
TASK ORDER NO. 2013-01
CITY OF ROHNERT PARK
AND
BRELJE & RACE
AUTHORIZATION FOR ADDITIONAL ENGINEERING SERVICES FOR
WATER MAIN IMPROVEMENTS PROJECT NO. 2004 -08
SECTION I — PURPOSE
The purpose of this Task Order is to authorize and direct BRELJE & RACE to proceed with the
work specified in Section 2 below in accordance with the provisions of the MASTER AGREEMENT
between the City of Rohnert Park ( "City ") and BRELJE & RACE ( "Consultant ") dated February 25,
2011.
SECTION 2 — SCOPE OF WORK
The additional items authorized by this Task Order are presented in Attachment 1.
SECTION 3 — COMPENSATION AND PAYMENT
Compensation shall be as provided in the MASTER AGREEMENT between the parties
hereto referenced in SECTION 1 above. The additional cost for the additional services as set
forth in SECTION 2 shall be actual costs (time and materials) based on Consultants' standard
labor charges in accordance with the provisions of the MASTER AGREEMENT and as shown in
Attachment I for an amount not -to- exceed $20,770.
Total compensation under this Task Order with this Amendment shall not exceed
$54,270.
SECTION 4 — TIME OF PERFORMANCE
The work described in SECTION 2 shall be completed by December 31, 2014, or as extended by
the City Manager.
SECTION 5 — ITEMS AND CONDITIONS
All items and conditions contained in the MASTER AGREEMENT for professional
services between City and Consultant are incorporated by reference.
Approved this day of )2014.
CITY OF ROHNERT PARK BRELJE & RACE
Darrin Jenkins, City Manager (Date) By: Name and Title
Per Resolution No. 2014- adopted by the
Rohnert Park City Council at its meeting of July 22, 2014.
Attest:
JoAnne M. Buergler
City Clerk
BRELJE & RACE
By: Name and Title
(Date)
(Date)
r :o Race Attachment 1
H &JLT�t�t, raVII, F :V3r,FFRq Page 1 Of 4
PROPOSAL
Amendment to Task Order No. 2013 -01
City of Rohnert Park
DESIGN SERVICES
FOR
ROHNERT PARK EXPRESSWAY TRANSMISSION MAIN
Project Number 2004 -08
June 17, 2014
For your consideration, Brelje & Race requests amending Task Order No. 2013 -01 to include additional bidding
and construction related services that have been performed or will be performed for the RPX Transmission plain
Project. The original services task order only included limited design related tasks. Bidding and constriction types
of engineering services were not requested in our original scope of services, however, we have been performing
several bid related tasks expressly at the request of City staff that are outside of our current scope, and anticipate
performing numerous additional tasks normally associated with construction. The original project budget for the
RPX Transmission Main design was $15,000. -An earlier amendment for Out -of -Scope design services was
approved for $18,500 to bring the project design total to $33,500. The design budget has been exhausted, thus
requiring an amendment to our services in order to continue during bidding and constriction.
Our billings through May 2014 indicate that we have exceeded the previously approved budget by roughly $4,500,
primarily performing tasks associated with bidding assistance or other out -of -scope tasks. We have been requested
to perform additional tasks such as submittal reviews and to prepare conformed drawings, and anticipate being
called upon to perform various other construction related engineering services as constriction progresses.
Therefore, additional budget is necessary for covering tasks already completed or requested, and work that
remains to be performed.
Work tasks outside of the original scope of services and included in this amendment are outlined below.
SCOPE OF SERVICES
The scope of services for this project will be expanded to include the following:
1. Provide assistance during bid advertising such as responding to bidder's questions, preparing addenda,
attend meetings and coordinating with the construction manager (work already performed).
2. Provide engineering services during the construction phase such as preparing CCO's or reviewing CCO's
prepared by the construction manager (CN1), attending on -site construction progress meetings (up to 3
anticipated), Respond to RFIs, review contractor proposed alternates, and review submittals. (Many of
these tasks have already been requested or partially performed)
3. Conform drawings to addenda (already completed) and per approved contract (e.g. remove electrical
conduit and related items which were bid electives). Provide 10 sets of contract documents (plans and
specifications) for City, CM and contractor use.
4. Upon project completion, incorporate red -line drawings assembled by contactor or CM (or both) into a
Record Drawing Set for City archive files.
5570 Skylane Blvd, • Santa Rosa, CA 65403 . v: 707.676 -1322 - t 707.576 -0469
www.brce.com
Attachment 1
AMENDED FEE REQUEST Page 2 of 4
A Task, Work Hour and Cost Tabulation worksheet (attached) has been prepared in order to estimate additional
expenses beyond the original and previously amended budgets. For the construction related services as described,
a fee of $20,770 is requested to be added to the budget. Our fees for this work will continue to be billed on a time
and materials basis, and will not exceed the requested arnount without prior written approval. Tabulated fees are
based on our 2014 schedule of rates and services, copy attached.
Associate Pnncrpal
Page 2 of 2
Attachment 1
Page 3 of 4
TASK/WORK HOUR TABULATION
Proposal - Construction Services
RPX Transmission Main
City of Rohnert Park
6/17/2014
$150 $110 $105 $65'
1 Assistance During Bidding (Respond to Bidder Questions; Prepare Addenda; Attend 16 4 8 2 30
Meetings, Coordinate w/ Constr. Manager)
2 Engineering Services during Construction (Prepare or Review CCO's; Attend Constr. 40 8 2 4 54
Meetings (up to 3); Respond to RFls; Review submittals)
Prepare Conformed Contract Documents for City, Contractor and Construction Observer
3 8 20 2 $ 1,600 30
(Drawings & Specifications - 10 Sets)
4 Prepare Record Drawings upon Contract Completion (1 Set - Velum) 8 4 24 4 $ 160 40
Brake & 111XIa- e
,�nnr�.i: �d�illTi,�; -C�eIE PG�lY1C��c
Bre1je c Attachment 1
1. FNGINFCPS Page 4 of 4
SERVICES RATE SCHEDULE
EFFECTIVE MARCH 1, 2014
PROFESSIONAL SERVICES
Senior Principal ......................................................... ...............................
........................$190.00 /hour
AssociatePrincipal .......................................................... ...............................
...................150.00 /hour
Associate........................................................................... ...............................
...................140.00 /hour
SeniorEngineer ............................................................... ...............................
...................140.00 /hour
Enoieer........................................................................... ...............................
....................130.00 /hour
Engineering Technician .................................................. ...............................
...................110.00 /hour
SeniorPlanner ................................................................... ...............................
..................130.00 /hour
Planner.............................................................................. ...............................
...................100.00 /hour
SeniorSurveyor ...................... ..................... ......................................
.............. ................... 130.00 /hour
Surveyor........................................................................... ...............................
....................115.00 /hour
SurveyTechnician ........................................................... ...............................
...................105.00 /hour
CADTechnician ........... ............................. ........................................................................
105.00 /hour
Construction Engineer ............................................. ...............................
.........................130.00 /hour
Construction Technician 2 ............................................. ...............................
...................110.00 /hour
Construction Technician 1 ..............................................
............................... ....................95.00 /hour
EXPERT WITNESS & MEDIATION SERVICES $$300.00 /hour
FIELD SURVEYING
One -man Part}, 4$160.00 /hour
(Including Survey Equipment & Vehicle)
Two -man Party $220.00 /hour
(Including Survey Equipment & Vehicle)
Three -man Party $270.00 /hour
(Including Survey Equipment & Vehicle)
CLERICAL SERVICES $65.00 /hour
OUTSIDE CONSULTANTS Cost + 10% Handling Charge
OUTSIDE PLOTTING AND REPRODUCTION Cost + 10% Handling Charge
IN -HOUSE PLOTTING
Vellum or Bond $8.00 /sheet
Mylar 20.00/sheet
Note
Brelje & Race does not charge separately for many of the expenses that are traditionally recouped from the
Client as "reimbursable ". The hourly rates listed above are inclusive of all expenses for mileage, surveying
materials, copies of recorded documents, and computer equipment costs.
475 Aviation Blvd., Suite 120 • Santa Rosa, CA 05403 v: 707.578 -1322
www.bree.com