2005/02/22 City Council Resolution (7)RESOLUTION NO. 2005 -50
APPROVAL OF CONTRACT CHANGE ORDER #1
TELSTAR INSTRUMENTS, INC.
SEWER FLOW METER REPLACEMENT PROJECT
PROJECT NO. 2003-32
FOR $22,100.00
WHEREAS, the 2004 -2009 Five -Year Capital Improvements Plan budgeted
$75,000 for the Sewer Flow Meter Replacement Project; and
WHEREAS, the City received bids and approved a construction contract with
Telstar Instruments, Inc. on October 12, 2004 in the amount of $25,980.00; and
WHEREAS, since the commencement of the contracted work, another sewer
flow meter near the Pump Station needs to be replaced; and
WHEREAS, Section 3.04.075 of the Rohnert Park Municipal Code provides for
negotiation for work under $25,000; and
WHEREAS, the City has negotiated the cost of the second flow meter down from
$25,980 to $22,100.
NOW, THEREFORE BE IT RESOLVED by the City Council of the City of
Rohnert Park that Contract Change Order #1 with Telstar Instruments, Inc. is approved
for the amount of $22,100.00 and the City Manager is authorized to execute the Contract
Change Order.
DULY AND REGULARLY ADOPTED this 22`d day of February, 2005.
CITY OF ROHNERT PARK
Mayor ake Mackenzie �� '�
ATTEST:
Deputy City Clerk