2005/09/13 City Council Resolution (8)RESOLUTION NO. 2005- 283
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROHNERT PARK
APPROVING CONTRACT CHANGE ORDER #1
WITH DAMA CONSTRUCTION, INC. FOR
ROBERTS LAKE DOG PARK PROJECT NO. 2000-11
FOR $6,789.82
WHEREAS, the City approved a construction contract with DAMA Construction, Inc.
on May 10, 2005; and
WHEREAS, changes to the construction contract are needed to best implement the goals
of the project; and
NOW, THEREFORE BE IT RESOLVED by the City Council of the City of Rohnert
Park that Contract Change Order #1 with DAMA Construction, Inc. is approved for the amount
of $6,789.82, and
BE iT FURTHER RESOLVED that the City Manager is authorized to execute the
Contract Change Order.
DULY AND REGULARLY ADOPTED this 13th day of September, 2005.
CITY OF ROHNERT PARK
Mayor
ATTEST:
City Clerk o , O 119
ERT
BREEZE: AYE FLORES: AYE SMITH: AU VIDAK MARTTNEZ E MACKENZIE: AYE
AYES: (3) NOES: (0) ABSENT: (0) ABSTAIN: (0)
CITY OF ROHNERT PARK
6750 Commerce Boulevard
Rohnert Park, CA 94928
Telephone (707)588 -2232 FAX (707)588 -2238
Roberts Lake Dog Park
PROJECT NO. 2000-11
CONTRACT CHANGE ORDER NO. 1
8 -31 -05
Item Description Amount
1 Plans called to connect to downstream side of existing 2" water meter on $ 6,789.82
the north end of the project, install a new backflow preventor and new
dog drinking fountain.
The existing water meter box is housing cable TV cables.
The contractor was directed to install a water service like the proposed
service on the south end of the project using the unit price in the original
bid.
Water main was located approximately 8' below finish grade. The water
main was constructed this way to avoid a conflict with an existing
crossing storm drain. This is an unforeseen condition and extra costs
were incurred by contractor to facilitate this new service.
These costs include labor and materials for additional excavation and
spoils, slurry backfill material and trench plate rentals.
Total Contract Change Order No. # 1 (item 1) $ 6,789.82
Existing Contract Amount $ 37,520.70
Revised Contract Arno nt $ 44,310.52
Recommended by:
Public Work%4nspector, George Frostick Dfate
Recommended by: Lwm-"� 9 Lo
City Eng eer, Darrin Jenkins ate
Approved by:
City Manager, Steve Donley Date
Accepted by:
Margaret Clardy, DAMA Construction Date
Contract Change Order No. 1
Roberts Lake Dog Park
Project No. 2000 -11