1992/10/27 Community Development Agency Minutes COMAJNITY DEVELOPMENT AGENCY
OF
THE CITY OF ROHNERT PARK MINUTES
October 27, 1992
The Members of the Community Development Agency of the
City of Rohnert Park met this date during the City Council
meeting at approximately 7:35 p.m. in the City Offices,
6750 Commerce Boulevard, Rohnert Park, with Chairperson
Spiro presiding.
Call to Order Chairperson Spiro called the meeting of the Community
Development Agency of the City of Rohnert Park to
order at approximately 7:35 p.m.
Roll Call Present: (5) Agency Members Eck, Hollingsworth, Hopkins,
Reilly, and Chairperson Spiro
Absent: (0) None
Staff present for all or part of the meeting: Executive
Director/City Manager Netter, City Attorney Flitner,
Assistant to the City Manager Leivo, City Engineer Brust,
Planning Director Skanchy.
Approval of Minutes Upon motion by Agency Member Hopkins, seconded by Agency
Member Eck, except for abstaining by Agency Member
Hollingsworth due to absence from the meeting, the
minutes of October 13, 1992 were unanimously approved as
submitted.
Approval of Bills Upon motion by Agency Member Hopkins, seconded by
Agency Member Hollingsworth, the bills presented per
attached list in the amount of $21 , 921 . 03 were
unanimously approved.
Acknowledging The Executive Director/Secretary's report on the posting
Exe.Dir./Sec.Report of the agenda was acknowledged.
Uischeduled Public Chairperson Spiro stated that in compliance with State
Appearances Law, (The Brown Act) , anyone in the audience who wished to
make a comment may do so at this time.
CDA Budget and Operations - Executive Director Netter referenced copies provided
to Agency of various communications related to Community
Development Agency Budget and Operations as listed on the
agenda. He shared comments as reviewed in tonight's City
Council Meeting Memo as follows:
A) Update on Community Development Agencies/Future
Outlook - outlining the future of redevelopment agencies
in California as reported at the California Redevelopment
Conference held in Sunnyvale on October 1st, 1992. The
CONMJNITY DEVELOPMENT AGENCY/CITY OF ROHNERT PARK MINUTES (2) October 27, 1992
report points out that, even though the State said redevelopment
agencies would only incur a one-time "hit", it appears likely that
the State Legislature will repeat the "take" again in 1993
considering the estimate that the State Budget may be in even
worse shape in 1993.
B) State "Hit" on City of Rohnert Park CDA for Fiscal Year
1991-92 in the amount of $538,765 via letter submitted by the
California Department of Finance dated October 1, 1992 requiring
"the county auditor, by no later than May 15, 1993, to transfer
any amount necessary to meet the obligation determined for that
agency from the legislative body's property tax allocation" .
C) Update on City of Rohnert Park CDA Cash Position - Agency
provided with copies of 1992-93 Cash Flow Statement (copy attached
to original set of these minutes ) reflecting $1 . 2 million at
Agency disposal after the $539,000 "hit". Executive Director
Netter strongly recommended doing no projects and holding these
funds in reserve until after the City knows what the State "hit"
will be next year. Mr. Netter explained the redevelopment
process with respect to annual increments , bond issues and
certificates of participation and said people might think the City
has increments for new projects, which is not true since all the
increments mist go to pay the debt service on the bonds and OOP's
previously approved. In response to Agency request, Executive
Director Netter extensively reviewed details regarding the
establishment of the City's Redevelopment Agency including how it
was founded, the rules and regulations under which it operates,
and how the tax increments are collected and distributed.
D) Project Funding Priorities - Agency was provided with copies
of project funding priorities (copy attached to original set of
these minutes) , as previously approved, listing estimated project
expenditures for Public Safety Building (Main) , Alicia Park
Lights, Public Safety West/Animal Shelter, Rohnert Park Expressway
( Interim project-overpass) and Commerce Blvd. Bike Path. Detailed
information and review of prior budget work sessions establishing
same was also provided for Agency information.
Executive Director Netter also shared contents of copies provided
to Agency of various items pertaining to options for the Animal
Shelter Project and the Rohnert Park Expressway Improvements
Project (copies attached to original set of these minutes) as
follows: 1) Staff report from City Manager dated October 27, 1992
regarding Animal Shelter Options; 2) Staff report from Finance
Director Harrow dated October 27, 1992 regarding F.A. I .R.E.
(Friends of the Animals in the Redwood Empire) Volunteer Labor;
3) Letter from Mullin Construction Co. , Inc. dated September 28,
1992 confirming extension of Animal Shelter bid date for an
additional 90 days; 4) Staff report from City Manager dated
October 27, 1992 regarding Humane Society of Sonoma County plans
for new facilities; and 5) Letter from Codling Enterprises dated
October 22, 1992 regarding widening of U. S. 101 overpass and
Rohnert Park Expressway.
COMMUNITY DEVELOPMENT AGENCY/CITY OF ROHNERT PARK MENUrES (3) October 27, 1992
Agency Committee Member Eck said he and Agency Committee Member
Hollingsworth had met several times regarding these matters and
said the above-reviewed reports fairly well covered the options.
He said there is still some legal language that needs to be worked
out regarding clear title for the proposed Animal Shelter site.
This would be a necessity prior to awarding a contract on the
Animal Shelter Project.
Agency Committee Member Hollingsworth also reviewed content of
discussions held with F.A.I.R.E. representatives and said he had a
hard time taking away funding from previously approved projects,
especially if it meant cutting a project down to only having a
shell of original plans. He said, however, that he would like to
further review the metal building option for the Animal Shelter as
it seemed there could be the possibility of retaining the major
plan with the reduced cost of the building. Agency Member
Hollingsworth confirmed an important factor of comparisons with
the metal building option would be regarding the maintenance
provisions necessary for the new Animal Shelter.
Discussion followed regarding the complexities of CDA funding
distributions and necessary precautions due to State "hits".
Chairperson Spiro consented to public comments at this time.
Alfred Haggerty, 167 Fescue Way, said he was speaking as an individual regarding
recommendations for the new Animal Shelter. The Community
Development Agency has $1.2 million at its disposal after the
State "hit". Since the State says this is a one time hit and City
staff is only assuming the redevelopment funds will be "hit"
again, consideration could be given to using $800,000 of the CDA
funds for the Animal Shelter and holding the other $400,000 in
escrow. Then, if the State does come back with an additional
"hit" next year, those funds would be available or, if not ,
progress on the Animal Shelter could continue. Mr. Haggerty also
expressed concern that tax dollars had been spent for
architectural services with questions of clear title on the site
and suggested the City find another site.
Kathy Hinkle, 547 Lorraine Court, Veterinarian for the Animal Shelter, expressed
concerns related to developing a facility that would be less than
adequate. She was not certain adequate drainage could be acquired
with the metal building option. There has been a lot of research
done for the proposed plans as presented and this is not a new
thing for herself and the volunteers involved. She said the
restrictive conditions of considering the Humane Society is nearly
ludicrous since the animals are gone within 72 hours after being
picked up. The Animal Shelter volunteers are currently working in
a 20 year old facility that was never adequate and it is tine to
address this matter now. There are serious ventilation problems.
It is understood that the Agency must make the right decision but
the Animal Shelter has waited a long time, and the longer we wait,
the more animals are affected. As one of the animal welfare
caretakers in this community, this is a real problem and the
people involved with it in the community are very concerned. The
CONMJNITY DEVELOPMENT AGENCY/CITY OF ROHNERT PARK MINUTES (4) October 27, 1992
Task Force that worked on the research for the facility did not
look into metal buildings and, therefore, this option should be
presented to them before a decision is made.
Holly Blue, 1312 Gold Way, representative of F.A. I.R.E. , referenced the 100 or
so people in tonight's audience in support of the new animal
shelter, distributed to Agency a petition of approximately 1500
signatures and attached letter responses, and said approximately
many other people have also contacted F.A. I .R. E. to express
support. It is no longer just the little F.A.I.R.E. group of
people, but many other concerned residents of the area. Pets are
hart of families and people are very concerned about what is going
on at the Animal Shelter. It is not a discussion of whether the
community needs the new facility as it has been discussed for over
several years. The above reports are true that costs have gone up
from $400,000 to $1.4 million in this timeframe, but so have the
costs of the Expressway expansion gone up the same comparatively.
A few more seconds of time for people to get across the freeway
does not compare to the needs at the Animal Shelter. We worked
with the Humane Society before and everyone knows the kind of job
they do. People are not going to be happy about going there,
especially the ones that have to commute. There is no control
over the costs because past experience has shown that the Humane
Society offers a great price for the first year and then nearly
doubles the cost the next year, or they can choose not to renew
the contract like they did to the County. If that happened to the
City, then there would not be any options to build a shelter. The
minutes of June 1990 reflect the decision that it was best for the
City to run its own shelter. Ms. Blue said she was not sure the
metal building option would meet all the needs and maintenance
requirements of the Animal Shelter. There would probably be
increased labor to provide the maintenance needs of the metal
building. The plans as proposed is designed for minimal labor and
maintenance. The City is growing and there is going to be more
home. With more homes comes more pets.
Discussion followed during which Council responded to above
concerns that the maintenance factor of the metal building option
had not been investigated. Mbdern metal buildings have become
very attractive and in no way resemble the old quonset huts .
Recommendation was made that F.A.I.R.E. should meet with staff to
review the various options more thoroughly. Further comments
pointed out that future State "hits" will become an actuality
rather than an assumption because the State is not generating
enough money to pay its obligations, therefore, in some form or
another it will have to raise taxes or cut services, so what will
be done is these kinds of "hits" . If projects are done and the
State does the same thing next year, monies will be taken from the
City General Fund. Comparisons were made with other projects with
acknowledgment that the Animal Shelter is not a relatively
expensive project, and other City projects have had to be planned
and done in phases. Further comments reviewed the various
options regarding this matter.
CONMJNITY DEVELOPMENT AGENCY/CITY OF ROHNERT PARK MINUTES (5) October 27, 1992
Hugh Codling, Codding Enterprises, referenced his above-mentioned letter
regarding widening the U. S. 101 overpass and Rohnert Park
Expressway and said he wanted to make it clear that this project
was not in competition with the Animal Shelter project . He
complimented the success of the theatre and said he would try to
help. He said he did not know what problems there were on the
title of the proposed site but Codding Enterprises could provide a
site behind the Pets Mart. They could give the City a piece of
property plus build a road. If that would be helpful , they would
be glad to do it. Mr. Codling mentioned the promises he had made
to west side developments that needed to be fulfilled regarding
the overpass improvements and Rohnert Park Expressway. He said
the City could build it or Codding Enterprises could build it and
lease it to the City at 7% return.
A motion was made by Agency Member Eck, seconded by Agency Member
Reilly, and unanimously approved, directing staff to see how the
Animal Shelter bid would change if the site were moved south,
investigate the metal building option more thoroughly, and provide
a full accounting of other available reserves to see if there are
sufficient funds to proceed with the Animal Shelter project.
Janis Storbo, 7665 Camino Colegio, said she wanted to make sure that any options
explored included input from the Animal Shelter Manager as well as
local veterinarians because they know the specific needs of an
animal shelter.
Roger Southfield, 5338 Daniel Drive, said he is presently running for City
Council candidacy. He referenced other budget items and expressed
concern regarding citizen needs compared to animals . Mr.
Southfield said he does support the Animal Shelter, but more
consideration should be given to the portable buildings, as well
as the proposal of the Humane Society handling our animals.
RECESS Chairperson Spiro declared a recess at approximately 8:55 p.m.
RECONVENE Chairperson Spiro reconvened the Community Development Agency
meeting at approximately 9:05 p.m. with all Agency Members
present.
Component Unit Financial Statement for Year Ended June 30, 1992:
Executive Director Netter referenced report provided to Agency of
Component Unit Financial Statement for Fiscal Year Ended June 30,
1992 for the Community Development Agency as submitted by CDA
external auditors, Deloitte & Touche. He responded to Agency
questions regarding same and said Deloitte & Touche
representatives Kevin Harper and General Manager Michael Johnson
were also available to answer questions.
A motion was made by Agency Member Hopkins, seconded by Agency
Member Reilly, and unanimously approved, accepting the Component
Unit Financial Statement for Year Ended June 30 , 1992 as
recommended by staff.
COMMUNITY DEVELOPMENT AGENCY/CITY OF ROHNERT PARK MINUTES (6) October 27, 1992
Burbank Housing Development Corporation:
Executive Director Netter referenced copies provided to Agency
of communications from Burbank Housing Corporation which were
reviewed at the previous CDA meeting of October 13, 1992 regarding
its affordable housing proposal on the Santa Alicia Drive
Presbyterian Church site (Community Garden site) . Copies of
additional information were provided to Agency, as requested at
the previous meeting, via letter dated October 22 , 1992 from
Burbank Housing regarding City Funds--Presbyterian Church Project
(copy attached to original set of these minutes) . As reviewed in
tonight's City Council Feting Memo, Burbank Housing original
request was amended from $850,000 to $825,000, allocating $625,000
from the City's redevelopment housing set-aside funds and $200,000
from Community Development Block Grant (CDBG) funds. The request
was again revised at the October 13, 1992 Agency meeting to
$260,000 from CDA set-aside funds or, specifically, $200,000 for
site purchase and $60,000 for pre- development costs.
Upon motion by Agency Member Hopkins, seconded by Agency Member
Reilly, allocation of $260,000 from CDA set-aside funds for
Burbank Housing Development Corporation affordable housing project
on Santa Alicia Drive Presbyterian church site was unanimously
approved as requested.
Sonoma County Community Development Commission:
a) 1992-93 Administrative Services Contract/Extension (4 months) -
Executive Director Netter referenced copies provided to Agency of
letter dated October 19, 1992 regarding Administrative Services
Contract for Rohnert Park CDA Neighborhood Rehabilitation Program
and shared comments as reviewed in tonight's City Council Meeting
Memo requesting a four (4) month extension of this program.
Mr. Netter also referenced copies provided to Council of staff
report dated October 27, 1992 regarding selected statistics for
the owner occupied housing rehabilitation program (copy attached
to original set of these minutes) .
A motion was made by Agency Member Hollingsworth, seconded by
Agency Member Hopkins, and unanimously approved, extending the
Sonoma County Community Development Commission 1992-93
Administrative Services Contract four (4) months as requested.
b) Executive Director Netter said copies were provided to Council
of notice dated October 16, 1992 from Sonoma County Community
Development Commission regarding scheduled public hearing for
Comprehensive Housing Affordability Strategy (CHAS) Annual Plan
for Fiscal Year 1993 and Annual Performance Report for Fiscal
Year 1992. This public hearing will be held on November 3, 1992
at 3 : 45 p.m. in the Chambers of the Sonoma County Board of
Supervisors , Sonoma County Administration Building , 575
Administration Drive, Santa Rosa, California.
Unscheduled
Public Chairperson Spiro asked if anyone in the audience wished to make
Appearances an appearance at this time. No one responded.
COMMUNITY DEVELOPMENT AGENCY/CITY OF ROHNERT PARK MINUTES (7) October 27, 1992
Adjournment There being no further business, Chairperson Spiro adjourned the
meeting at approximately 9:10 p.m.
De Se tart' Chairperson
/
aiT
COMMUNITY DEVELOPMENT AGENCY co
?
OF THE 901
CITY OF ROHNERT PARK
1992-93 CASH FLOW STATEMENT
General Low & Moderate
Fund Housing Fund
Balance, July 1, 1992
& Moderate Income Housing Fund $2,235,077
ovement Project Fund $137, 140 0
1 Proceeds Fund 586, 185 0
rest earned cash 72,779 0
1 from tax increment 503,625 0
COP cash 2,451,008 0
:IPATED SOURCES OF CASH
>erty Tax Increment 2,400,000 0
set-aside (274,000) 274,000
!rest from investments 40,000 80,000
!rest from loan repayments 0 30,000
.e grant (CHRP-O) 0 20,000
application fee 0 20,000
Anticipated Sources of Cash $5,916, 737 $2,659,077
:IPATED USES OF CASH
.ractual services:
mty Rehab program administration $0 $53,000
program administration 0 27,000
lovative Housing administration 0 23, 500
erfaith Shelter Network grant 0 6,000
ieless Prevention Group grant 0 5,000
iinistration fee-City general fund (see note) 325,000 20,000
stee fees/bond issues 8,000 0
my property tax admin fee 50,000 0
Rehab loans 0 540,000
NEH loans 0 250,000
Innovative Housing loan 0 26,000
Tower Apartments (Burbank) loan 0 300,000
oan interest payaments 358,720 0
tre land lease payment 20,000 0
tal project expenditures (see attached) 2,653,753 0
service pmts/1991 TARBS 1,560,270 0
service pmts/1991 COPS 402,293 0
-nt to State 538,701 0
Anticipated Uses of Cash $5,916, 737 $1,250,500
valance, June 30, 1993, Estimated
$0 $1,408, 577
:1 amount due to City will be $631, 500 from this fund.
, $325,000 will be available for repayment in 1992-93.
balance will accrue and be repaid as CDA funds become available
future years.
COMMUNITY DEVELOPMENT AGENCY
OF THE
CITY OF ROHNERT PARK
1992-93 CASH FLOW STATEMENT
Total
Projects Increment General Fund
Balance, July 1, 1992
-ovement Project Fund $137,140 $0 $137,140
1 Proceeds Fund 586,185 0 586,185
?rest earned cash 39,815 32,964 72,779
1 from tax increment 0 503,625 503,625
COP cash 2,451,008 2,451,008
:IPATED SOURCES OF CASH
)erty Tax Increment 0 2,400,000 2,400,000
set-aside 0 (274,000) (274,000)
rest from investments 0 40,000 40,000
. Anticipated Sources of Cash 3,214, 148 2,702,589 $5,916,737
:IPATED USES OF CASH
:ractual services:
iinistration fee-City general fund 0 325,000 325,000
istee fees/bond issues 0 8,000 8,000
inty property tax admin fee 0 50,000 50,000
.oan interest payaments 0 358,720 358,720
Ltre land lease payment 0 20,000 20,000
.tal project expenditures (see attached) 2,653,753 0 2,653,753
service pmts/1991 TARBS 0 1,560,270 1,560,270
. service pmts/1991 COPS 21,694 380, 599 402,293
Lent to State 538, 701 0 538,701
Anticipated Uses of Cash 3,214,148 2,702,589 $5,916,737
Balance, June 30, 1993, Estimated 0 0 $0
93CASHDE.XLS
COMMUNITY DEVELOPMENT AGENCY
OF THE
CITY OF ROHNERT PARK
REDEVELOPMENT FUND
1992-93 BUDGET
Estimated Project Expenditures:
Public Safety Building (Main) $1, 000, 000
Alicia Park Lights 60 , 000
Public Safety West/Animal Shelter 1, 000 , 000
RP Expressway (Interim project-overpass) 1, 000 , 000
Commerce Blvd. Bike Path 200 , 000
Total $3 , 260, 000
Recommended option:
Reduction in Animal Shelter/State budget crisis (538 , 701)
Reduction (TBD) to balance budget (67 , 546)
Total Project Expenditures $2 , 653 , 753
:3PROJ.XLS
a7
COMMUNITY DEVELOPMENT AGENCY P
OF THE
CITY OF ROHNERT PARK
REDEVELOPMENT FUND
1992-93 BUDGET
imated Project Expenditures: Budget Committed Balance
Lic Safety Building (Main) $1, 000 , 000 $1, 000, 000 $0
;ia Park Lights 60 , 000 95, 000 (35 , 000)
Lic Safety West/Animal Shelter 1, 000 , 000 110, 000 890 , 000
Expressway (Interim project-overpass 1, 000, 000 300, 000 700, 000
nerce Blvd. Bike Path 200 , 000 15, 000 185 , 000
31 3 , 260, 000 1, 520, 000 1 , 740 , 000
:e "Hit" - due 5/10/93 (538, 701) (538 , 701)
�r reduction TBD to balance (67, 546) (67, 546)
ince 2 , 653 , 753 1 , 201, 299
fte4/ 0/0 AA/G s.
el.„02r-t;- A/6 4-4-- 9/=0"t0
93PROJ 1.XLS
GA3Zd4 (747rtz
A / /
/mc,e 6)11' e 'CPT; S C
Nan,/ 17e.74- • '-/ o,ad 0
ill 9 t 4,?ee,ex:0 _
ited //0, 61,c,
144 1SC- 50, 4900
ror....e.. 1';54o, coo
Pget_ --- "hoe DAAIA..) st 804 000
//o, 6rA)
/ett ?/ - )4/60/aici Css7,
//' S Sec
/1, 44.444epo 742,, tetw wcotcr.,o - az,( 7
el enret-2.4-7
e6e4/?e41 il/O)S rri4117 OA)
I-44w 44,4 Sac,
4011 cr);
5 LI 1.4141 4444. , 40C/? 1°. eei
_ _ _. •
al:V
to 1
INTER-OFFICE MEMORANDUM ' (.17 �Y
/17
TO: Joseph D. Netter FROM: Michael L. Harrow
City Manager Finance Director
RE: F.A.I.R.E. Volunteer Labor DATE: October 27, 1992
The following is a recap of the estimated volunteer hours as performed by F.A.I.R.E.
at the City`s animal shelter.
Monday -0-
Tuesday 4 hours 2 persons
Wednesday 4 hours 1 person
Thursday 4 hours 2 persons
Friday 4 hours 2 persons
Saturday 4 hours 3 persons
Sunday -0-
Total 20 hours 2 persons (average)= 40 volunteer hours per week
If a part-time person was hired at $7.50 per hour, the value of these volunteer hours
would be $ 15,600 per year.
Pease contact me should you need additional information.
Post-It,brand fax transmittal memo 1671 Forpages ► - '
Ca.
Jol.
R�i�
,I (.. ' .., , tr:
- NNNN �;. 1
rt
MULLIN CONSTRUCTION CO. INC. .
September 28 , 1992
City of Rohnert Park
6750 Commerce Boulevard '
Rohnert Park, CA 94928
ATTENTION: Ron Brust, City Engineer
RE: City of Rohnert Park Animal Shelter
Dear Ron: .
Mullin Construction would like to express our appreciation for the
opportunity to bid your Animal Shelter Project. : ;
Our position as low bidder, is always very
gratifying!
project is understand there are some issues outstanding bifo and duce project
this
giver the go-ahead. With regard to our bid price,
imposed delay, we would like to assure you that our pperiod. is hereby
extended and guaranteed for an additional 90 day
Should you have any further questionsour ish to discuss this in
detail , please don't hesitate to call ,
RQgay s , 1/.// `
.
!ichael . Mullin, Pre dent
Mullin Construction Company, Inc.
tad/
P.0 BCX b9.SEsrscCn ;.A 95472•;701)°23-647 '447..0 475538 .
C176
AP`9 (-R
/o- 3
INTER-OFFICE MEMO
TO: Members of the City FROM: Joseph D. Netter, City
Council Manager
BY: Carl E ic:,eivo, Assistant
to the ity Manager
RE: Report Regarding Humane DATE: October 27, 1992
Society of Sonoma Co.
Dan Knapp, Director of the Humane Society of Sonoma County, was
contacted.
The Humane Society has prepared plans for new facilities at their
current 14 acre location on Highway 12 . The Society is currently in
the process of raising funds to finance construction from bequests,
foundations , and similar private sources . The Society intends to
build a pavilion within one and a half years . The pavilion would be
used for a variety of educational activities . The Society intends to
build added shelter facilities in two and one half years.
Mr. Knapp stated that the Humane Society currently has facilities and
programs sufficient to immediately serve the City of Rohnert Park .
The Humane Society is willing to negotiate a service contract . The
Society currently has contracts with the cities of Santa Rosa, Cotati
and Petaluma ( for operation of the Petaluma shelter) . Contract costs
would be prorated based on the number of animals taken to the Highway
12 shelter from Rohnert Park compared to those from Santa Rosa ,
Cotati , and taken in by the Society itself .
The Humane Society facility is open to receive animals from 8: 00 a .m.
to 6 : 00 p.m. , seven days a week . Members of the public can adopt
animals between the hours of 11 :00 a .m. to 6: 00 p.m. Monday through
Friday and 11 :00 a.m. to 5 :00 p.m. on Saturday .
The Humane Society shelter has been remodeled over the past two years .
Mr. Knapp indicates that it is a "state-of-the-art" facility. Facets
of the Humane Society facilities and programs include:
* An in-house spay/neuter clinic;
* An on-site veterinarian 20 hours per week;
* 28 indoor dog runs 16 feet in length (can be divided into two 8
ft . runs ) ;
* 12 to 15 air exchanges per hours to control air borne disease and
odors;
* Dog isolation room;
* Secure intake area;
* Healthy wild and stray cat room, pre-adoption cat room, and cat
adoption room.
PAGE 2
Animals received by the Society are given a full health examination.
Preventive care is provided and corrective measures are taken when
needed .
Approximately 80 percent of dogs are spayed or neutered. All cats are
spayed or neutered (by the Society) .
The Humane Society conducts an extensive adoption promotion program.
The Society publishes "North Bay Pets" which is mailed to 100,000
households bi-monthly. The Society regularly runs ads in newspapers .
Every Friday evening, the Channel 50 news includes a Humane Society
feature. On Saturday mornings, KSRO Radio broadcasts a Humane Society
program. The Society has an extensive mobile adoption program
including "Love-a-Pet" every Saturday and Sunday at PetsMart .
Of healthy animals with a sound disposition, the adoption rate is over
90 percent of the dogs taken in ( in some months 98 to 100 percent ) and
over 80 percent of the cats received.
An important component of Humane Society activities is the volunteer
program. Mr. Knapp and the Society would heartily welcome additional
volunteers . Mr Knapp suggests that Humane Society volunteers have
more resources available to them than do the diligent individuals who
volunteer their time assisting at the Rohnert Park shelter.
The Humane Society provides an annual ordinance review to its
contract jurisdictions . It can provides expert advise to cities on
animal issues .
The Society continually engages in grant writing and fund raising
activities . Funds so raised benefit all the users of the Humane
Society shelter. For instance , a bequest paid for the new dog
adoption wing. The cost of this improvement is not included in
charges to the Society' s municipal clients .
Codding Enterprises
A CALIFORNIA LIMITED PARTNERSHIP
ALL CORRESPONDENCE TO: POST OFFICE BOX 6655 • SANTA ROSA • CALIFORNIA • 95406-0655
TELEPHONE: (707) 584-7550 • TELEFAX; (707) 586-9569
October 22 , 1992
RECEIVED
City Council of Rohnert Park
6750 Commerce Boulevard OCT 2 61992
Rohnert Park , CA 94928 CITYOF
Dear Council Members : RONNERTPARK
For the last two years , Codding Enterprises has assured the various
companies that have located on the west side of U . S . 101 that the
City of Rohnert Park was making every attempt to progress with the
widening of the overpass of U . S . 101 and Rohnert Park Expressway .
Codding Enterprises , at the request of the City Engineer and City
Manager , has contributed S300 , 000 that otherwise would have been
the City ' s share of improving Labath Avenue adjoining Price Club,
towards the engineering plans for said overpass . I 'm enclosing
Rohnert Park Resolution #90-254 where the Rohnert Park City Council
with four of the present council voting aye , Eck , Hopkins , Spiro
and Hollingsworth , requested Cal -Trans to design the Expressway
interchange and authorizing the City to pay Cal -Trans S300 , 000 for
the cost of engineering design .
Based upon assurances by the City staff , Codding Enterprises
assured the various companies on the west side of the freeway
including King ' s Office Supply , Kelly-Moore Paint , Food 4 Less ,
PetsMart , Sear ' s Homelife , Price Club, Target , K-Mart , Olive Garden
Restaurant and Red Lobster Restaurant that the approach overpass
would be completed at the earliest possible time the City could
make it possible . We feel the continued occupancy of the majors
on the west side of the freeway , along with the substantial sales
tax they are bringing to Rohnert Park , will be seriously depleted
without the overpass being completed in the earliest possible time
frame .
Codding Enterprises has done the best they can to enhance retail
activity and increase sales tax revenue for the City of Rohnert
Park and can only continue to do so with the full cooperation of
the City of Rohnert Park .
Yours truly ,
CODDINC ENTERPRISES
By : Coddiz}g Investments , Inc .
General Partner
/ )1 K./
// ill
HUGS B'. CODDING rr1(/'/
Chief Executive Officer
OFFICES LOCATED AT: CODOI�N-�G BANK 6UIILDING • 6400 REDWOOD DRIVE • ROHNERT PARK • CALIFORNIA
J�uif�eny Sonoma C..Oil nfit ?epee 1849'r
Y Ut nvtuvt'.tt1 rtinn
6750 Commerce Boulevard
Rohnert Park, Sonoma County, C-ai+fornia 94927
Telephone 795-2411
November 26, 1990
reston W. Kelly, District Director
tate of California
epartment of Transportation
. 0. Box 7310
an Francisco, CA 94120
.ear Mr. Kelly:
he City Council , at its meeting of November 13, 1990, authorized by Resolution
lo. 90-254 (enclosed) an allocation of up to $300, 000 to have the design work
:ompleted for the Rohnert Park Expressway/US Highway 101 Interchange.
ks you are aware, this interchange is in the heart of the City of Rohnert Park
Ind is very critical to the proper traffic movement from the east to the west
;ide of Rohnert Park as well as ingress and egress from US Highway 101. We
inderstand that Cal Trans has not programmed funds for the design or for
improvements of this interchange and that funds may not be appropriated in the
tear future. In order to expedite this process and hopefully be first in line
Then funds do become available, the City Council has authorized this $300,000 to
:over Cal Trans cost for the design phase of this interchange. The City Council
is committed and is showing how important this project is to the City by
allocating this $300,000 to get the process going.
4e hereby request Cal Trans representatives to prepare the necessary agreements
and documents in order to proceed with the design phase of this interchange so
that the City can reimburse Cal Trans for the cost of said design.
If you should have any questions, feel free to contact Director of Public
works/City Engineer Ron Brust (707/795-2411) . Your immediate attention to this
natter is sincerely appreciated.
Very truly yours,
CAtil OF ROHNERT PARK
el D. Netter
lire or of Administrative Services/
Assistant to the City Manager
JDN: Ir
Enc. (Resolution No. 90-254)
cc: Dick Giegling, Cal Trans
Peter M. Callinan, City Manager
Ron Brust, Director of Public Works/City Engineer
RESOLUTION NO. 90— 254
REQUESTING CALTRANS TO DESIGN EXPRESSWAY INTERCHANGE
ULTIMATE IMPROVEMENTS AND AUTHORIZING CITY TO PAY
CALTRANS COST FOR ENGINEERING DESIGN
WHEREAS, the City desires to have the ultimate improvements for the Rchnert
Park Expressway/U.S. Highway 101 Interchange completed; and
WHEREAS, development on the west side of the freeway will be adding traffic
impacts to the Rohnert Park Expressway/U.S. Highway 101 Interchange; and
WHEREAS. the Rohnert Park Expressway/U.S. Highway 101 interchange is an
integral hub for the flow of traffic east and west; and
WHEREAS, Caltrans has not programmed funds for design or improvements of the
interchange nor feels that funds will be programmed in the near future; and
WHEREAS, by the City providing funds for design of the ultimate interchange
will allow the City and Caltrans to move quickly on obtaining funds that may
become available; and
WHEREAS, by expediting the design phase of this project it will encourage the
State to make this interchange project a higher priority in their transportation
program; and
WHEREAS, the City Engineer estimates the cost for design of the interchange
ultimate improvements to be approximately $300,000.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Rohnert Park
that Caltrans is requested to design the ultimate interchange improvements for the
Rchnert Park Expressway/U.S. Highway 101 interchange;
BE IT FURTHER RESOLVED that the City of Rohnert Park commits to the expendi—
ture of up to $300,000 for the design of this interchange;
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to work with
Caltrans on the preparation of the necessary agreements and documents;
BE IT FURTHER RESOLVED that the appropriate agreements and documents shall
be presented to the City Council for approval .
DULY AND REGULARLY ADOPTED this 13th day of Nove:rber , 1990.
CRY CITY OF ROHNERT PARK
RO .!Alt A K
ir:
wLi 11.-
.... r1II� Mayor
allIV(/
ATTEST: ', '; ,
...
. .
...
Oepu it erk pro", AY' A „� y
COCHRAN ECK HOPKINS-nt SPIRO �' HOLINGSNORTH
AYES (5) NOES (°) ABSENT (0) ABSTAIN (o)
to�7/
,el&
BURBANK HOUSING DEVELOPMENT CORPORATION
I 3432-A Mendocino Avenue • Santa Rosa, CA 95403 • (707)526-9782 • Fax (707) 526-98 t 1
October 22. I992 aka /
•
Rohnert Park Community Development Agency
City Hall ')%7/92
6750 Commerce Boulevard 44.404--
Rohnert Park, CA 94928
Re: City Funds—Presbyterian Church Project
Dear Agency Members.
.-4t your meeting on October 13th when you considered our request for $260,000 for acquisition
and predevelopenint of the Faith Presbyterian land you asked for more information on the
following:
Mat leverage can the City expect on its money?
Assuming rents affordable at 50% of hi.f1, the budget attached shows the sources of funds and
their projected uses. Funding from Rohnert Park as figured after all the other subsidy sources
and conventional financing were factored in. In this scenario, $327,000 of Redevelopment
Agency finding leverages 25 units of housing costing $2 589,000 for a 7.9 to 1 ratio.
Dues Burbank build at per square foot prices which are competitive?
The a.taciied budget is based on hard construction costs estimated to be , 3SS.00 per square foot,
irncludin? landsc.iping. To this add conirarlor's profit and overheaxd••S5,00 per sq. ft., general
conditions at $2.40 per sq. f►. and 10% << 'charge for Fcde'ral prevailing wage requirements of
the HOME program. Total is 549.94, w/iich we believe to be competitive.
To this must be added as shown, the so-called soft costs, much of which is mandated by the
subsidy programs we use.
What Is the Role of Faith Presbyterian Church and how Is the Joint Venture between the
Church .and Burbank structured?
It is Burbank's intention to form a new non profit corporation to act as managing general
partner of the limited partnership to be formed as required for use of tar credits. Because of the
Church's location nett to the development and its social interests and experience, Burbank has
invited the Church to nominate one or more persons from its active membership to fill a
minority of the positions on the Board of the new corporation. Burbank directors will constitute
a majority of the Board and thus retain c )ntrol. The limited partner investors and other funding
A Non-Profit Organization Serving Sonoma County
sources will be retying on Burbank's history balance sheer, and e.tpenence rather than the
Churchs whose nrilnary interest in the project is the provision of social service support to
Burbankand the tenants. In any event, the Curl: is protected from liability by the structure
of the new non-profit and it is Burbank which must provide all the loan and fund guarantees
and assurances.
What is role of City in the Project?
As in any other development, thee C y's responsibility lies in its planning, zoning and permitting
ficnctions. Here in addition we seek City support in the CDBG and other funding applications
and most directly an allocation of Co ntnunity Redevelopment Agency Low and Moderate
income Housing Set Aside hinds.
o0o
With this additional information, I hope the Commission will be able to proceed with an
allocation of Housing Set Aside funds for this project.
Sincere!,
(Yhrz —Mt.)rga 'ect Manager
Faith Presbyterian A=artments/City, ARP, 00mE/Davis-8acer vases/csma
INCOME/EXPENSE & SOta'R S ANALYSIS
10/19/92
Paget 1 100%
LI % 0%
INCONN
t fiat Total Veit Total
2 bedroom - �:,; en 21 rent aO�sa_�feet •.
12 447 s..
3 bedroom - y_2 it E,364 900 10,800
4 bedroom - V.I 519 5,709 1,075
2 S7912,500
community bldg. 1,158 1,250 2,500
Totals or Arq. ZS 4B9 000
1?,231 25,925
NT y ANNUAL
Total rental income
Laundry income $12,231 $146,772
Grass income 5200 $2,400
vacancy loon 4.003 $12,431 7149, 172
Total net income $489 $5,871
$11,942 $143,301
Total operating expenses $232 POPK
lteplacerert reserve $5, 7Q8 $69,450
0.006 const. cost $684 $8,213
Operating reserve 3% e
:yet income for debt service perat. ex?. 8174I,C84
Debt Ee:vice ewvQraQe ratio $5,296 $63,555
1.20 S4,815 d57,777
SOURCES
Lass #1 - 8 C L Loan 02 - City Reday.
:merest rate 9.0011 �-
0.75% rntereat rant 3.00%
Months 360 MonthO
Debt service 360
$4,815 Debt service deferred
Pri7"_pal _ 5509 ,355 ?rinrinal
_ S327,000
:can #3 - County CDDG County HOMY
Interest rate 3.00t interest rate 0.00%
Marfhe
Debt service deferred Months 360
deferred Debt service deferred
Frir.ci Ai 150,000 Prinei al $163 070
Loan 04 - ARP
Partnership Equity
Interest rate 0.00% d Limite Partner Cont.
:�ontr.B 240
$1,isz, 7sv
Debt service General Partner Cont. $41,517
deferred Total Capital Cont.
PrincIPal $7, 500/unit $187, 5CC - S1,I63u246
Total sources os fuada
leas total davelopeent coats 62,589,201 S2•58�,10i
Residual
$0
100% TC VLI units e 50% MI
1 t 1Fe. .H:'�1 .'1 l'�+ 1 F 7.� 4
ra.:h Presbyterian APaztrents/City, A ', ROXE/Davis-Bacon wa
qes/cams
DEVELOPMENT BUDGET
10/29/92
Page 1
Land
Construct-tot Cost 200,000
Off-site irovements
On-site improvements 38, 100
8uLldings 25,92S s.f_ 105,600
552.80 1,368,640
Total Construction Cost
1,512,940
CoastructiOn Pe04
Local permits and fees
rchitsOture/engineering fags 187,50C}
�1
Survey 65,004
tonal preeri,u:. 3 000
Soils report/testing 2,000
construction contingency 10,000
Total Construction !sa.004 105,906
373,406
General Development Costs
Construction loan fee
Construction loan interest i�001 1. 1,370,b00 617
3,126
Real estate taxes 0a ,000
Risk/liability insurance 3, 00
Permanent loan foe 16,000
A raisalf 3•00♦ let c,ort, 11,974
PP ar.7iror�as:stai audit
Legal foss 10,000
consultant fees 20,000
T .tle/escrow fees 10,000
Organization 1s,000
iurnishi;;,s ,000
sent-up: marketing 2,500
Start-up and pre-op costs 10,000
Operatic.; reserve 10,000
Pro'ect administration 25,000
?oat-Comic ction audit 25,000
7,500
Total General Develol.eent costs
353,855
Bradicatioo Coats
250,000
TOTAL DEVELOPMEN2 BUDOXT
2,589,201
100% TC VLI units a 50% MI
Tnra 0 w?
atgi\ (oY C-A
INTER-OFFICE MEMO
TO: Members of the City FROM: Joseph D. Netter, City
Council Manager
BY: Carl Er eivo, Assistant
to the City Manager
RE: Report on Owner Occupied DATE: October 27, 1992
Rehabilitation Program
As of October 22, 1992, selected statistics for the owner occupied
housing rehabilitation program are as follows :
Number of applicants : 119
Applications Approved by the Agency: 72
Applications Dropped/Disqualified 60
( Includes some of those Approved)
Total number of Loans Approved: 47
Number of Cases in Bid Process 1
Total Number of Contracts Signed 46
Number of Projects Under Const . 9
Total Number of Completed Jobs 35
Total Amount of Approved Loans $1 , 051 , 727 .00
Average Loan Amount $ 22 ,377. 00
Total Amount of Const . Contracts $1 ,007,810 . 00
Total CDA Funds Transferred to Date $ 963 ,762 . 45
Total Owner Contributions $ 11 ,533 .80
Contracted administrative costs and amounts paid are listed below:
TIME PERIOD CONTRACT ACTUAL
Oct . 1 , 1988 to Sep. 30, 1989 $45 , 000 $28,500 . 00
Oct . 1 , 1989 to Sep. 30, 1990 $47,700 $46,930. 19
Oct . 1 , 1990 to Sep. 30, 1991 $50,863 $50,863 .00( .1)
May. 1 , 1991 to Sep. 30, 1992 $59, 200 $38 , 291 . 93
(Amended to include CHRP-O Admin. )
While actual Sonoma County Community Development Commission costs may
exceed the contract amount , the Commission has not asked for, and the
Agency has not made payments in excess of the contract amount . In the
last year, CHRP-O administration costs have exceeded expectations as
indicated in the materials from the Commission. The City will receive
reimbursement for a portion of CHRP-O administrative costs from the
State.