HomeMy WebLinkAbout2026/04/28 City Council Resolution 2026-034 RESOLUTION NO. 2026-034
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROHNERT PARK
AMENDING THE FISCAL YEAR 2025-26 CAPITAL IMPROVEMENT PROGRAM
(CIP) BUDGET TO ADD SIX(6) PROJECTS TO CITY CAPITAL PROJECTS FUND
(FUND 7110), TWO (2) PROJECTS TO CITY NON-CAPITALIZED PROJECTS FUND
(FUND 7111), ONE (1) PROJECT TO SEWER CAPITAL PROJECTS FUND (FUND
7420),AND ONE (1) PROJECT TO SEWER NON-CAPITALIZED PROJECTS FUND
(FUND 7421), AND TO INCREASE AND/OR DECREASE APPROPRIATIONS WITHIN
VARIOUS FUNDS AS INCORPORATED IN EXHIBIT A
WHEREAS, on June 10, 2025, the City Council approved Resolution No. 2025-040,
adopting the Five-Year Capital Improvements Program for Fiscal Years 2025-26 through 2029-30
including Fiscal Year 2025-26 CIP Projects ("CIP Budget") as included in the City Budget ; and
WHEREAS, since then, three (3) street improvement projects need to be created and
funded as they relate to the City's obligation to provide certain off-site improvements in
accordance with the Non-Binding Preliminary Term Sheet pursuant to the Exclusive Agreement
to Negotiate between the City and CenterCal Properties, dated October 22, 2024; and
WHEREAS, three (3) City facilities rehabilitation projects at the Community Center
server room in the Public Safety Headquarters, and pedestrian bridges on Copeland Creek need to
be created and funded to address critical deficiencies identified by the 2022 Building Condition
Assessment; and
WHEREAS, two (2) park improvements projects need to be created and funded to a.)
assess and repair the Roberts Lake Dock and b.) demonstrate the City's follow-through with an
extensive community engagement process in 2020 conducted with the A Section neighborhood,
John Reed Elementary School community, and a broad set of users of Alicia Park; and
WHEREAS,one (1) inflow and infiltration project affecting the sewer system needs to be
created and funded to reduce the risk of sewer overflows in the B Section neighborhood; and
WHEREAS, one (1) sewer manhole pavement preservation update project needs to be
created and funded to coordinate with an upcoming Citywide pavement preservation in summer
2026; and
WHEREAS, one (1) recycled water project needs to be created and funded to replace the
deteriorating irrigation system at Alicia Park; and
WHEREAS,adjustments to appropriations for project funding ensures that active projects
are fully funded in the current fiscal year; and
WHEREAS, adjustments to appropriations for project funding releases excess funding
from completed or nearly-completed projects, allowing for reallocation; and
WHEREAS, strategic use of fund balance for projects addresses critical capital needs,
regulatory compliance; and contractual obligations of the City; and
WHEREAS,this action is not a"project"pursuant to the California Environmental Quality
Act (CEQA) as it lacks the potential for a direct or indirect physical change in the environment
(14 CCR § 15378; Cal. Pub. Res. Code § 21065) and, alternatively, is exempt under CEQA
Guidelines Sections 15306(b)(3) (Common Sense Exemption), 15273(a)(4) (Funds for Capital
Projects), and 15306 (Information Collection).
NOW THEREFORE BE IT RESOLVED by the City Council of the City of Rohnert
Park that the foregoing recitals are true and correct and that it does hereby authorize budget
amendments to increase and/or decrease appropriations for the FY 2025-26 CIP Budget as set forth
in Exhibit A and incorporated herein.
BE IT FURTHER RESOLVED that the Finance Director is authorized to make
modifications to the CIP Budget by adding the following projects:
1. Downtown Rohnert Park Expressway Improvements (CIP2610)to Fund 7110
2. State Farm Drive Improvements (CIP2611)to Fund 7110
3. Enterprise Drive Improvements (CIP2612) to Fund 7110
4. Alicia Park Playground Relocation& Replacement(CIP2613) to Fund 7110
5. Roberts Lake Dock Assessment and Repairs (CIP2615)to Fund 7110
6. Community Center(BCA Implementation) (CIP2617)to Fund 7110
7. Public Safety Main Server Room Renovation(CIP2616NC) to Fund 7111
8. Pedestrian Bridges BCA Implementation(CIP2614NC) to Fund 7111
9. I&I Reduction-B Section Phase 2 (Basin 5) (CIP2609S)to Fund 7420
10. Pavement Preservation Manhole Upgrades (CIP2508SNC)to Fund 7421
BE IT FURTHER RESOLVED that the Director of Finance is authorized to make any
administrative adjustments necessary to process the amendments in accordance with generally
accepted accounting principles.
DULY AND REGULARLY ADOPTED this 28th day of April, 2026.
CI O OHNERT PARK
ATTEST: Ern' S)nborn, Mayor
Sylvia Lopez . uevas, t Ity er c _
P ' i� 1 o FO 'M:
‘14 _
ichelle en on, City Attorney \ ---
Attachments: Exhibit A �,,(�
ADAMS: IUDICE ODRIGUE2��Y^'-ELWARD: tSANBORN
AYES: ( ) N S: ( ) ABSENT:( ) ABS11AIN: ( )
Resolution 2026-034
Page 2 of 2
Proposed FY 2025/26 Budget Appropriation Amendments EXHIBIT A
Expenditure
Account Number
Funding Source
Account Number
Amount
GENERAL FUND INFRASTRUCTURE (FUND 7109)
Transfer available/unspent funds from CIP2226 Downtown
Infrastructure (non-utilities portion) to New Downtown Streets
Improvements Phase 1 project CIP2610.
71114305-65500
71094295-77111
71114305-47109
Fund Balance (1,200,000)
Transfer available/unspent funds from CIP2204 Central RP Complete
Streets to New Downtown Streets Improvements Phase 1 project
CIP2610.
71104300-69000
71094295-77110
71104300-47109
Fund Balance (54,000)
Increase appropriations on the New Downtown Streets Improvements
Phase 1 project CIP2610 to receive the transferred funds above from
CIP2226 Downtown Infrastructure (non-utilities portion).
71104300-69000
71094295-77110
71104300-47109
Fund Balance 1,254,000
Transfer available/unspent funds from CIP2310 Building Condition
Assessment Implementation to New Community Center Building
Condition Assessment Implementation project CIP2617.
71104305-65500
71094295-77110 71104300-47109 (650,000)
Increase appropriations on the New Community Center Building
Condition Assessment Implementation project CIP2617 to receive the
transferred funds above from CIP2310 Building Condition Assessment
Implementation.
71104300-69000
71094295-77110
71104300-47109
Fund Balance 650,000
Increase appropriations to transfer funds from the fund balance to the
New CIP2616NC Public Safety Main Server Room Renovation project.
71114305-65500
71094295-77111
71114305-47109
Fund Balance 200,000
200,000$
GENERAL FUND RESERVES
Increase appropriations to transfer funds from the Assigned General
Fund Downtown Reserve to the New CIP2612 Downtown Enterprise
Drive Improvements project.
10001399-77109
71094295-77110
71104300-69000
71104300-47109
71104300-41000
Assigned Downtown
Reserve
313,943
313,943$
SPECIAL REVENUE FUNDS
HUTA Gas Tax (Fund 4420)
Transfer available/unspent funds from CIP2204 Central RP Complete
Streets to New Downtown Streets Improvements Phase 1 project
CIP2610.
71104300-69000
44204120-77110
71104300-44420
Fund Balance (46,796)
Increase appropriations on the New Downtown Streets Improvements
Phase 1 project CIP2610 to receive the transferred funds above from
CIP2204 Central RP Complete Streets.
71104300-69000
44204120-77110
71104300-44420
Fund Balance 46,796
Release available/unspent funds from CIP2206 Pothole Repair &
Maintenance project to fund balance.
71104300-65500
44204120-77110
71104300-44420
Fund Balance (170,000)
Total net appropriations
Total net appropriations
Release available/unspent funds from CIP2225 Citywide Traffic Signal
Safety Improvements project to fund balance.
71104300-69000
44204120-77110
71104300-44420
Fund Balance (29,041)
Release available/unspent funds from CIP2303 Sidewalk Replacement
Program project to fund balance.
71104300-65500
44204120-77110
71104300-44420
Fund Balance (100,000)
(299,041)$
SB1 RMRA (Fund 4425)
Increase appropriations to transfer funds from the fund balance to
CIP2206 Pothole Repair project.
71104300-65500
44254120-77110
71104300-44425
Fund Balance 70,000
Increase appropriations to transfer funds from the fund balance to
CIP2303 Sidewalk Replacement Program project.
71104300-65500
44254120-77110
71104300-44425
Fund Balance 100,000
Increase appropriations to transfer funds from the fund balance to
CIP1826 Wooden Streetlight Pole Replacement project.
71104300-65500
44254120-77110
71104300-44425
Fund Balance 250,000
420,000$
Measure M Transportation (Fund 4327)
Transfer available/unspent funds from CIP2204 Central RP Complete
Streets to New Downtown Transportation Improvements Phase 2
project CIP2611.
71104300-69000
43274120-77110
71104300-44327
Fund Balance (58,917)
Transfer available/unspent funds from CIP2301 Various Streets
Pavement Management to New Downtown Transportation
Improvements Phase 2 project CIP2611.
71104300-65500
43274120-77110
71104300-44327
Fund Balance (24,551)
Increase appropriations on the New Downtown Transportation
Improvements Phase 2 project CIP2611 to receive the transferred funds
above from CIP2204 Central RP Complete Streets and CIP2301 Various
Streets Pavement Management.
71104300-69000
43274120-77110
71104300-44327
Fund Balance 83,468
-$
Measure M Parks (Fund 4322)
Transfer available/unspent funds from CIP2207 Parks Playground
Equipment to New Alicia Park Playground Relocation & Replacement
project CIP2613.
71104300-65500
43224120-77110
71104300-44322
Fund Balance (224,000)
Increase appropriations to transfer funds from the fund balance and
CIP2207 Parks Playground Equipment to the New Alicia Park Playground
Relocation & Replacement project CIP2613.
71104300-69000
43224120-77110
71104300-44322
Fund Balance 1,324,000
1,100,000$
Rohnert Park Foundation (Fund 4609)
Transfer available/unspent funds from CIP2226 Downtown
Infrastructure (non-utilities portion) to New Downtown Streets
Improvements Phase 1 project CIP2610.
71114305-65500
46096000-77111
71114305-44609
Fund Balance (1,200,000)
Increase appropriations on the New Downtown Streets Improvements
Phase 1 project CIP2610 to receive the transferred funds above from
CIP2226 Downtown Infrastructure (non-utilities portion).
71104300-69000
46096000-77110
71104300-44609
Fund Balance 1,200,000
Total net appropriations
Total net appropriations
Total net appropriations
Total net appropriations
Increase appropriations to transfer funds from the fund balance to the
Electric Vehicle Charging Station project CIP2312.
71104300-69000
46096000-77110
71104300-44609
Fund Balance 275,000
Increase appropriations to transfer funds from the fund balance to the
New Pedestrian Bridges BCA Implementation project CIP2614NC.
71114305-65500
46096000-77111
71114305-44609
Fund Balance 50,000
Increase appropriations to transfer funds from the fund balance to the
Park Benches and Shade Structures Replacement project CIP2218.
71104300-65500
46096000-77110
71104300-44609
Fund Balance 60,000
Increase appropriations to transfer funds from the fund balance to the
New Roberts Lake Dock Assessment & Repairs project CIP2615.
71104300-69000
46096000-77110
71104300-44609
Fund Balance 30,000
415,000$
Casino NUWH (Fund 4607)
Transfer available/unspent funds from CIP2226 Downtown
Infrastructure (non-utilities portion) to New Downtown Streets
Improvements Phase 1 project CIP2610.
71114305-65500
46076000-77111
71114305-44607
Fund Balance (500,000)
Increase appropriations on the New Downtown Streets Improvements
Phase 1 project CIP2610 to receive the transferred funds above from
CIP2226 Downtown Infrastructure (non-utilities portion).
71104300-69000
46076000-77110
71104300-44607
Fund Balance 500,000
Increase appropriations to transfer funds from the fund balance to the
Ladybug Park Pool Building Demolition project CIP1924.
71104300-65500
46076000-77110
71104300-44607
Fund Balance 130,000
130,000$
Public Facilities Fee (Fund 4250)
Increase appropriations to transfer funds from the fund balance to the
Corporate Yard Expansion project CIP2402.
71104300-69000
42504300-77110
71104300-44250
Fund Balance 700,000
Release available/unspent funds from the Highway 101 SB/Golf Course
Drive Off-Ramp Intersection Improvements project CIP2408 to fund
balance.
71104300-69000
42504300-77110
71104300-44250
Fund Balance (1,233,728)
Release available/unspent funds from the Highway 101 NB/Commerce
Blvd Off-Ramp Intersection Improvements project CIP2409 to fund
balance.
71104300-69000
42504300-77110
71104300-44250
Fund Balance (1,370,712)
(1,904,440)$
Wilfred Avenue JEPA (Fund 4655)
Increase appropriations to transfer funds from the fund balance to the
Pavement Preservation project CIP2508.
71104300-69000
46556000-77110
71104300-44655
Fund Balance 200,000
200,000$
CASINO INFRASTRUCTURE FUND (FUND 7108)
Transfer available/unspent funds from CIP2226 Downtown
Infrastructure (non-utilities portion) to New Downtown Streets
Improvements Phase 1 project CIP2610.
71114305-65500
71084290-77111
71114305-47108
Fund Balance (364,028)
Transfer available/unspent funds from CIP2204 Central RP Complete
Streets to New Downtown Streets Improvements Phase 1 project
CIP2610.
71104300-69000
71084295-77110
71104300-47108
Fund Balance (40,000)
Total net appropriations
Total net appropriations
Total net appropriations
Total net appropriations
Increase appropriations on the New Downtown Streets Improvements
Phase 1 project CIP2610 to receive the transferred funds above from
CIP2226 Downtown Infrastructure (non-utilities portion) and CIP2204
Central RP Complete Streets.
71104300-69000
71084295-77110
71104300-47108
Fund Balance 404,028
Increase appropriations to transfer funds from the Traffic Circulation
Assignment in fund balance to the Golf Course Drive Southbound Ramp
to Redwood project CIP2407.
71104300-69000
71084290-77110
71104300-47108
Assigned FB 303,831
Increase appropriations to transfer funds from the Traffic Circulation
Assignment in fund balance to the Highway 101 SB/Golf Course Drive
Off-Ramp Intersection Improvements project CIP2408.
71104300-69000
71084290-77110
71104300-47108
Assigned FB 1,505,560
Increase appropriations to transfer funds from the Traffic Circulation
Assignment in fund balance to the Highway 101 NB/Commerce Blvd Off-
Ramp Intersection Improvements project CIP2409.
71104300-69000
71084290-77110
71104300-47108
Assigned FB 1,605,560
3,414,951$
PROPRIETARY FUNDS
Enterprise Fund - Sewer Utility (Fund 3420)
Release available/unspent funds from the Pump Station Motor
Replacements project CIP2013 to fund balance in order to be
reallocated to new projects.
74204300-69000
34204710-77420
74204300-43420
Fund Balance (100,827)
Release available/unspent funds from the I & I Reduction B Section
project CIP2015 to fund balance in order to be reallocated to new
projects.
74204300-69000
34204710-77420
74204300-43420
Fund Balance (365,431)
Release available/unspent funds from the Pump Station Mechanical
project CIP2104 to fund balance in order to be reallocated to new
projects.
74204300-69000
34204710-77420
74204300-43420
Fund Balance (214,557)
Release available/unspent funds from the Water, Sewer, Storm Water
and Recycled Water Mapping project CIP2219 to fund balance in order
to be reallocated to new projects.
74214305-65500
34204710-77421
74214305-43420
Fund Balance (68,732)
Release available/unspent funds from the A Section Commerce Sewer
Line Replacement Phase 2 project CIP2220S to fund balance in order to
be reallocated to new projects.
74204300-69000
34204710-77420
74204300-43420
Fund Balance (2,766,600)
Increase appropriations to transfer funds from the fund balance to the
Water Meter Replacement project CIP1918.
74304300-69000
34204710-77430
74304300-43420
Fund Balance 673,315
Increase appropriations to transfer funds from the fund balance to the
new I & I Reduction B Section Phase 2 (Basin 5) project CIP2609S.
74204300-69000
34204710-77420
74204300-43420
Fund Balance 2,390,367
Increase appropriations to transfer funds from the fund balance to the
Forcemain Rehab Phase 3 project CIP2305.
74204300-69000
34204710-77420
74204300-43420
Fund Balance 300,000
(152,466)$
Enterprise Fund - Sewer Capital Preservation (Fund 3425)
Transfer available/unspent funds from Manhole Frame and Cover
project CIP1711 to Water Meter Replacement project CIP1918.
74214305-65500
34254710-77421
74214305-43425
Fund Balance (71,232)
Total net appropriations
Total net appropriations
Transfer available/unspent funds from Pump Station Mechanical project
CIP2104 to Water Meter Replacement project CIP1918.
74204300-69000
34254710-77420
74204300-43425
Fund Balance (360,509)
Transfer available/unspent funds from A Section Commerce Sewer Line
Replacement Phase 2 project CIP2220S to Water Meter Replacement
project CIP1918 and Pavement Preservation Manhole Upgrades project
CIP2508SNC .
74204300-69000
34254710-77420
74204300-43425
Fund Balance (217,301)
Transfer available/unspent funds from Forcemain Rehab Phase 3 project
CIP2305 to Water Meter Replacement project CIP1918.
74204300-69000
34254710-77420
74204300-43425
Fund Balance (291,971)
Increase appropriations to transfer funds from the fund balance and
projects CIP1711, CIP2220S, CIP2104 and CIP2305 as listed above to the
Water Meter Replacement project CIP1918.
74304300-69000
34254710-77430
74304300-43425
Fund Balance 1,939,185
Increase appropriations on the Pavement Preservation Manhole
Upgrades project CIP2508SNC to receive the transferred funds above
from A Section Commerce Sewer Line Replacement Phase 2 project
CIP2220S.
74214305-65500
34254710-77421
74214305-43425
Fund Balance 30,000
1,028,171$
Enterprise Fund - Recycled Water Utility (Fund 3440)
Increase appropriations to transfer funds to F7441 Recycled Water Non-
Capital Project fund for the Alicia Park Irrigation Replacement Project
CIP2605RNC
34404730-77441
74414305-65500
74414305-43440
Fund Balance 345,093
345,093$
Enterprise Fund - Recycled Water Capital Preservation (Fund
3445)
Increase appropriations to transfer funds to F7441 Recycled Water Non-
Capital Project fund for the Alicia Park Irrigation Replacement Project
CIP2605RNC
34454730-77441
74414305-65500
74414305-43445
Fund Balance 104,907
104,907$
Enterprise Fund - Water Capacity (Fund 3436)
Increase appropriations to replenish CIP2102 Water Tank #9 project
funding that was previously swapped to CIP1919 Well Pump/Motor
Replacement project in FY24-25. Appropriations are needed to return
the remaining cash to the Water Capacity Fund.
74304300-69000
34364720-77430
74304300-43436
Fund Balance 53,800
53,800$
Total net appropriations
Total net appropriations
Total net appropriations
Total net appropriations