HomeMy WebLinkAbout2026/09/22 City Council Resolution 2026-080 RESOLUTION NO. 2026-080
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ROHNERT PARK
AUTHORIZING THE CITY MANAGER TO CREATE A NEW CAPITAL
IMPROVEMENT PROGRAM PROJECT FOR THE WELL NOS. 14,33,35,AND 40
REHABILITATION PROJECT (PROPOSED PROJECT NO. CIP2707WNC),
AUTHORIZE THE CITY MANAGER TO EXECUTE CONSTRUCTION CONTRACT
CHANGE ORDER NO. 4 WITH WEEKS DRILLING AND PUMP CO., IN THE
AMOUNT OF $143,524.09,AUTHORIZE THE CITY MANAGER TO APPROVE
ADDITIONAL CHANGE ORDERS UP TO A CUMULATIVE AMOUNT OF $36,348.33
(10%),AUTHORIZE A BUDGET AMENDMENT TRANSFERRING $219,959.22 FROM
F3430 WATER UTILITY CONTRACT- OUTSIDE SERVICES TO THE
CORRESPONDING TRANSFER ACCOUNTS ON THE PROJECT,AUTHORIZE
ADDITIONAL TRANSFER APPROPRIATIONS OF $200,000 FROM F3430 WATER
UTILITY FUND BALANCE AND THE NON-CAPITAL WATER PROJECT FUND,
AND FIND THE PROJECT EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL
QUALITY ACT (CEQA) PURSUANT TO CEQA GUIDELINES SECTIONS 15301
(EXISTING FACILITIES) AND 15302 (REPLACEMENT OR RECONSTRUCTION) (14
CAL. CODE REGS. §§ 15301 AND 15302)
WHEREAS, Well Nos. 33, 35, and 40 are located along Camino Colegio and East Cotati
Avenue, and Well No. 14 is located on Evonne Avenue; and
WHEREAS, the groundwater well pumps and motors have reached the end of their
useful life and/or failed, requiring rehabilitation to return the wells to drinking water production;
and
WHEREAS,the Well Nos. 14, 33, 35, and 40 Rehabilitation Project("Project") consists
of rehabilitating the wells, including replacement of pumps, motors, damaged column pipe, well
screens, and casings; and
WHEREAS, staff recommends creating a new Capital Improvement Program ("CIP")
Project, Proposed Project No. CIP2707WNC, to consolidate Project expenses and improve
budget tracking; and
WHEREAS, on June 8, 2026, the City executed a Construction Contract with Weeks
Drilling and Pump Co. ("Weeks Drilling") in the amount of$136,556.58 for construction of the
Project; and
WHEREAS, the original Construction Contract and Contract Change Order Nos. 1-3,
totaling $219,959.22, are currently encumbered from F3430 Water Utility Fund, Contract-
Outside Services; and
WHEREAS, video inspections and deviation surveys completed after removal of the
pumps, motors, and column pipe identified numerous holes in the existing well casings at Well
Nos. 33, 35, and 40, and the deviation survey determined that installation of PVC liner is feasible
to address the casing conditions; and
WHEREAS, staff recommends authorizing the City Manager to execute Construction
Contract Change Order No. 4 ("CCO No. 4") with Weeks Drilling in the amount of$143,524.09
for the necessary PVC liner work and an eight-hour pump test, bringing the revised total contract
amount to $363,483.31; and
WHEREAS, staff recommends transferring $219,959.22 from F3430 Water Utility Fund
Contract-Outside Services to the transfer accounts on the new CIP Project and appropriating an
additional $200,000 from F3430 Water Utility Fund Balance to the non-capital water project
fund to fund CCO No. 4, an additional construction contingency of$36,348.33 (10%revised
total contract value), and staff time; and
NOW, THEREFORE,BE IT RESOLVED by the City Council of the City of Rohnert
Park that it does hereby authorize and approve as follows:
1. The above recitals are true and correct and material to this Resolution.
2. In making its findings the City Council relied upon and hereby incorporates by reference
all of the correspondence, staff reports and all other related materials.
3. The City Council finds that the additional work authorized by Contract Change Order No.
4 arises from unforeseen subsurface conditions discovered during performance of the
existing Construction Contract, is within the general scope of and integral to the
competitively bid Project and is authorized as a modification of the Construction Contract
as provided in the contract and under applicable law, consistent with Public Contract
Code section 7105.
4. The City Council finds that the Project is categorically exempt from the requirements of
the California Environmental Quality Act("CEQA")pursuant to CEQA Guidelines
sections 15301 (Existing Facilities) and 15302 (Replacement or Reconstruction), (14 Cal.
Code Regs. §§ 15301, 15302), and directs staff to file a notice of exemption with the
Sonoma County Clerk—Recorder.
5. The City Council hereby directs the Finance Director to create a new CIP Project for the
Well Nos. 14, 33, 35, and 40 Rehabilitation Project, CIP2707WNC.
6. The Finance Director is authorized to increase and transfer out appropriations in the total
amount of$419,959.22 from F3430 Water Utility Fund to F7431 Water Non-Capital
Projects Fund and increase and transfer in the appropriations to F7431 Water Non-Capital
Projects Fund and appropriate to the Project.
7. The City Manager is hereby authorized and directed to execute Contract Change Order
No. 4 with Weeks Drilling and Pump Co. in substantially similar form to Exhibit A,
which is attached hereto and incorporated by this reference, for the sum of one hundred
forty-three thousand, five hundred twenty-four dollars and nine cents ($143,524.09) for
the additional work on the Project in accordance with the bid documents and applicable
law upon submission by Weeks Drilling and Pump Co. of all documents required
pursuant to the Project bid documents.
8. The City Manager is hereby authorized to approve up to $36,348.33(10% of the revised
total contract amount) in additional construction contract change orders.
9. This Resolution shall become effective immediately.
Resolution 2026-080
Page 2 of 3
10. All portions of this Resolution are severable. Should any individual component of this
Resolution be adjudged to be invalid and unenforceable by a body of competent
jurisdiction, then the remaining Resolution portions shall continue in full force and effect,
except as to those Resolution portions that have been adjudged invalid. The City Council
of the City of Rohnert Park hereby declares that it would have adopted this Resolution
and each section, subsection, clause, sentence,phrase and other portion thereof,
irrespective of the fact that one or more section, subsection, clause, sentence, phrase or
other portion may be held invalid or unconstitutional.
BE IT FURTHER RESOLVED that the City Manager, or her designee, is hereby
authorized and directed to execute documents pertaining to same for and on behalf of the City of
Rohnert Park.
DULY AND REGULARLY ADOPTED BY THE CITY COUNCIL OF THE CITY
OF ROHNERT PARK ON this 22"a day of September, 2026.
CITY OF ROHNERT PARK
ATTEST: it anborn, Mayor
Sylvia Lopez Cuevas, City Clerk
PR AS TO FORM•
c elle . enyon, City Attorney
Attachment: Exhibit A
ADAMS: GIUDICE: /iill/. RODRIGUEZ: ELWARD: SANBORN:
ES: (T NO (may) ABSEN ( ABSTAIN::�
Resolution 2026-080
Page 3 of 3
Contract # 326000315
DATE:9/22/2026
Item Description Amount
1 PCO#5 Well Nos. 33, 35, and 40 PVC Liner and Pump Testing $143,524.09
Original Contract Amount:$136,556.58
CCO #1:$33,032.38
CCO #2:$13,900.00
CCO #3:$36,470.26
CCO #4:$143,524.09
Revised Contract Amount:$363,483.31
Original Contract Completion Date:9/25/2026
Contract Time Adjustment: 35 New Contract Completion Date:10/30/2026
(Calendar Days)
Recommended by: ______________________________________________________
Julian De Anda, City Engineer Date
Recommended by: ______________________________________________________
Laura Luchini, CIP Program Manager Date
Recommended by: ______________________________________________________
Kelsey Nguyen, Project Coordinator Date
Approved by: ______________________________________________________
Marcela Piedra, City Manager Date
Approved by: ______________________________________________________
Tracy Rankin, Risk Manager Date
Approved by: ______________________________________________________
Betsy Howze, Finance Director Date
ATTEST: __________________________________________________
City Clerk
APPROVED AS TO FORM: __________________________________
Michelle Marchetta Kenyon, City Attorney
Accepted by: ___________________________________________________________
Date
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is
approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services
necessary for the work above specified, and will accept as full payment therefore the prices shown above.
The City Manager's Signing Authority for Change Order No. 4 in the amount of $143,524.09 was approved by the City Council at their
meeting on September 22, 2026 by Resolution No. 2026-________.
Item #1: Video inspections of Well Nos. 33, 35, and 40 discovered multiple holes throughout the casing causing issues with well depth
and sediment entry. A deviation survey was conducted to determine the exact path and deviation of the drill hole. After reviewing the
survey results, the City and Contractor have determined that a PVC liner is the next appropriate step. The liner will significantly increase
the lifespan of the well. An eight hour pump test will also be conducted to confirm the wells' performance after the PVC liner is installed.
Weeks Drilling and Pump Co., Phillip Thompson, CFO
CITY OF ROHNERT PARK
600 Enterprise Drive Rohnert Park CA 94928
PH: (707) 588-3300 FAX: (707) 588-3333
Well Nos. 14, 33, 35, and 40 Rehabilitation Project
The total of Contract Change Order Nos. 1, 2, 3 and 4 are 166.2% of the original contract.
*********************************************************************************************************************
CONTRACT CHANGE ORDER NO. 4
TO: WEEKS DRILLING AND PUMP CO.
You are herby directed to make the herein described changes from the plans and specifications or do the following described work not
included in the plans and specifications of this contract. All new work herein described shall be done in accordance with the applicable
provisions of the plans and specifications, except as modified by this contract change order. NOTE: This change order is valid when
signed on behalf of the Owner.
Justification:
The adjustments to the Contract Price and Contract Time in this Change Order include all costs, including direct, indirect, consequential,
and overhead (field and home office) costs, related to the Change described above. By signing this Change Order, Contractor agrees to
accept the adjustment to the Contract Price, calculated as provided above, and the adjustment of the Contract Time, as payment in full
for all costs, including direct, indirect, consequential, and overhead (field and home office) costs, related to the Changes described
above. Except as amended by this Contract Change Order, the Contract shall remain in full force and effect.
Docusign Envelope ID: B3DFBF3B-0FA1-8C4A-8117-CB70E702EBAD
9/14/2026
CHANGE ORDER
WDPQ7322QUOTE #
DATE Jul 10, 2026
Salesperson Joshua Moore
6100 Highway 12 / P.O. Box 176,
Sebastopol, CA 95473
Contractor's License:177681
To Site:Wells, 33,35 & 40
Rohnert Park, Ca 94928City of Rohnert Park
600 Enterprise Drive
Rohnert Park, Ca 94928
APN:
Phone:707.588.3303
Email:
Scope of Work:
Change Order
Well #33
Install Flush Joint SDR17 Liner to Bottom of Deviated Section of Well Casing--Match Pref Intervals
Install Test Pump and Conduct an 8hr Well Yield test and Record and Provide Data to City of Rohnert Park
Well #35
Install Mild Steel Patch at 150ft to 153.6ft--proceed with Air Lift Development
Install SDR17 8" Liner to Bottom as Applicable--Match pref Intervals
Install Test Pump and Conduct an 8hr Well Yield test and Record and Provide Data to City of Rohnert Park
Well #40
Install SDR17 8" Liner to Bottom as Applicable--Match pref Intervals
Introduce NuWell-110 Acid Treatment-Let Sit 48hr and neutralize with Soda Ash
Proceed with Open Air Lift Development
Install Test Pump and Conduct an 8hr Well Yield test and Record and Provide Data to City of Rohnert Park
QTY DESCRIPTION UNIT PRICE TOTAL PRICE
$31,690.00Liner for Well 33
160 $56.00 $8,960.00Blank 8" Flush Joint Casing SDR17 8x20ft
Created on 08/20/26 13:06:43 by Joshua Moore
1 of 10
Docusign Envelope ID: B3DFBF3B-0FA1-8C4A-8117-CB70E702EBAD
QTY DESCRIPTION UNIT PRICE TOTAL PRICE
200 $64.00 $12,800.00Perf 8" Flush Joint Casing SDR17 8x20ft
1 $200.00 $200.008" Cap
1 $250.00 $250.00Rig Charge
1 $9,480.00 $9,480.00Labor
$9,000.00Pump Testing 8hr
1 $1,250.00 $1,250.00Test Pump Rental Equipment
1 $200.00 $200.00Rig Charge
1 $7,550.00 $7,550.00Labor
$48,477.50Liner for Well 35
1 $18,187.50 $18,187.50Mild Steel Liner Patch 150.1-153.6
140 $56.00 $7,840.00Blank 8" Flush Joint Casing SDR17 8x20ft
180 $64.00 $11,520.00Perf 8" Flush Joint Casing SDR17 8x20ft
1 $200.00 $200.008" Cap
1 $250.00 $250.00Rig Charge
1 $10,480.00 $10,480.00Labor
$9,000.00Pump Testing 8hr
1 $1,250.00 $1,250.00Test Pump Rental Equipment
1 $200.00 $200.00Rig Charge
1 $7,550.00 $7,550.00Labor
$31,554.52Liner for Well 40
280 $48.00 $13,440.00Blank 8" Flush Joint Casing SDR17 6.9x20ft
120 $58.00 $6,960.00Perf 8" Flush Joint Casing SDR17 6.9x20ft
1 $200.00 $200.008" Cap
1 $100.00 $100.00NuWell-110 Treatment
2 $62.26 $124.52Soda Ash (Sold by the bag)
1 $250.00 $250.00Rig Charge
Created on 08/20/26 13:06:43 by Joshua Moore
2 of 10
Docusign Envelope ID: B3DFBF3B-0FA1-8C4A-8117-CB70E702EBAD
QTY DESCRIPTION UNIT PRICE TOTAL PRICE
1 $10,480.00 $10,480.00Labor
$9,000.00Pump Testing 8hr
1 $1,250.00 $1,250.00Test Pump Rental Equipment
1 $200.00 $200.00Rig Charge
1 $7,550.00 $7,550.00Labor
SUBTOTAL $138,722.02This change order will be billed:
PREVAILING W AGE SALES TAX $4,802.07
TOTAL $143,524.09
Notes
Important Notice:
W eeks Drilling and Pump Company, Contractor or "we" or "us" proposes to furnish equipment, material, and labor in accordance with the
specifications above. The undersigned, Buyer, or "you" or "your", hereby accepts the proposal and authorizes the work to be performed, and
acknowledges having read the attached Estimate & Contract Terms and Conditions of this contract and having received a copy of the "Notice to
Owner" (attached).
To accept this quotation, sign here and return:
Print Name:Email:
Salesperson Signature:Email:
Created on 08/20/26 13:06:43 by Joshua Moore
3 of 10
Docusign Envelope ID: B3DFBF3B-0FA1-8C4A-8117-CB70E702EBAD